8110-400-030 - Procedure - Utility Crossing(s) Under Future and Existing Rail Reserve
8110-400-030 - Procedure - Utility Crossing(s) Under Future and Existing Rail Reserve
Document Compliance
If this document contains requirements that provide a standard of compliance in accordance with legislation, they shall be complied with irrespective of a project’s stage in
relation to the Project Management Framework. In all other circumstances, projects that have formally completed Stage Gate 3 may continue to comply with the relevant
PTA standards that were current at the completion of project Stage Gate 3.
Table of Contents
1. Introduction .................................................................................................... 7
1.1 Document Purpose............................................................................................................. 7
1.2 Audience and Applicability.................................................................................................. 7
1.2.1 Document Applicability ................................................................................................... 8
1.2.2 Document Exclusions ..................................................................................................... 8
1.3 Roles and Responsibilities.................................................................................................. 8
1.4 Key Concepts..................................................................................................................... 9
2. Procedure for Third Party Trenchless Excavations .................................. 10
2.1 Initial Contact and Letter of Conditions ............................................................................. 10
2.2 Submission and Approval of Safety Management Plan (SMP) .......................................... 11
2.2.1 The Letter of Conditions and the Signed Acknowledgement Form................................. 11
2.2.2 Work Methodology........................................................................................................ 11
2.2.3 Risk Assessment and Job Safety Analysis (JSA) .......................................................... 13
2.2.4 Design Summary Report and Design Drawings for Third Party Service Installation ....... 13
2.2.5 Permanent Way (Perway) Condition Report.................................................................. 14
2.2.6 Geotechnical Report..................................................................................................... 15
2.2.7 Existing Services and Utilities Location Report.............................................................. 17
2.2.8 Access Management Plan ............................................................................................ 17
2.2.9 Environmental Impact Statement and Management Plan .............................................. 17
2.2.10 Inspection and Test Plans......................................................................................... 17
2.2.11 Details of the Cable or Service Markers and Form of Construction ............................ 18
2.3 Application to Access the Rail Reserve............................................................................. 18
2.4 Technical Requirements for Third Party Service Installation.............................................. 18
3. Procedure for PTA Trenchless Excavations .............................................. 20
3.1 Track and Civil Branch Approval....................................................................................... 20
3.2 Safety Management Plan (SMP)....................................................................................... 21
3.3 Application to Access the Rail Reserve............................................................................. 21
3.4 Technical Requirements for PTA Service Installation ........................................................ 21
4. Construction ................................................................................................. 23
4.1 Safeworking Rules and Procedures.................................................................................. 23
4.2 Project Contact................................................................................................................. 23
4.3 Approved Supervisor for Trenchless Excavation............................................................... 24
4.4 Track Occupancy – Works within 3m from the Nearest Rail .............................................. 25
4.5 Existing Service Locating.................................................................................................. 25
4.6 Drainage .......................................................................................................................... 26
List of Tables
Table 1: Related Documents............................................................................................................. 6
Table 2: Description of Roles ............................................................................................................ 8
Table 3: Third Party Overcut Requirements .................................................................................... 19
Table 4: PTA Overcut Requirements............................................................................................... 22
Table 5: Supervisors for Trenchless Excavation............................................................................... 24
Table 6: Terms and Definitions ....................................................................................................... 32
Table 7: Abbreviations and Acronyms............................................................................................. 33
List of Figures
Figure 1: Typical PTA Cross-section and Minimum Depth for Trenchless Excavation (Third Party
Underbores) .................................................................................................................................... 11
Figure 2: Typical PTA Cross-section and Minimum Depth for Trenchless Excavation (For PTA
Underbores) .................................................................................................................................... 23
Figure 3: Underground Service Installation Minimum Survey Points ................................................ 27
Figure 4: Track Occupancy Diagram............................................................................................... 34
Related Documents
Table 1: Related Documents
Document Number Name
8103-000-004 Guideline: Safety Management Plan Working on PTA Property
8103-400-004 Procedure: Working in and Around the Rail Reserve
8110-000-013 Procedure: Deviation from PTA Requirements
8110-100-014 Procedure: Management of Engineering Change
8110-300-011 Procedure: Preparation of Computer Aided Drafting (CAD) Drawings
8110-400-029 Procedure: Applying for Access to the PTA Operating Railway Corridor
8130-000-004 Form: Application for Deviation from PTA Requirements
8130-400-560 Form: Trenchless Excavation and Survey
8190-400-002 Code of Practice: Narrow Gauge Main Line Track and Civil Infrastructure
8203-100-001 Guideline: Network and Infrastructure (N&I) Risk Management
8230-000-025 Safety Management Plan – Tier 1 & 2 Evaluation Checklist
8880-450-300 Specification: Access to Infrastructure
9100-000-007 PTA Safeworking Rules & Procedures
AS 1726 Geotechnical site investigations
AS/NZS 2566 Buried flexible pipelines
AS/NZS 3725 Design for installation of buried concrete pipes
AS 4799 Installation of underground utility services and pipelines within railway boundaries
– PTA Weekly Notice
1. Introduction
The Public Transport Authority (PTA) operates an integrated public transport system that
provides rail services throughout Western Australia. The PTA operating railway,
infrastructure and assets are frequently criss-crossed with high pressure gas main and high
voltage transmission lines, in addition to its own extensive services infrastructure.
