Work Instruction - Painting

This work instruction outlines the painting process. It assigns responsibilities to the project engineer, paint representative, and lead man for painting. It details that after surface preparation by blasters, the paint representative will inspect the surface and give approval to start painting. The lead man will then proceed with painting while the paint representative periodically inspects the work. Any issues will be addressed by coordinating with the project engineer. Upon satisfactory completion and final inspection, the painting process ends.

Uploaded by

Aaron Perez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
388 views1 page

Work Instruction - Painting

This work instruction outlines the painting process. It assigns responsibilities to the project engineer, paint representative, and lead man for painting. It details that after surface preparation by blasters, the paint representative will inspect the surface and give approval to start painting. The lead man will then proceed with painting while the paint representative periodically inspects the work. Any issues will be addressed by coordinating with the project engineer. Upon satisfactory completion and final inspection, the painting process ends.

Uploaded by

Aaron Perez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Work Instruction Title:

PAINTING
WI. Ref NO Effectivity Date: Rev. No.: Page Total:
WI-RAJT-21 09.01.2020 00 1/1
PURPOSE: : To Inform operation personnel on how to properly proceed with painting

SCOPE: : This procedure covers the standard workflow for painting.

Responsible Process flow Details


Project engineer
Paint representative
Lead man (painting) Start PROCESS

After the surface preparation is done by the


blasters the paint representative would inspect
the surface if it is ready for painting.
Inspection of surface
preparation Upon the go signal given by paint
representative the lead man can proceed with
painting from time to time the paint
representative would inspect the work done
accomplished by the painters any concern of
the paint representative should coordinate with
the project engineer for documentation
Was the surface
ready for
painting?
No

Tackle all the concern by


the paint representative
Painting

Inspection

Tackle all the concern by


No
the paint representative

Are the painting


in satisfactory
condition?

END

Prepared By: Reviewed and Approved By:

JOHN ANGELO D. TULIAO ALLEN JAMES C. TULIAO


Operations Head Director
REVISION HISTORY
No. Revision details: Effectivity Date:
0 Initial Issue 09.01.2020