Monthly Quality Assurance Report For August-13, Elf RVNL Dankuni
Monthly Quality Assurance Report For August-13, Elf RVNL Dankuni
A. CONTTROL CHART:
1 Concrete : cube Compressive strength Tests(Set) 5739 418 5739 418 As per IS: 456
Cement – Compressive Physical Tests at site Lab. And MTC for every batch and 3
3 25 1 25 1
strength,Fineness,Soundness,Sp. Gravity,Consistency Nos physical and chemical Test done from 3 rd party laboratory.
7 Binder Extraction Test N.A. There is no Bituminous work scope in contractual provision
N.A. N.A.
8 Pile- Load Test 20 4 20 4 1% of total pile
10 Welder's Qualification 35 0 35 0
Remarks
Sl. No. Activity Yes/ No
1 Weather aggregate grading is carried out daily No It is done per Truck basis
1 M35 48.74
2 04/07/13 Pile Cap D40 / Work shop 1 M35 37.63 CA1(40mm) - 768.000 Kg Type: OPC
1 M35 48.82
3 04/07/13 Pedestal B68 / Work shop 1 M35 37.63 CA2 (10mm)- 512.000 Kg Make: BHARAT SUPER
1 M35 48.00
1 M35 48.59
5 04/07/13 Pile B56P3 /Work shop 1 M35 37.18 W - 160.000 L Sp. Gr. 3.15
1 M35 47.75
1 M35 48.00
7 04/07/13 Pile Cap C48 / Work shop 1 M35 38.07 M20: C - 400 .00 Kg CA1: 40 mm
1 M35 45.87
8 05/07/13 Road Pavement (PCC) 1 M15 16.74 CA1(40mm) - 772.55 Kg Sp. Gr. 2.80
1 M15 24.52
1 M25 37.48
11 05/07/13 Pile Cap D46,D47 / Work shop 1 M35 36.00 W- 160.000 L Sp. Gr. 2.78
1 M35 45.83
1 M30 41.48
13 06/07/13 Road Pavement (PCC) 1 M15 16.44 M25: C- 410 Kg Sand: Zone – II (River)
1 M15 24.37
14 06/07/13 Tie Beam / Staff Quarter 1 M25 25.33 CA1(20 mm) 587.14 Kg River: Damodar, Burdwan.
1 M25 32.89
As per IS:456 Table 11
RCC Precast pipe line (1)Mean of the Group of 4 Non- 20.15 CA2(10mm) 587.14 Kg
15 06/07/13 1 M20 Sp. Gr. : 2.65
Overlapping Consecutive test results
1 M20 in N/mm2 up to M 15 Grade of 29.63
Concrete is ≥fck+0.825 x
16 06/07/13 Pedestal C46 / Work shop 1 M35 established standard deviation 38.07 FA - 746.24 Kg ADM: N. F. P.
( rounded off to nearest 0.5N/mm2)
1 M35 or fck + 3 N/mm2 which ever is 53.00
greater (2) Mean of the Group of 4
17 06/07/13 Pedestal C63 / Work shop 1 M35 38.07 N.A. W - 169.85 L Make: BASF
Non- Overlapping Consecutive test
results in N/mm2 M 20 or above 48.15
1 M35
Grade of Concrete is ≥fck+0.825 x
18 06/07/13 Tie Beam/ Sub Station 1 M30 established standard deviation 24.88 ADM : 3.28 Kg Brand : BASF Rehobuild, 916(CL)
( rounded off to nearest 0.5N/mm2)
1 M30 or fck + 4 N/mm2 which ever is 42.48
greater (3) As per Amend No. 3 of IS
19 06/07/13 Pile Cap D45 / Work shop 1 M35 456 : 2000 , against M 20 and 38.67 Sp.Gr: 1.16
above fck + 3 N/mm2 has adopted.
