1. Fice Solution Cons. Inc. provides a quotation for a concrete generator pad project including excavation, rebar installation, formwork, concrete works, backfilling, pre-construction works like site preparation and mobilization, and post-construction works like generator delivery, installation, and filling the generator with diesel. 2. The total project cost is PHP 259,449.15 with a 50% down payment required upon receiving the purchase order and the remaining 50% due upon completion. 3. The quotation is valid for 15 days and no changes or cancellations are allowed once the purchase order is issued.

Uploaded by

Victor Biacolo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
153 views1 page

Genset Base Pad

1. Fice Solution Cons. Inc. provides a quotation for a concrete generator pad project including excavation, rebar installation, formwork, concrete works, backfilling, pre-construction works like site preparation and mobilization, and post-construction works like generator delivery, installation, and filling the generator with diesel. 2. The total project cost is PHP 259,449.15 with a 50% down payment required upon receiving the purchase order and the remaining 50% due upon completion. 3. The quotation is valid for 15 days and no changes or cancellations are allowed once the purchase order is issued.

Uploaded by

Victor Biacolo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

OUR REF SL_CW_038

FICE SOLUTION CONS. INC. PROJECT TITLE Conrete Genset Pad


Blk 1, Lot 42, Sienna Villas, Habay 1 Bacoor COMPANY XDU Enterprises
Samar Office: Calbayog City, Samar ADDRESS NCR
Camarines Sur office: Brgy Panagdapian, Del Gallego, Camarines Sur. CONTACT PERSON Sarah Florano
CP no. 09952727103, email: [email protected] DATE 2-Dec-22
VAT NO: 603-297-847-000
QUOTATION/BOQ
UNIT PRICE
Item No. Unit Qyt (php, VAT- TOTAL
EXCLUSIVE)

A CIVIL WORKS
Manual excavation works, includes all necessary equipment, dewatering, hauling and disposal of
1 surplus materials. (2.5 M X 1.5 M X ) Thk 100 mm and (1MX1MX) thk 100 mm M3 0.475 1,050.00 498.75

2 Rebar, includes fabrication, cutting bending and installation KG 83 73.55 6,104.65


Formworks, includes all necessary support and frameworks to complete the
3 works M2 11.448 520.08 5,953.88

Concreting Works, 25 MPa, includes curing and all necessary testing works
4 such as compression test. M3 2.7 7,580.50 20,467.35

5 Backfilling works and compaction M3 1.08 580.00 626.40

B PRE-CONSTRUCTION

1. Mobilization/Demobilzation, Hauling of project materials, disposal and waste segregation, clearing of


Lum 1.00 25,000.00 25,000.00
area and HSE signages.
C POST-CONSTRUCTION

1. Genset Delivery to site (1050 kg). Lum 1.00 30,000.00 30,000.00

2. Genset / FSU Installation/Commissioning Lum 1.00 70,000.00 70,000.00

3. Supply & Fill 1000 L of diesel for Genset LTR 1,000.00 73.00 73,000.00

TERMS AND CONDITION: Sub-Total 231,651.03

1. Validity : 15 days from the date hereof. VAT 12% PHP 27,798.12
2. Payment Terms: 50% Down payment upon receiving of P.O, 50% upon completion TOTAL AMOUNT 259449.15
3. No Changes or cancellation are allowed once the P.O is issued.
4. The price has considered that the site is not slope and the distance from laydown area to site is maximum of 100 M, otherwise V.O shall be applied and agreed by both
parties.

We hope that this offer meets your expectation

Thank you & Regards,