Quatation Plumbing Kamaladi
Quatation Plumbing Kamaladi
1 White glazed earthernware European close coupled water closet. unit 1 set.
Commercial Type
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 3.00 960.00 2,880.00
Unskilled md 3.00 700.00 2,100.00
Total - A 4,980.00
B Materials
White Glazed European water closet, bakelite seat
cover no 1.00 20,389.00 20,389.00
15 mm. CP Angular stop cock no 1.00 1,244.00 1,244.00
15 mm PVC connector no 1.00 139.00 139.00
CP Nipple no 1.00 200.00 200.00
CP cap no 1.00 50.00 50.00
Screws, zinc oxide etc. Ls 50.00 50.00
Total - B 22,072.00
C Equipment
-
Total - C -
Total (A+B+C) : 27,052.00
D Add 15% Contractor's OHP 4,057.80
Total (A+B+C+D) : 31,109.80
Rate per set of White glazed earthernware European water closet = 31,110.00
Total - A 105.60
B Materials
150 x 150 mm. paper holder no 1.00 510.00 510.00
Total - B 510.00
C Equipment
-
Total - C -
Total (A+B+C) : 615.60
D Add 15% Contractor's OHP 92.34
Total (A+B+C+D) : 707.94
Rate per set of CP Paper Holder = 708.00
Page 3/16
6 150 x 150 mm. CP soap dish unit 1 no.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.11 960.00 105.60
Total - A 105.60
B Materials
150 x 150 mm. soap dish no 1.00 510.00 510.00
Total - B 510.00
C Equipment
-
Total - C -
Total (A+B+C) : 615.60
D Add 15% Contractor's OHP 92.34
Total (A+B+C+D) : 707.94
Rate per set of CP Soap Dish = 708.00
7 20mm. dia. 600 mm. long CP. Towel rail unit 1 no..
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.22 960.00 211.20
Total - A 211.20
B Materials
Towel rail with cap no 1.00 1240.00 1,240.00
Screws etc. LS 50.00 50.00
Total - B 1,290.00
C Equipment
-
Total - C -
Total (A+B+C) : 1,501.20
D Add 15% Contractor's OHP 225.18
Total (A+B+C+D) : 1,726.38
Rate per set of CP Towel Rail = 1,726.00
Total - A 211.20
B Materials
CP Commode Spray no 1.00 1798.00 1,798.00
Total - B 1,798.00
C Equipment
-
Total - C -
Total (A+B+C) : 2,009.20
D Add 15% Contractor's OHP 301.38
Total (A+B+C+D) : 2,310.58
Rate per set of Commode Spray = 2,311.00
Page 4/16
9 5 mm thick Looking Mirror size 900x600. unit 1 no.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.33 960.00 316.80
Total - A 316.80
B Materials
Looking mirror no 1.00 2970.00 2,970.00
Hinges, Screws LS 40.00 40.00
Total - B 3,010.00
C Equipment
-
Total - C -
Total (A+B+C) : 3,326.80
D Add 15% Contractor's OHP 499.02
Total (A+B+C+D) : 3,825.82
Rate per set of 900x600 looking mirror = 3,826.00
Total - A 336.00
B Materials
Looking mirror no 1.00 4620.00 4,620.00
Hinges, Screws LS 40.00 40.00
Total - B 4,660.00
C Equipment
-
Total - C -
Total (A+B+C) : 4,996.00
D Add 15% Contractor's OHP 749.40
Total (A+B+C+D) : 5,745.40
Rate per set of 1400x600 looking mirror = 5,745.00
Total - A 384.00
B Materials
Looking mirror no 1.00 4950.00 4,950.00
Hinges, Screws LS 40.00 40.00
Total - B 4,990.00
C Equipment
-
Total - C -
Total (A+B+C) : 5,374.00
D Add 15% Contractor's OHP 806.10