1 M35 48.79
20 06/07/13 Pile Cap B50 / Work shop 1 M35 37.33 M30: C -420 Kg Cement:
1 M35 48.74
1 M20 38.96
22 06/07/13 Pile Cap D 49 / Work shop 1 M35 37.18 CA2 (10mm)- 569.62 Kg Make: LAFARGE
1 M35 48.52
23 08/07/13 Pile Cap M69 / A.Building 1 M35 38.67 FA - 723.98 Kg Grade : PPC 33
1 M35 48.74
24 08/07/13 RCC Precast pipe line 1 M20 19.85 W - 168.000 L Sp. Gr. 2.90
1 M20 30.07
1 M20 38.37
1 M25 39.11
1 M35 48.30
29 08/07/13 Tie Beam/ Sub Station 1 M30 31.11 CA1(20mm)-594.64 Kg Type: OPC
1 M30 47.40 CA2(10mm)-594.64 Kg
1 M35 47.66
31 08/07/13 Pedestal B51 / Work shop 1 M35 38.07 W - 171.20 L Sp. Gr. 3.15
1 M35 48.30
1 M35 45.70
Sheet4
1 M30 40.89
1 M20 30.22
1 M30 40.44
1 M20 29.63
1 M35 46.81
38 09/07/13 Tie Beam c10,c11,c12 / Work shop 1 M35 38.22 ADM - 0.000 Kg
1 M35 46.81
1 M30 42.37
40 10/07/13 Tie Beam C13 / Work shop 1 M35 38.07 CA1(40mm) - 772.55 Kg
1 M35 46.51
41 10/07/13 Pile Cap B4 /Sub Station 1 M35 36.88 CA2 (10mm)- 515.04 Kg
1 M35 46.81
1 M35 48.10
1 M35 46.07
1 M35 47.11
1 M35 47.40
1 M30 41.03
As per IS:456 Table 11
(1)Mean of the Group of 4 Non- 27.26 CA2(10mm) 587.14 Kg
47 10/07/13 Tie Beam / A.Building 1 M30
Overlapping Consecutive test results
1 M30 in N/mm2 up to M 15 Grade of 41.92
Concrete is ≥fck+0.825 x
48 11/07/13 Column/ Staff Quarter 1 M20 established standard deviation 19.85 FA - 746.24 Kg
( rounded off to nearest 0.5N/mm2)
1 M20 or fck + 3 N/mm2 which ever is 29.63
greater (2) Mean of the Group of 4
49 11/07/13 Tie Beam / Work shop 1 M35 37.48 N.A. W - 169.85 L
Non- Overlapping Consecutive test
results in N/mm2 M 20 or above 46.81
1 M35
Grade of Concrete is ≥fck+0.825 x
50 11/07/13 Pile Cap / A.Building 1 M35 established standard deviation 37.03 ADM : 3.28 Kg
( rounded off to nearest 0.5N/mm2)
1 M35 or fck + 4 N/mm2 which ever is 47.78
greater (3) As per Amend No. 3 of IS
51 11/07/13 Pile Cap C39 / Work shop 1 M35 456 : 2000 , against M 20 and 37.92
above fck + 3 N/mm2 has adopted.
1 M35 46.44
1 M30 44.44
1 M30 40.29
54 12/07/13 RCC Precast pipe line 1 M20 20.89 CA2 (10mm)- 569.62 Kg
1 M20 29.93
1 M35 47.11
1 M35 46.07
1 M35 46.81
1 M20 28.89
1 M30 40.89
1 M35 46.42
1 M35 47.85
63 13/07/2013 Column/ Over Head Tank 1 M25 23.55 W - 171.20 L
1 M25 41.78
64 13/07/2013 Pile Cap B71 / Work shop 1 M35 37.18 ADM - 5.564 Kg
1 M35 46.82
Page 3
Sheet4
STRUCTURES LIMITED
SIL/QA/MREP/03/Date21.12.2009
SHEET : 03 OF 3/2
Remarks
Cement:
Type: OPC
Grade : 43
CA1: 40 mm
CA2 : 10 mm
ADM: N. F. P.