As the Perth metropolitan area expands, developments are occurring throughout Perth and
this necessitates utility and services connection across PTA infrastructure, mostly
underground. With railway line speeds up to 130km/h, high pressure gas mains at a
pressure of 8.5MPa (1233 PSI), road speeds up to 110km/h and water supply pressure
mains from desalination plants, it is imperative that the installation of new utilities and
services do not interrupt the operations or cause damage to critical existing infrastructure.
Any incident resulting from interruption or damage could result in serious damage or
possible loss of life.
Developers, consultants and contractors shall be informed of the requirements for the safe
installation of these utilities and services that traverse PTA infrastructure so that correct
process can be followed, ensuring that asset operations can continue uninterrupted.
The procedure described herein applies to all trenchless underground service installation
works that enter and or cross under the PTA Operating Railway.
This document does not include the installation of a tunnel crossing of PTA infrastructure of
diameter greater than 2.0m or that may require a manned Tunnel Boring Machine (TBM)
with segmental lining or other installation method as part of a major infrastructure project.
Principal Track Provides final review and gives approval prior to proponent conducting the
Engineer trenchless excavation.
Third Party Project Proponent – Third Party Service Providers and their contractor applying to install
Manager underground service.
PTA PM and their Proponent – Person appointed by the PTA to install the PTA underground
Contractor service. Submits documents as required by procedure to Civil Branch for review.
Individual worker with a Track Access Permit level of a PO3 and approved by the
Approved Person PTA responsible for implementation of Safeworking Rules and supervision of
trenchless excavations on the PTA Network.
Protection Officer Individual worker with a Track Access Permit level of a PO1, PO2 or PO3
(PO) appointed to supervise workers within the Railway Reserve.
Person appointed by the Proponent and approved by the PTA, responsible for
Track Certifier
certifying that track is suitable for rail traffic post underboring works on each shift.
Figure 1: Typical PTA Cross-section and Minimum Depth for Trenchless Excavation
(Third Party Underbores)
See section 2.1 Initial Contact and Letter of Conditions. The Letter of Conditions and signed
Acknowledgement Form shall be part of the initial submission.
also required (e.g. if rates are lower than what was expected, what are the follow up
contingencies or remedial steps?).
A risk assessment shall be undertaken and provided to the PTA before commencing any
trenchless technology construction. The risk assessment shall consider potential
interference with existing or future works and focus on risks associated with the PTA
infrastructure, assets and the land within which it sits.
The risk assessment will be reviewed by the PTA, and subject to its review and/or the scale
of the project, PTA may direct the proponent to complete a risk assessment workshop which
is aligned to the PTA Guideline 8203-100-001 – Network and Infrastructure (N&I) Risk
Management.
The following potential risks, as a minimum, shall be considered in the risk assessment:
a. Loss of drilling fluid by breakout;
b. Collapsed hole, washout of cavities, subsidence and sinkholes formation;
c. Ground displacement associated with overpressure or blockage of drill stem or cutter
head;
d. Stuck drill rods or tools becoming detached;
e. Damaged pipes or coatings requiring redrill;
f. Abandonment due to equipment failure, unexpected ground conditions or obstructions;
and
g. Encountering unexpected ground or groundwater conditions (rock head, boulders,
running sand, artesian pressure, cemented layers).