Total (A+B+C+D) : 6,180.10
Rate per set of 1500x600 looking mirror = 6,180.00
Page 5/16
12 5 mm thick Looking Mirror size 1700x600. unit 1 no.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.40 960.00 384.00
Total - A 384.00
B Materials
Looking mirror no 1.00 4488.00 4,488.00
Hinges, Screws LS 40.00 40.00
Total - B 4,528.00
C Equipment
-
Total - C -
Total (A+B+C) : 4,912.00
D Add 15% Contractor's OHP 736.80
Total (A+B+C+D) : 5,648.80
Rate per set of 1700x600 looking mirror = 5,649.00
Total - A 480.00
B Materials
Looking mirror no 1.00 4752.00 4,752.00
Hinges, Screws LS 40.00 40.00
Total - B 4,792.00
C Equipment
-
Total - C -
Total (A+B+C) : 5,272.00
D Add 15% Contractor's OHP 790.80
Total (A+B+C+D) : 6,062.80
Rate per set of 1800x600 looking mirror = 6,063.00
Total - B 280.00
C Equipment
-
Total - C -
Total (A+B+C) : 455.60
D Add 15% Contractor's OHP 68.34
Total (A+B+C+D) : 523.94
Rate per set of Multi floor trap = 524.00
Page 6/16
15 110 mm. PVC Cowl. Unit 1 no.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.17 960.00 163.20
Unskilled md 0.20 700.00 140.00
Total - A 303.20
B Materials
110mm. PVC Cowl no 1.00 87.00 87.00
Total - B 87.00
C Equipment
-
Total - C -
Total (A+B+C) : 390.20
D Add 15% Contractor's OHP 58.53
Total (A+B+C+D) : 448.73
Rate per set of 110mm PVC Cowl = 449.00
Total - B 3,200.00
C Equipment
-
Total - C -
Total (A+B+C) : 3,503.20
D Add 15% Contractor's OHP 525.48
Total (A+B+C+D) : 4,028.68
Rate per set of 110 mm. PVC Rain inlet with jali = 4,029.00
Total - A 33.20
B Materials
50mm dia CPVC pipe rm 1.00 677.00 677.00
CPVC fittings 40% of pipe cost 270.80
Sundries @ 50% of fittings cost 135.40
Total - B 1,083.20
C Equipment
-
Total - C -
Total (A+B+C) : 1,116.40
D Add 15% Contractor's OHP 167.46
Total (A+B+C+D) : 1,283.86
Rate per rm of 50mm CPVC pipe = 1,284.00
Page 7/16
17.1.2 40mm dia for hot and cold water. Unit 1 rmt.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.04 960.00 38.40
Unskilled md 0.04 700.00 28.00
Total - A 66.40
B Materials
40mm dia CPVC pipe rm 1.00 418.00 418.00
CPVC fittings 40% of pipe cost 167.20
Sundries @ 50% of fittings cost 83.60
Total - B 668.80
C Equipment
-
Total - C -
Total (A+B+C) : 735.20
D Add 15% Contractor's OHP 110.28
Total (A+B+C+D) : 845.48
Rate per rm of 40mm CPVC pipe = 845.00
17.1.3 32mm dia for hot and cold water. Unit 1 rmt.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.03 960.00 28.80
Unskilled md 0.03 700.00 21.00
Total - A 49.80
B Materials
32mm dia CPVC pipe rm 1.00 300.00 300.00
CPVC fittings 50% of pipe cost 150.00
Sundries @ 50% of fittings cost 75.00
Total - B 525.00
C Equipment
-
Total - C -
Total (A+B+C) : 574.80
D Add 15% Contractor's OHP 86.22
Total (A+B+C+D) : 661.02
Rate per rm of 32mm CPVC pipe = 661.00
17.1.4 25mm dia for hot and cold water. Unit 1 rmt.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.015 960.00 14.40
Unskilled md 0.015 700.00 10.50
Total - A 24.90