Make: BASF
Sp.Gr: 1.16
Cement:
Type: PPC
Make: LAFARGE
Grade : PPC 33
Cement:
Type: OPC
Grade : 43
Page 4
Sheet5
1 M30 42.37
1 M20 42.52
1 M30 42.37
68 13/07/2013 Pile Cap D50 / Work shop 1 M35 38.96 FA - 640.000 Kg
1 M35 48.30
1 M35 46.67
1 M35 48.15
1 M35 46.67
1 M35 46.07
73 15/07/13 Pile Cap B3 / Work shop 1 M35 37.62 CA2 (10mm)- 515.04 Kg
1 M35 49.19
1 M35 47.86
1 M35 46.71
76 15/07/13 Pile Cap C65 / Work shop 1 M35 38.37 ADM - 4.000 Kg
1 M35 47.03
1 M35 43.26
78 15/07/13 Tie Beam / Work shop 1 M35 38.22 CA1(20 mm) 587.14 Kg
1 M35 46.07
As per IS:456 Table 11
Pile A5 / Traverser (1)Mean of the Group of 4 Non- 38.07 CA2(10mm) 587.14 Kg
79 16/07/13 1 M35
Overlapping Consecutive test results
1 M35 in N/mm2 up to M 15 Grade of 48.14
Concrete is ≥fck+0.825 x
80 16/07/13 Roof Slab / A.Building 1 M30 established standard deviation 28.59 FA - 746.24 Kg
( rounded off to nearest 0.5N/mm2)
1 M30 or fck + 3 N/mm2 which ever is 43.73
greater (2) Mean of the Group of 4
81 16/07/13 Road Pavement (PQC) 1 M30 27.55 N.A. W - 169.85 L
Non- Overlapping Consecutive test
results in N/mm2 M 20 or above 41.23
1 M30
Grade of Concrete is ≥fck+0.825 x
82 16/07/13 RCC Precast pipe line 1 M20 established standard deviation 20.44 ADM : 3.28 Kg
( rounded off to nearest 0.5N/mm2)
1 M20 or fck + 4 N/mm2 which ever is 31.11
greater (3) As per Amend No. 3 of IS
83 17/07/13 Pile B2 / Traverser 1 M35 456 : 2000 , against M 20 and 38.22
above fck + 3 N/mm2 has adopted.
1 M35 47.71
1 M35 48.45
1 M25 39.26
86 17/07/13 Pedestal D62 / Work shop 1 M35 38.37 CA2 (10mm)- 569.62 Kg
1 M35 46.51
1 M35 46.96
1 M35 47.26
1 M35 47.55
1 M30 40.00
1 M35 46.27
92 18/07/13 Pile Cap D43 / Work shop 1 M35 37.92 M35: C - 428 Kg
1 M35 47.92
1 M30 40.15
1 M35 46.44
1 M35 47.11
Page 5
Sheet5
Remarks
Cement:
Type: OPC
Grade : 43
CA1: 40 mm
CA2 : 10 mm
ADM: N. F. P.
Make: BASF
Sp.Gr: 1.16
Cement:
Type: PPC
Make: LAFARGE
Grade : PPC 33
Cement:
Type: OPC
Grade : 43
Page 6
Sheet6
1 M30 41.85
1 M30 39.41
99 18/07/13 Pedestal D64 / Work shop 1 M35 38.22 CA2 (10mm)- 512.000 Kg
1 M35 46.52
100 18/07/13 Pedestal B71 / Work shop 1 M35 37.92 FA - 640.000 Kg
1 M35 45.63
1 M35 47.75
1 M35 47.01
1 M35 45.67
1 M35 46.52
105 19/07/13 Tie Beam / Work shop 1 M35 37.33 CA2 (10mm)- 515.04 Kg
1 M35 46.22
106 19/07/13 Pile Cap D72 / Work shop 1 M35 39.25 FA - 658.53 Kg
1 M35 46.37
1 M35 45.63
1 M35 46.91
1 M35 46.32
110 20/07/13 Road Pavement (PQC) 1 M30 27.70 CA1(20 mm) 587.14 Kg
1 M30 40.63
As per IS:456 Table 11
Pile Cap D41 / Work shop (1)Mean of the Group of 4 Non- 37.78 CA2(10mm) 587.14 Kg
111 20/07/13 1 M35
Overlapping Consecutive test results
1 M35 in N/mm2 up to M 15 Grade of 45.7
Concrete is ≥fck+0.825 x
112 20/07/13 Pile Cap Q5A / A.Building 1 M35 established standard deviation 38.07 FA - 746.24 Kg
( rounded off to nearest 0.5N/mm2)
1 M35 or fck + 3 N/mm2 which ever is 46.22
greater (2) Mean of the Group of 4
113 20/07/13 Tie Beam / A.Building 1 M30 26.22 N.A. W - 169.85 L
Non- Overlapping Consecutive test
results in N/mm2 M 20 or above 41.48
1 M30
Grade of Concrete is ≥fck+0.825 x
114 20/07/13 Pedestal C49 / Work shop 1 M35 established standard deviation 38.52 ADM : 3.28 Kg
( rounded off to nearest 0.5N/mm2)
1 M35 or fck + 4 N/mm2 which ever is 45.48
greater (3) As per Amend No. 3 of IS
115 20/07/13 Pile C14 / Traverser 1 M35 456 : 2000 , against M 20 and 38.66
above fck + 3 N/mm2 has adopted.