Should a deviation from any of this procedure need to occur to minimise risk to the project
and the railway infrastructure, PTA Document: 8110-000-013 Procedure: Deviation from
PTA Requirements (see section 6) shall be followed. The risk assessment needs to provide
suitable detail to show that the project has considered alternatives and why the proposed
deviation is acceptable.
Please refer to the following PTA documents:
a. 8110-100-014 Procedure: Management of Engineering Change
b. 8110-000-013 Procedure: Deviation from PTA Requirements Deviation; and
c. 8130-000-004 Form: Application for Deviation from PTA Requirements more
information.
2.2.4 Design Summary Report and Design Drawings for Third Party
Service Installation
Design summary report and design drawings shall be provided in .pdf format and shall
comply with all requirements listed in section 2.4. Design shall include:
a. Details of the design of the utility crossing verifying that the crossing conduit(s) can
withstand the required overburden loads that may be exerted on the service during its
design life. The design life for any crossing is a minimum of 120 years in accordance
Current 8110-400-030 Rev 2.00 UNCONTROLLED IF PRINTED
to the PTA Specification 8880-450-010: Design Actions, Asset Design Life and
Maintenance Free Period, and is subject to acceptance by PTA, depending on the
location of the crossing. Certain locations may require a longer design life for the
crossings;
b. Cross-sections with location, length, dimensions of the crossing (i.e. reamer diameter),
encasement and carrier pipe diameter and thickness, construction material,
pipe/conduit contents, filling material (i.e. concrete/grout slurry), purpose of the
crossing, minimum cover proposed above trenchless crossing, minimum distance
apart of additional trenchless crossings (which shall at all times be at least 1.0m apart)
depths of launch, retrieval and any intermediate inspection pits;
c. A long section to true scale of 1:100 of the length of the new utility showing existing
services, infrastructure and buildings, the new utility(ies), launch, intermediate and
retrieval pits, relevant geotechnical conditions, geological profile and groundwater
levels, and proposed ground water level during dewatering if occurring;
d. Evidence to demonstrate protection of the PTA infrastructure and that it will not be
damaged or compromised in any way during the installation works. For example, any
potential electrical interference to rail signalling systems or corrosion protection of a
steel pipe for a proposed high-voltage electrical crossing; and
e. Should a Proponent wish to deviate from any Initial Design for which a design report
has been reviewed and commented on by a PTA infrastructure owner/operator then a
new design report shall be resubmitted for review and comment prior to commencing
site works that could potentially affect the PTA’s infrastructure.
Note: This section is only applicable to the PTA Heritage Lines (Armadale, Fremantle and
Midland lines) OR if the reamer diameter exceeds 200mm, unless otherwise
requested by the PTA.
A Perway Condition Report, including photographs of the existing track and rail reserve shall
be undertaken by an independent track experienced personnel prior to submission of the
Underbore SMP and one (1) week after the installation (refer to section 5.2).
The Proponent shall carry out an inspection for the Perway Condition Report in accordance
with 9100-000-007 PTA Safeworking Rules & Procedures. A nominated railway accredited
Protection Officer (PO) is required to ensure the safety of the works and train services.
A Perway Condition Report shall include all items listed below:
a. Ballast condition and profile:
1. Are there visible signs of fouling, rounding of the material, is there evidence of
bog holes, do the ballast shoulders comply with 8190-400-002 Code of Practice:
Narrow Gauge Main Line Track and Civil Infrastructure etc.?
2. Is there evidence of the track pumping?
b. Drainage:
1. Are the cess (outer) drains clean and clear of debris, ballast, etc.? What does the
6ft (between the Up & Down mains) drainage look like?
c. Sleepers:
1. Signs of damage (chipping, steel exposed), are they skewed, straight and at the
correct spacing? Are they all concrete? Is there a crossover or turnout in the
affected area?
d. Fastenings:
1. Type of fastening; e2003 Pandrol e-clips or otherwise? Any fastenings missing or
loose?
e. Track Geometry:
1. On a curve or tangent track? Is there cant (superelevation) and, if so, is this in
generally in line with the PTA Guideline: 8880-400-001: Rail Access Manual and
any other available data?