B Materials
25mm dia CPVC pipe rm 1.00 248.00 248.00
UPVC fittings 50% of pipe cost 124.00
Sundries @ 50% of fittings cost 62.00
Total - B 434.00
C Equipment
-
Total - C -
Total (A+B+C) : 458.90
D Add 15% Contractor's OHP 68.84
Total (A+B+C+D) : 527.74
Rate per rm of 25mm CPVC pipe = 528.00
Page 8/16
17.1.5 20mm dia for hot and cold water. Unit 1 rmt.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.01 960.00 9.60
Unskilled md 0.01 700.00 7.00
Total - A 16.60
B Materials
20mm dia CPVC pipe rm 1.00 178.00 178.00
UPVC fittings 50% of pipe cost 89.00
Sundries @ 50% of fittings cost 44.50
Total - B 311.50
C Equipment
-
Total - C -
Total (A+B+C) : 328.10
D Add 15% Contractor's OHP 49.22
Total (A+B+C+D) : 377.32
Rate per rm of 20mm CPVC pipe = 377.00
17.1.6 15mm dia for hot and cold water. Unit 1 rmt.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.01 960.00 9.60
Unskilled md 0.01 700.00 7.00
Total - A 16.60
B Materials
15mm dia CPVC pipe rm 1.00 133.00 133.00
UPVC fittings 50% of pipe cost 66.50
Sundries @ 50% of fittings cost 33.25
Total - B 232.75
C Equipment
-
Total - C -
Total (A+B+C) : 249.35
D Add 15% Contractor's OHP 37.40
Total (A+B+C+D) : 286.75
Rate per rm of 15mm CPVC pipe = 287.00
Total - A 384.00
B Materials
50mm. CPVC Ball Valve no 1.00 2117.00 2,117.00
Total - B 2,117.00
C Equipment
-
Total - C -
Total (A+B+C) : 2,501.00
D Add 15% Contractor's OHP 375.15
Total (A+B+C+D) : 2,876.15
Rate per set of 50mm. CPVC Ball Valve = 2,876.00
Page 9/16
18.2 40mm. CPVC Ball. Unit 1 no.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.25 960.00 240.00
Total - A 240.00
B Materials
40mm. CPVC Ball Valve no 1.00 1643.00 1,643.00
Total - B 1,643.00
C Equipment
-
Total - C -
Total (A+B+C) : 1,883.00
D Add 15% Contractor's OHP 282.45
Total (A+B+C+D) : 2,165.45
Rate per set of 40mm. CPVC Ball Valve = 2,165.00
Total - A 211.20
B Materials
32mm. CPVC Ball Valve no 1.00 1371.00 1,371.00
Total - B 1,371.00
C Equipment
-
Total - C -
Total (A+B+C) : 1,582.20
D Add 15% Contractor's OHP 237.33
Total (A+B+C+D) : 1,819.53
Rate per set of 32mm. CPVC Ball Valve = 1,820.00
18.4 25mm. CPVC Ball. Unit 1 no.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.22 960.00 211.20
Total - A 211.20
B Materials
25mm. CPVC Ball Valve no 1.00 588.00 588.00
Total - B 588.00
C Equipment
-
Total - C -
Total (A+B+C) : 799.20
D Add 15% Contractor's OHP 119.88
Total (A+B+C+D) : 919.08
Rate per set of 25mm. CPVC Ball Valve = 919.00
Page 10/16
18.5 20mm. CPVC Ball. Unit 1 no.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.11 960.00 105.60
Total - A 105.60
B Materials
20mm. CPVC Ball Valve no 1.00 486.00 486.00
Total - B 486.00
C Equipment
-
Total - C -
Total (A+B+C) : 591.60
D Add 15% Contractor's OHP 88.74
Total (A+B+C+D) : 680.34
Rate per set of 20mm. CPVC Ball Valve = 680.00
Total - A 303.20
B Materials
110mm. OD pipe 6 kg/cm2 rm 1.00 462.00 462.00
PVC fittings @ 50% of pipe cost 231.00
