BILL NO.
1: PRELIMINARY
S/N DESCRIPTION OF WORK QTTY UNIT RATE AMOUNT (N)
1 Allow a provisional sum for the running 9,600,000.00
cost of the project
Carried to summary 9,600,000.00
P/1
BILL NO.2: SITE CLEARANCE
S/N DESCRIPTION OF WORK QTTY UNIT RATE AMOUNT (N)
2.1 Clear site on either side of centre line of
the road up to the limit of construction
width of all bushes, trees including the
removal and disposal or stocking of
topsoil as directed by project manager’ 199,500 m2 170 33,915,000.00
2.2 Excavate and dispose suitable material 10,980 m2 1,600 17,568,000.00
2.3 Excavate from approved borrow pits
haul excavated material any distance,
deposit, spread 150mm layer and
compact to 100% B.S. compaction as
filling for embankments and margins,
shape formation and trim slopes to
required cross section. All measured as
completed work in final sites (haulage 22,500 m3 2,450 55,125,000.00
inclusive)
Carried to summary 106,608,000.00
P/2
BILL NO. 3: CULVERT AND
DRAINS
S/N DESCRIPTION OF WORK QTTY UNIT RATE AMOUNT (N)
3.1 Excavate for all culvert and drains to any
depth including backfilling and disposal
of surplus materials as directed by the
project manager’s representatives
(including dewatering) 24,200 m3 1,400 33,880,000.00
3.2 Provide and install 900mm double ring
culverts as specified by and directed by
the project manger’s representatives,
rates includes surrounding, wing wall,
head walls and form work 88 m3 65,000 5,720,000.00
3.3 Provide and install concrete Drains Type
1 but uncovered (600mm x 600mm) as
specified by the project manager’s
representatives, rates includes
reinforcements and form work 5,200 m2 35,000 182,000,000.00
3.4 Provide and place 150mm thick stone
pitching set in mortar 1:4 cement and
sand mortar 1,320 m2 4,000 5,280,000.00
3.5 Provide concrete type 4 kerbs (450mm x
150mm) as specified and directed by
project manager’s representatives 2,670 m2 4,800 12,816,000.00
3.6 Provide, mix and place concrete grade
25 in vehicular crossing slab 200mm
form work and reinforcement inclusive 54 m3 20,700 1,117,800.00
Carried to summary 240,813,800.00
P/3
BILL NO.4: PAVEMENT AND
SURFACING
S/N DESCRIPTION OF WORK QTTY UNIT RATE AMOUNT (N)
4.1 Shape and compact formation in cut as
specified in 100% B.S. Compaction 97,000 m2 133 12,901,000.00
4.2 Provide, spread, shape and compact to
100% W.A.S compaction selected
breaking materials as fill materials as
sub base not exceeding a compacted
layer of 200mm thickness (Haulage
inclusive) 15,400 m2 8,000 123,200,000.00
4.3 Provide, spread, shape and compact to
100% W.A.S. compaction selected
crushed materials as fill materials as
base (wet process) not exceeding a
compacted layer of 200mm thickness
(Haulage inclusive) 15,400 m2 16,200 249,480,000.00
4.4 Provide and lay prime coat using MCD
or MC1 cutback bitumen at including
blinding with sand or quarry fine on
carriageway 96,500 m3 800 77,200,000.00
4.5 Provide, lay and compact asphaltic
concrete binder course to a compacted
thickness of 60mm on carriageway 96,500 m3 6,500 627,250,000.00
4.6 Provide, lay and compact asphaltic
concrete wearing course to a compacted
thickness of 40mm on carriageway 96,500 m3 4,700 260,550,000.00
4.7 Provide pavement marking as directed
by ER P.S. 4,000,000.00
4.8 Provide mounted regulatory road signs
as shown on drawings and directed by
project manager’s representative P.S. 5,000,000.00
Carried to summary 1,359,581,000.00
P/4
SUMMARY PAGE
BILL NO.1: GENERAL 9,600,000.00
BILL NO.2: SITE CLEARANCE 106,608,000.00
BILL NO. 3: CULVERT AND DRAINS 240,813,800.00
BILL NO. 4: PAVEMENT AND 1,359,581,000.00
SURFACING
SUB-TOTAL 1,716,602,800.00
ADD CONTINGENCY 2.5% 42,915,070.00
SUB-TOTAL 1,759,517,870.00
ADD V.A.T. 7.5% 131,963,840.30
SUB-TOTAL 1,891,481,710.30
CONSULTANCY FEE 30,000,000.00
GRAND TOTAL 1,921,481,710.30