2. Are there visual signs of top or alignment defects?
f. Formation:
1. Is the formation compacted limestone or not? Are there signs of weakness or
defects in the formation? Is the section adjacent using cement stabilised
formation potentially indicating poor load bearing soils?
2. Is there a steep embankment or cutting? How high is the embankment or
cutting? etc.
3. How wide is the formation top past the ballast profile?
g. Fencing:
1. What condition is the fencing in and what type? Are the footings secure? Will
they be in danger of being undermined and/or leaving a gap under the fence?
How far offset from nearest rail?
h. Welds:
1. Are they in the cribs that the trenchless excavation will be underneath? Same
crib or staggered? Condition, evidence of the dipped welds, signs of pumping?
Are they flashbutt or aluminothermic welds?
i. General Surrounds:
1. Underground services, cabinets pits, lids, turkey nests, bridges, culverts, other
anomalies;
2. Are the surroundings flat, undulating in relation to the launch entry/exit pit and
the pipe itself? Dips, hollows etc.
3. Aerial view of section (example below depicting drill shot location and extent in
relation to surrounding area);
4. Provide photographs of the affected area.
The Proponent shall seek expert independent geotechnical advice on the proposed works
from a consulting Geotechnical Engineer. The report may require geotechnical investigation,
to ascertain the geotechnical conditions to a depth of at least 1m below the lowest level of
the proposed new construction (includes invert level of the proposed crossing, base levels of
any pits or shafts, etc.), including ground and groundwater conditions around the proposed
trenchless crossing of the PTA Operating Railway.
This advice shall be submitted in the format of a geotechnical report in accordance with AS
1726 as part of the access application process. As a minimum, the report shall include:
a. Description of the geotechnical testing undertaken and impacts of the construction
methodology;
b. Advice on the type of soil, whether cohesive or non-cohesive, rock, fill or other, and
expected groundwater conditions for the launch and retrieval pits as well as the
installation of the crossing;
c. Identification of any unusual subsurface features or geotechnical hazards associated
with the proposed works, including buried objects in fill, cemented layers, rock,
boulders, clean running sand, etc. and possible solutions to the hazards these may
pose;
d. Assessment to be carried out to establish expected displacement due to all works
activities including dewatering if any. The magnitude of displacement at each stage
and cumulative displacement at each activity shall be documented ensuring
conformance to limits provide in section 4.9.2;
e. Anticipated impacts of the excavations and installation process on the PTA
infrastructure;
f. Any protective or remedial measures that may be required to prevent adverse impacts
on the PTA’s infrastructure as a result of the trenchless installation;
g. Recommendations on monitoring requirements including details of the location and
type of monitoring equipment to be used, frequency of monitoring and details of how
the results should be presented and acted upon (e.g. monitoring meetings, daily
updates and summary reports). The monitoring requirements shall be as per 8103-
400-004 Procedure: Working in and Around the Rail Reserve;
h. Confirmation of Push/Pull Plan suitability (as required in section 2.2.2);
i. Identify and provide remedial measures for the potential for acid sulphate spoils (ASS)
being encountered during the works;
j. Maximum allowable drilling fluid pressures and annulus grouting pressures to prevent
fluid breakout for the cover depths and geological materials present along the route;
k. An assessment of and methodology to minimise/ prevent impacts to site drainage as
per section 4.6; and
l. The Geotechnical Report shall include a section, or provide a letter confirming that the
geotechnical consultant has reviewed and considers the proposed Work Methodology
as being appropriate to limit the ground displacement to acceptable levels as per
section 4.9.2 in the short and long term.
The consulting geotechnical engineer shall be available at all times during the works to
advise on actual ground conditions encountered and advise on any resulting changes
necessary to the design or work methodology, should ground conditions vary from those
expected.
The Proponent shall demonstrate that they have thoroughly investigated and identified any
existing services that are within the trenchless installation corridor. This shall include a Dial
Before You Dig (DBYD) search (www.1100.com.au).