Jointing materials, nails, hooks, clamps etc. LS 231.00
Total - B 924.00
C Equipment
-
Total - C -
Total (A+B+C) : 1,227.20
D Add 15% Contractor's OHP 184.08
Total (A+B+C+D) : 1,411.28
Rate per rm of 110mm PVC pipe = 1,411.00
Page 11/16
19.1.2 75mm. OD Pipe (ID 63mm). Unit 1 rmt.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.11 960.00 105.60
Unskilled md 0.11 700.00 77.00
Total - A 182.60
B Materials
75mm. OD pipe 6 kg/cm2 rm 1.00 222.00 222.00
PVC fittings @ 50% of pipe cost 111.00
Jointing materials, nails, hooks, clamps etc. LS 111.00
Total - B 444.00
C Equipment
-
Total - C -
Total (A+B+C) : 626.60
D Add 15% Contractor's OHP 93.99
Total (A+B+C+D) : 720.59
Rate per rm of 75mm PVC pipe = 721.00
19.1.3 50mm. OD Pipe (ID 40mm). Unit 1 rmt.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled md 0.06 960.00 57.60
Unskilled md 0.10 700.00 70.00
Total - A 127.60
B Materials
50mm. OD pipe 6 kg/cm2 rm 1.00 99.00 99.00
PVC fittings @ 50% of pipe cost 49.50
Jointing materials, nails, hooks, clamps etc. LS 49.50
Total - B 198.00
C Equipment
-
Total - C -
Total (A+B+C) : 325.60
D Add 15% Contractor's OHP 48.84
Total (A+B+C+D) : 374.44
Rate per rm of 50mm PVC pipe = 374.00
Total - A 49.80
B Materials
63mm OD PPR pipe rm 1.00 820.00 820.00
PPR fittings 10% of pipe cost 82.00
Sundries @ 10% of fittings cost 8.20
Total - B 910.20
C Equipment
-
Total - C -
Total (A+B+C) : 960.00
D Add 15% Contractor's OHP 144.00
Total (A+B+C+D) : 1,104.00
Rate per rm of 63mm PPR pipe = 1,104.00
Page 12/16
20 HDPE vertical storage tank (2000 ltr.) Unit 1 no.
S.No. Particulars Unit Quantity Rate Amount
A Labourers 10% of material cost 2,400.00
Skilled
Unskilled
Total - A 2,400.00
B Materials
2000 liters roof tank no 1.00 24,000.00 24,000.00
Interconnection pipes and fittings @ 20% of material cost 4,800.00
Total - B 28,800.00
C Equipment
-
Total - C -
Total (A+B+C) : 31,200.00
D Add 15% Contractor's OHP 4,680.00
Total (A+B+C+D) : 35,880.00
Rate per no of 5000 liters roof tank = 35,880.00
21 Electric centrifugal water pump 35 lpm @ 22m head. Unit 1 set.
S.No. Particulars Unit Quantity Rate Amount
A Labourers
Skilled nos 3.00 960.00 2,880.00
Unskilled nos 3.00 700.00 2,100.00
Total - A 4,980.00
B Materials
Centrifugal water pump 40 lpm @ 18m head no 1.00 9465.00 9,465.00
Automatic motor operator upto 1 HP no 1.00 5665.00 5,665.00
Motor starter switch no 1.00 3398.00 3,398.00
Total - B 18,528.00
C Equipment
-
Total - C -
Total (A+B+C) : 23,508.00
D Add 15% Contractor's OHP 3,526.20
Total (A+B+C+D) : 27,034.20
Rate per pump set = 27,034.00
- 50 mm Rm 12
- 40 mm Rm 55
- 32 mm Rm 23
- 25 mm Rm 15
- 20 mm Rm 123
14 CPVC Ball Valve
- 50 mm No. 2
- 40 mm No. 4
- 32 mm No. 0
- 25 mm No. 0
- 20 mm No. 12
2000 litres capacity HDPE vertical water storage tank
15 complete with inter-connection, overflow, washout No. 2
and vents
Sub Total B:
C. SEWER AND WASTE WATER INSTALLATION
Page 16/16
Sub Total C:
Total A + B + C: