INSTRUMENTS CHECKLIST Page 1 of 1
Project:
Inspector: Project Name: JG4+ TRZEBNICA
Area: TRZEBNICA Client: NATURALNA ENERGIA
Equipment
Tag: TT-201 Description: Percolate piping MEP Master
Manufacturer: KOBOLD Model: MMA PT100 Serial Number:
Power supply: 19-28.5VDC Analog outputs: 4-20mA Digital outputs: 0
Inspection Checklist
Pass
No. Item to be Inspected Comments
(P/F)
1. Equipment type and class per P&ID and specification P
2. Equipment tag(s) installed and correct P
3. Installation of electrical circuit complete and correct P
4. Block and drain valves NA
5. Pneumatic / hydraulic tubing leak tested NA
6. Heat tracing / insulation / equipment housing P
7. Wiring correct P
8. Drawings marked up as-built Not yet sent to client F
9. HMI Graphic symbol and tag correct P
State Checklist
Pass
State Description PLC Local SCADA Comment
(P/F)
Input HMI
Ambient temperature 6.90 mA 2.9 °C NA To be calibrated P
50°C NA To be confirmed
100°C NA To be confirmed
Calibration
Setpoint Trip Point Actual Trip Point Calibration method Pass
State
(incl. units) (incl. units) (P/F)
ambient 9.00 mA / 3.7°C 6.90 mA From PLC program P
Max 20.00 mA / 100°C To be identified From PLC program
Comments:
- Medium and high levels of sensor feedback will be identified after heating
- The sensor can be calibrated by program adaptation
- Tag has to be installed
Company Name Signature Date
Methania Majdi Touili 06/12/2022
Tested By
Witnessed By