The existing PTA and Third Party services shall be identified and proven either by hand dig
or pot holing. The use of ground penetrating radar (GPR) can be used to locate the service
but physical identification shall be made to prove location and depth.
The identified services shall be shown on a Services Drawing that shall be submitted to PTA
with the detailed design for the trenchless installation. The Proponent shall comply with all
relevant utility owner/operator and PTA requirements, including the provision of spotters and
site supervision, if required.
An Access Strategy Plan shall be produced as per the PTA Specification: 8880-450-300
Access to Infrastructure.
The Proponent shall prepare an Environmental Impact Statement (EIS) for the works and an
Environmental Management Plan (EMP). The EIS shall consider the methodology to be
utilised in installing the proposed service, including details of any drilling fluids and
lubrication materials. The statement shall consider the potential impact on the local
environment and water courses, ground water and flora and fauna that may be affected by
the works or a failure in the methodology, e.g. spillage.
The environmental submission shall address any potential impacts, Aboriginal and European
heritage issues, including evidence of consultation with relevant authorities, groundwater
management proposals and noise, vibration and traffic management requirements.
If acid sulphate spoils (ASS) were identified during the geotechnical investigations, the
Proponent shall include within the EMP the proposed management methodology for ASS
materials, including the handling, treatment and disposal of ASS material, at all times
ensuring that there is no contamination of the environment or water courses.
The EMP shall also consider all tunnelling materials, including drilling fluids, lubrication
materials and hydraulic oils and the proposed clean-up methodologies in the event of any
spillage. The EMP shall also include the relevant reporting requirements that will be adopted
for the project including reporting to the Client, PTA infrastructure owner/operator and the
relevant authorities in such an event.
The Proponent shall prepare Inspection and Test Plans (ITP) for all aspects of the proposed
works. Copies of the ITPs shall be submitted to the PTA as part of the access approval
process.
h. All encasing pipes shall be concrete and be designed to take into account a scenario
where leaks from the carrier pipe could corrode the concrete encasing pipe;
i. Any HDPE pipe installed under the railway with no encasing shall have a minimum
class of SDR 11;
j. The parallel trenchless crossings are to be installed with a minimum separation of 1.0
metres and in such a manner and level as to not destabilise adjacent bores;
k. Water and gas services shall be installed in concrete encasing pipes under the entire
railway reserve. The Polyethylene or High Density Polyethylene (PE/HDPE) encasing
pipes may be permitted, providing the gap between the encasement pipe and carrier
pipe is filled with a cement based grout or similar. The method of grouting shall be
included in the Work Methodology and describe how voids are eliminate;
l. Table 3 shows the requirements of grouting based on the overcut size (measured on
radius).
m. The entry pit where the bore commences shall be outside the railway boundary, unless
otherwise approved by the Civil Engineering Manager. Except where exceptional
circumstances exist, the launch pit shall be on the side closest to any PTA cable route,
to minimise bore alignment errors that may cause cable damage;
n. The bore apparatus shall enter the rail reserve with the top of the encasing pipe/bore
apparatus at a depth of not less than 2.5m below ground level;
o. The bore apparatus shall adjust its depth in the vicinity of PTA underground services to
provide a clearance of not less than 1.2 metre plus a margin of safety of 5% of the
indicated depth below ground, unless otherwise approved by the Civil Engineering
Manager. (For example, if the PTA cable is at 1.5m depth, then the top of the bore
shall be below [1.5+1.2]+5% = 2.84m below ground level.);
p. The bore process shall be that the bore apparatus shall not approach within 2.0 metres
of the position of the PTA cables without the depth being checked to confirm that the
bore head is at least 1.2m deeper than the PTA cables. Additional measurements shall
be made to demonstrate that the duct alignment is at least 1.2m clear of the PTA
cables;
q. No metallic pipes are to be installed below electrified railway, unless otherwise
approved by the Civil Engineering Manager in consultation with the Electrical
Engineering Branch;
r. The trenchless crossing shall be installed at right angles 90° (±5°) to the tangent
alignment of the track at the crossing point, with cable/pipeline markers clearly
indicating the entry and exit points if no services pits are present. Should this not be
possible due to site constraints, an Application for Deviation may be required to be
submitted to provide proof that no alternative alignment closer to 90º (±5°) is available
for approval by the Civil Engineering Manager. This will be at PTA’s discretion;
s. Under-track crossings shall in general be located:
1. At least two sleeper spacing away from any rail joints/welds;
2. A minimum of 5 metres clear of the moving parts of points and crossings; and
3. A minimum of 5 metres clear of any fixed nose crossing; and
t. The Design Life requirement for any crossing, including the sleeves, is a minimum of
120 years in accordance to the PTA Specification 8880-450-010: Design Actions,
Asset Design Life and Maintenance Free Period, and is subject to acceptance by PTA
depending on the location of the crossing. Certain location a higher design life may be
requested. The Design Life is to be confirmed in the design report as per section 2.2.4
above.
Figure 2: Typical PTA Cross-section and Minimum Depth for Trenchless Excavation
(For PTA Underbores)
4. Construction
This section covers the construction requirements for trenchless excavations. The Proponent
is to comply with the following requirements and the Work Methodology (described in section
2.2.2).
The Proponent shall liaise with the PTA on a regular basis, providing progress reports
including those highlighted in section 4.13. Any occurrence of an unusual or unexpected
nature, including significant construction issues encountered during installation, for example
stuck TBM, slurry breakout, subsidence, voided ground or sinkholes shall be immediately
notified to the PTA via a communications process specified in the SMP.
The project contact shall also be identified as part of the SMP.
The Track Certifier shall be present on site at all times while the site is working to
Track Certifier
supervise any underground service installation works.
The Track Certifier shall have a Certificate III in Rail Infrastructure or equivalent
and have suitable experience.
The Protection Officer shall ensure that the control of the track is handed back to
Train Control, once it is approved fit for rail traffic by the Track Certifier. If the Track
Certifier or the Protection Officer do not believe that the condition of the track is
suitable for rail traffic, the Protection Officer shall take the appropriate steps to
protect the site and inform Train Control.
Protection Officer
The Protection Officer shall be present on site at all times while the site is working
to supervise any underground service installation works.
The Protection Officer shall be suitably qualified as per the PTA Document: 9100-
000-007 PTA Safeworking Rules & Procedures.
Role Description
The Geotechnical Engineer shall review the Design, Methodology and
Geotechnical Report, and all other relevant documentation.
Geotechnical Engineer The Geotechnical Engineer shall be on-call at any time during the works.
Note: The Approved Employee or Track Certifier shall complete 8130-400-560 Form: Trenchless Excavation
and Survey, Part 3 and provide a copy to [email protected] before 10.00am the
following morning, after completion of the trenchless excavation works or each shift if works are
undertaken during multiple track closures.
Part 3A of 8130-400-560 Form: Trenchless Excavation and Survey shall be completed by Approved
Person prior to commencement of works inside or below the rail reserve.
WORKS INSIDE/BELOW THE RAIL RESERVE CANNOT COMMENCE IF “NO” IS THE ANSWER TO
ANY QUESTION IN PART 3A.
4.6 Drainage
The installation of the service ducts shall not detrimentally affect the existing site drainage.
Where the installation of a service duct results surface settlement greater to limits provide in
section 4.9.2 in the short-term or long-term, remediation of the drainage shall be undertaken
by the Proponent. Control of the volume loss during installation is therefore very important.
In addition, drainage of groundwater into the annulus between the overbore and the outside
of the pipe shall be prevented where flow along the service line is possible. To prevent this,
the overcut ratio shall be minimised. The required steps and methodology to prevent this
from occurring shall be detailed in the Geotechnical Report, where appropriate (see section
2.2.6).
The PTA railway reserve is to be reinstated to a similar condition to the existing to the
satisfaction of the PTA on completion of the works. All trenched work within PTA rail reserve
shall be backfilled and compacted to the satisfaction of the PTA for easy traffic by the PTA
maintenance vehicles.
The track geometry shall not be changed vertically or horizontally by more than 5mm due to
trenchless excavation. If the track geometry has been changed all costs associated with
repair works shall be borne by the Proponent or internal PTA Project.
If the track condition is unfit for normal mainline operation at the scheduled time due to
underground service installation works and/or the track requires repair works, all costs of rail
closures, emergency bus replacement services and repair works shall be borne by the
Proponent or internal PTA Project.
The bore tracking equipment shall, as a minimum, transmit the position, pitch, depth,
direction, and roll of the drill head. Walk over systems will only be feasible when no trains
are running (track closure). Hence, a wired or remote system is required.
An accuracy of at least 75mm from the centreline position of bore shall be maintained at any
point along the alignment.
The tracking and accuracy of the drill head shall be documented in the Work Methodology.
The Installation Methodology shall include specific details of the thrust boring or Micro
Tunnel Boring Machine (MTBM) and the records that will be taken. As a minimum, the daily
records shall include the name of the operator, distance of shift advance, rate of advance for
each ring or pipe, jacking pressures, survey details for start and end of shove, flow rates of
drilling fluids into and out of the MTBM, volume or weight of spoil removed for each ring or
pipe compared to the theoretical volume to be extracted, quantities of any additives or
drilling muds added to the system and timings, details of any annulus grouting undertaken
and details of the pipes or rings installed, including any repairs undertaken.
For thrust bore installation, the gap between the sleeve and pipe shall be filled with a cement
based grout or similar.
The above items shall be submitted as part of the Work Methodology.
The Installation Methodology shall include specific details for the horizontal directional
drilling (HDD) machine and the records that will be taken. As a minimum, this shall include
distance of shift advance, rate of advance for each length of drill, methods of checking HDD
head alignment on a progressive basis, drilling thrust pressures, survey details for start and
end of drill, drill head size, installed pipe diameter, calculated resulting void dimension and
operator name.
For directional drilling installation, the maximum mud pressures allowed during the process
are the lesser of the pressures recommended in the Geotechnical Report or the following:
a. Drilling phase – mud pressure, measured at the mud jets, not greater than 20 Bar
(2MPa or 290psi);
b. Pull back phase – mud pressure not to exceed 20 Bar (2MPa or 290psi); and
c. Pull back phase – ram hydraulic pressure not to exceed 55 Bar (5.5 MPa or 800psi)
The Installation Methodology shall include specific details for the auger boring machine and
the records that will be taken. As a minimum, this shall include name of the operator,
distance of shift advance, rate of advance for each length of drill, drilling thrust pressures,
quantity of spoil removed compared to the theoretical volume to be extracted, methods of
checking HDD head alignment on a progressive basis, survey details for start and end of
drill, maximum distance the auger is permitted to protrude out in front of the protective
casing and operator name.
The Proponent or Surveyor shall submit 8130-400-560 Form: Trenchless Excavation and
Survey to the PTA no later than 24 hours after completion of each topographical survey.
7. Glossary
The following terms are used in this document.
Table 6: Terms and Definitions
Term Definition
Auger boring is a method of installation of pipes or conduits by simultaneously jacking
Auger Bore the casing pipe whilst using a rotating helical auger within the casing to excavate the
spoil.
A microtunnel is a small diameter tunnel excavated by a remotely-operated microtunnel
Microtunnel
boring machine.
The difference between the radius of the bored hole to the radius of the pipe, measured
Overcut Radius
concentrically from one radius to the other.
The ratio of the annular area outside the installed pipe to the area enclosed by the
Overcut Ratio
pipe.
Perway Permanent Way, railway reserve and all PTA infrastructure.
Pipe jacking is a technique for the installation of underground pipelines, ducts and
Pipe Jack culverts using hydraulic jacks to push specially designed pipes through the ground
behind a micro tunnel boring machine.
Any land owned by the PTA that forms part of the PTA rail or network on which trains
belonging to PTA are operational or are intended to operate. This includes, but is not
limited to:
Mundijong Junction (Armadale) to Perth;
PTA Operating
Railway Midland to Perth;
Robbs Jetty (Fremantle) to Perth;
Butler to Mandurah; and
Thornlie to Beckenham
Shall This indicates that a requirement is mandatory.
A Slurry TBM is a full face tunnel boring machine which provides face support by
pressurising a drilling fluid comprising bentonite and additives such as polymers and
Slurry TBM
foams inside the cutter head chamber. Tunnel spoil is pumped away from the face via
a slurry pipeline.
The ratio of the surface settlement trough area to the area of the bored tunnel per
Volume Loss
metre run of tunnel.