1 M35 46.5
116 20/07/13 Tie Beam /Sub Station 1 M30 27.26 M30: C -420 Kg
1 M30 40.44
1 M35 45.48
118 20/07/13 Tie Beam / Work shop 1 M35 38.37 CA2 (10mm)- 569.62 Kg
1 M35 46.37
1 M35 45.97
1 M35 47.80
121 22/07/13 Pedestal Jacketing / Work shop 1 M35 37.33 ADM - 4.20 Kg
1 M35 52
1 M30 41.63
1 M35 47.34
124 22/07/13 Tie Beam / Work shop 1 M35 37.92 M35: C - 428 Kg
1 M35 47.56
1 M35 48 CA2(10mm)-594.64 Kg
1 M35 48.25
1 M35 50.00
1 M20 35.11
Page 7
Sheet6
Remarks
Cement:
Type: OPC
Grade : 43
CA1: 40 mm
CA2 : 10 mm
ADM: N. F. P.
Make: BASF
Sp.Gr: 1.16
Cement:
Type: PPC
Make: LAFARGE
Grade : PPC 33
Cement:
Type: OPC
Grade : 43
Page 8
Sheet7
1 M30 42.81
1 M30 44.44
131 24/07/13 Grade Beam / A.Building 1 M30 29.48 CA2 (10mm)- 512.000 Kg
1 M30 39.85
132 24/07/13 Pile B16 / Traverser 1 M35 38.22 FA - 640.000 Kg
1 M35 45.58
1 M35 48.00
134 24/07/13 Pedestal B31 / Work shop 1 M35 40.00 ADM - 0.000 Kg
1 M35 50.60
135 24/07/13 Tie Beam / Work shop 1 M35 37.78 M20: C - 400 .00 Kg
1 M35 46.82
136 24/07/13 Pile Cap A4 / Sub Station 1 M35 38.07 CA1(40mm) - 772.55 Kg
1 M35 53.18
137 24/07/13 Pile A15 / Traverser 1 M35 38.37 CA2 (10mm)- 515.04 Kg
1 M35 45.53
1 M35 47.01
1 M20 28.69
140 25/07/13 Pedestal Jacketing / Work shop 1 M35 38.81 ADM - 4.000 Kg
1 M35 45.77
1 M35 45.70
142 25/07/13 Pile Cap D44 / Work shop 1 M35 37.63 CA1(20 mm) 587.14 Kg
1 M35 46.46
As per IS:456 Table 11
Pedestal Jacketing / Work shop (1)Mean of the Group of 4 Non- 37.78 CA2(10mm) 587.14 Kg
143 25/07/13 1 M35
Overlapping Consecutive test results
1 M35 in N/mm2 up to M 15 Grade of 45.92
Concrete is ≥fck+0.825 x
144 25/07/13 Pile C10 / Traverser 1 M35 established standard deviation 38.22 FA - 746.24 Kg
( rounded off to nearest 0.5N/mm2)
1 M35 or fck + 3 N/mm2 which ever is 46.66
greater (2) Mean of the Group of 4
145 25/07/13 Grade Beam / A.Building 1 M30 28.30 N.A. W - 169.85 L
Non- Overlapping Consecutive test
results in N/mm2 M 20 or above 41.03
1 M30
Grade of Concrete is ≥fck+0.825 x
146 26/07/13 Column / A.Building 1 M30 established standard deviation 28.00 ADM : 3.28 Kg
( rounded off to nearest 0.5N/mm2)
1 M30 or fck + 4 N/mm2 which ever is 39.41
greater (3) As per Amend No. 3 of IS
147 26/07/13 Column / Sub Station 1 M30 456 : 2000 , against M 20 and 28.89
above fck + 3 N/mm2 has adopted.
