This hazard analysis and risk assessment document analyzes risks associated with material handling and loading/unloading tasks manually or mechanically for a project in Bellary, Karnataka, India. It identifies potential hazards such as moving machine parts, slips/falls, and falling from heights. For each hazard, it evaluates the severity, likelihood, and risk level, and provides control measures and preventive actions to be taken by the contractor supervisor to mitigate the risks, such as using proper fall protection, tested lifting equipment, and personal protective equipment.

Uploaded by

Rais Zayn
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views

Jsa Unloading Loading

This hazard analysis and risk assessment document analyzes risks associated with material handling and loading/unloading tasks manually or mechanically for a project in Bellary, Karnataka, India. It identifies potential hazards such as moving machine parts, slips/falls, and falling from heights. For each hazard, it evaluates the severity, likelihood, and risk level, and provides control measures and preventive actions to be taken by the contractor supervisor to mitigate the risks, such as using proper fall protection, tested lifting equipment, and personal protective equipment.

Uploaded by

Rais Zayn
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT : 2X2063 TPD OXYGEN PLANT, JSW, BELLARY, Doc No:

KARNATAKA Rev
Date 11/5/2021
HAZARD ANALYSIS & RISK ASSEMENT
Page 1 OF 1
PTW NO
PTW DATE
TASK : Material handling and loading unloading - Manually/ Mechanically[**]
JSA NO.3
CONTRACTOR NAME: M/s.SPACETECH REVISION NO: PREPARED BY: I H ANSARI/VIJAYAKUMAR

GROUP MEMBERS: Supervisior, Riggers


RISK
HAZARD ANAYSIS

CONSEQUNCE
CONTROL ACTION

RISK LEVEL
NO JOB STEPS PREVENTIVE MEASURES

SEVERITY
MEASURES PARTY
HAZARD FACTORS

1.2 C M 1. Provide wheel guard to vehicles to


2 all moving parts.
2. All break and emergency stopper
Movement of machine and Contractor
3. Engineer Control to be in working condition.
vechicle supevisior
3. Provide Wheel check during
parking of vehicles.

1.2 C M 1. All unwanted material to be


2 cleaned from surface level.
2. Proper access/egress to be
provided to climb on truck trailer
during handling of the material
Engineer Control/ Contractor
5. Stumble, Slip and fall 3. Only skilled and experience
PPE supevisior
worker to be engagged for the work.
Material Handling / Loading
Unloading

L.2 C2 M 1. Prior to using all lifting tools &


tackles i.e wave sling , D-shackles,
wire sling, CPB etc. comply with
local rules.

1. Contractor
Unprotected moving parts Engineering Control
supevisior
2. All pinching, cutting/shearing
1. Contractor
Unprotected moving parts Engineering Control
points to be removed from work area. supevisior
3. Only skilled and experiened works

to be engagged for the work.


4. Wear all types of/job related PPEs

1. Prior to slinging material on


loaded trailer at height use proper
fall protection.
C Contractor
6 Falling from heights L.3 M Enginner Control 2. Use only tested sling/belt prior to
2 supevisior
lifting material for unloading .
3. Use lifting permit if
lifting/unloading is crtical.
[**] REFER WITH JSA MATERIAL UNLOADING, SHIFTING AND LIFTING