1 M30 38.52
1 M30 39.40
1 M35 44.89
150 26/07/13 Pedestal B27 / Work shop 1 M35 37.33 CA2 (10mm)- 569.62 Kg
1 M35 46.67
1 M35 46.42
1 M35 46.81
153 27/07/13 Pedestal C65 / Work shop 1 M35 37.18 ADM - 4.20 Kg
1 M35 45.03
1 M35 46.32
1 M20 28.15
1 M30 41.63
1 M30 41.18
1 M30 40.44
160 29/07/13 Pedestal D65 / Work shop 1 M35 38.08 ADM - 5.564 Kg
1 M35 46.37
Page 9
Sheet7
Remarks
Cement:
Type: OPC
Grade : 43
CA1: 40 mm
CA2 : 10 mm
ADM: N. F. P.
Make: BASF
Sp.Gr: 1.16
Cement:
Type: PPC
Make: LAFARGE
Grade : PPC 33
Cement:
Type: OPC
Grade : 43
Page 10
Sheet8
1 M30 41.78
162 29/07/13 Pedestal starter / Work shop 1 M35 38.81 CA1(40mm) - 768.000 Kg
1 M35 46.22
163 30/07/13 Pedestal D18 / Work shop 1 M35 38.81 CA2 (10mm)- 512.000 Kg
1 M35 46.23
164 30/07/13 Pile B63P1 / Work shop 1 M35 38.81 FA - 640.000 Kg
1 M35 46.86
1 M35 47.15
166 30/07/13 Pedestal D44 / Work shop 1 M35 38.07 ADM - 0.000 Kg
1 M35 46.66
167 30/07/13 Pedestal C66 / Work shop 1 M35 38.96 M20: C - 400 .00 Kg
1 M35 45.52
168 30/07/13 Tie Beam / Work shop 1 M35 37.77 CA1(40mm) - 772.55 Kg
1 M35 46.82
169 30/07/13 Pedestal D66 / Work shop 1 M35 37.18 CA2 (10mm)- 515.04 Kg
1 M35 46.82
1 M35 46.37
1 M35 47.41
1 M30 44.44
1 M30 44.44
1 M30 43.26
As per IS:456 Table 11
(1)Mean of the Group of 4 Non- 27.11 CA2(10mm) 587.14 Kg
175 31/07/13 Grade Beam / A.Building 1 M30
Overlapping Consecutive test results
1 M30 in N/mm2 up to M 15 Grade of 43.11
Concrete is ≥fck+0.825 x
176 31/07/13 Pile A58P1 / Work shop 1 M35 established standard deviation 37.78 FA - 746.24 Kg
( rounded off to nearest 0.5N/mm2)
1 M35 or fck + 3 N/mm2 which ever is 47.49
greater (2) Mean of the Group of 4
177 31/07/13 Pile B62P3 / Work shop 1 M35 38.82 N.A. W - 169.85 L
Non- Overlapping Consecutive test
results in N/mm2 M 20 or above 47.11
1 M35
Grade of Concrete is ≥fck+0.825 x
178 31/07/13 Column / Sub station 1 M30 established standard deviation 29.63 ADM : 3.28 Kg
( rounded off to nearest 0.5N/mm2)
1 M30 or fck + 4 N/mm2 which ever is 43.99
greater (3) As per Amend No. 3 of IS
179 31/07/13 Pedestal Jacketing / Work shop 1 M35 456 : 2000 , against M 20 and 39.26
above fck + 3 N/mm2 has adopted.
1 M35 47.10
180 31/07/13 RCC Precast pipe line 1 M20 21.67 M30: C -420 Kg
1 M20 30.36
1 M35 47.11
182 31/07/13 Tie Beam / Work shop 1 M35 38.51 CA2 (10mm)- 569.62 Kg
1 M35 47.55
1 M35 47.11
1 M35 47.65
185 01/08/13 Pile A59P1 / Work shop 1 M35 38.07 ADM - 4.20 Kg
1 M35 47.18
1 M35 45.33
1 M35 47.50
188 01/08/13 Pedestal D47 / Work shop 1 M35 37.92 M35: C - 428 Kg
1 M35 46.07
1 M35 46.37
191 01/08/13 Column/ Over Head Tank 1 M25 25.92 W - 171.20 L
1 M25 35.85
192 01/08/13 Pedestal C45 / Work shop 1 M35 38.96 ADM - 5.564 Kg
1 M35 46.89
Page 11
Sheet8
Remarks
Cement:
Type: OPC
Grade : 43
CA1: 40 mm
CA2 : 10 mm
ADM: N. F. P.
Make: BASF
Sp.Gr: 1.16
Cement:
Type: PPC
Make: LAFARGE
Grade : PPC 33
Cement:
Type: OPC
Grade : 43
Page 12
Sheet9
193 01/08/13 Pile B58P1 / Work shop 1 M35 38.22 M15: C - 320.00 Kg
1 M35 46.22
194 01/08/13 Lift Wall / A.Building 1 M30 29.92 CA1(40mm) - 768.000 Kg
1 M30 41.48
195 02/08/13 Pile B63P4 / Work shop 1 M35 37.63 CA2 (10mm)- 512.000 Kg
1 M35 46.96
196 02/08/13 Pile A58P2 / Work shop 1 M35 39.26 FA - 640.000 Kg
1 M35 48.14
1 M35 46.81
198 02/08/13 Pedestal B33 / Work shop 1 M35 38.37 ADM - 0.000 Kg
1 M35 47.50
199 02/08/13 Pile B61P2 / Work shop 1 M35 39.11 M20: C - 400 .00 Kg
1 M35 48.40
1 M30 42.96
201 03/08/13 Grade Beam / A.Building 1 M30 27.25 CA2 (10mm)- 515.04 Kg
1 M30 41.93
1 M35 45.04
1 M35 46.86
204 03/08/13 Column/ Over Head Tank 1 M25 23.11 ADM - 4.000 Kg
1 M25 31.85
205 03/08/13 Sill Beam / Sub station 1 M30 27.55 M25: C- 410 Kg
1 M30 42.67
206 03/08/13 Column / Sub station 1 M30 28.00 CA1(20 mm) 587.14 Kg
1 M30 43.26
As per IS:456 Table 11
Pedestal D31 / Work shop (1)Mean of the Group of 4 Non- 38.96 CA2(10mm) 587.14 Kg
207 03/08/13 1 M35
Overlapping Consecutive test results
1 M35 in N/mm2 up to M 15 Grade of 45.63
Concrete is ≥fck+0.825 x
208 03/08/13 Column / A.Building 1 M30 established standard deviation 28.30 FA - 746.24 Kg
( rounded off to nearest 0.5N/mm2)
1 M30 or fck + 3 N/mm2 which ever is 43.11
greater (2) Mean of the Group of 4
209 03/08/13 Pile B63P3 / Work shop 1 M35 38.07 N.A. W - 169.85 L
Non- Overlapping Consecutive test
results in N/mm2 M 20 or above 47.06
1 M35
Grade of Concrete is ≥fck+0.825 x
established standard deviation ADM : 3.28 Kg
( rounded off to nearest 0.5N/mm2)
or fck + 4 N/mm2 which ever is
greater (3) As per Amend No. 3 of IS
456 : 2000 , against M 20 and
above fck + 3 N/mm2 has adopted.
M30: C -420 Kg
CA1(20mm)-569.62 Kg
FA - 723.98 Kg
W - 168.000 L
ADM - 4.20 Kg
M35: C - 428 Kg
CA1(20mm)-594.64 Kg
CA2(10mm)-594.64 Kg
FA - 694.83 Kg
W - 171.20 L
ADM - 5.564 Kg
Page 13
Sheet9
Remarks
Cement:
Type: OPC
Grade : 43
CA1: 40 mm
CA2 : 10 mm
ADM: N. F. P.
Make: BASF
Sp.Gr: 1.16
Cement:
Type: PPC
Make: LAFARGE
Grade : PPC 33
Cement:
Type: OPC
Grade : 43
Page 14