Client Lead Consultant Main Contractor
MEP T&C:
Contractor:
Project Title: MAYAN YAS ISLAND LIVING
Document No. YAS-MYN-ARK-
ME-MST-00002(00)
Method Statement for Testing & Balancing of FCU Revision No.: 00
Date: 24/06/2020
Page: 1 of 9
METHOD STATEMENT FOR TESTING & BALANCING
OF FCU
Main Consultant
T&C HVAC
Contractor Approval
Rev Date Description
Status
CES ELMACS Al Rakha AECOM
00 24/06/2020 First issue
Client Lead Consultant Main Contractor
MEP T&C:
Contractor:
Project Title: MAYAN YAS ISLAND LIVING
Document No. YAS-MYN-ARK-
ME-MST-00002(00)
Method Statement for Testing & Balancing of FCU Revision No.: 00
Date: 24/06/2020
Page: 2 of 9
INDEX
I. PURPOSE
II. SCOPE
III. REFERENCES
IV. SAFETY
V. RESPONSIBILITIES
VI. TOOLS & EQUIPMENT
VII. EXECUTION OF WORKS
VIII. QUALITY CONTROL PROCEDURE
IX. ENVIRONMENTAL
X. EMERGENCY PROCEDURE
XI. ATTACHMENTS
CHECK LIST
ITP
RISK ASSESSMENT
SAMPLE TEST SHEETS
Client Lead Consultant Main Contractor
MEP T&C:
Contractor:
Project Title: MAYAN YAS ISLAND LIVING
Document No. YAS-MYN-ARK-
ME-MST-00002(00)
Method Statement for Testing & Balancing of FCU Revision No.: 00
Date: 24/06/2020
Page: 3 of 9
I. PURPOSE
The purpose of this Method Statement is to explain the method, nature and procedures for the
testing and air balancing of FCU. This activity should be performed with strict compliance and
implementation of Safety Requirement Procedure and project specifications.
This document is for submission to the Consultant, for their review and concurrence. This
document, if deemed necessary will be revised to accommodate circumstantial changes &
modifications; which cannot be foreseen at this stage.
This document is applicable to the works related to MAYAN YAS ISLAND LIVING Project
II. SCOPE
The scope of this Method of Statement covers the works as follows,
Testing & Air Balancing of FCU’s – 1824 Nos
This work will be carried out by Choices Evaluation Services.
III. REFERENCES
Project Specification
Approved Shop Drawings
Inspection and Test Plan
Estidama Requirements
ASHRAE-90.1-2007
CIBSE cod A and code B (1996, confirmed 2006)
BSRIA Standards
OSHAD – SF CoP 1.0 Hazardous Materials
OSHAD – SF CoP 11.0 & OSHAD SF – TG: Safety in Heat
OSHAD – SF CoP Lock Out Tag Out
Client Lead Consultant Main Contractor
MEP T&C:
Contractor:
Project Title: MAYAN YAS ISLAND LIVING
Document No. YAS-MYN-ARK-
ME-MST-00002(00)
Method Statement for Testing & Balancing of FCU Revision No.: 00
Date: 24/06/2020
Page: 4 of 9
IV. SAFETY
All individual operation will be set up and expedited to ensure the compliance with project
approved HSE Management Plan.
Workers should use proper Personal Protection Equipment.
Workers will be advised of hazards (Tool Box Talks) prior to start the activities.
Suitable and sufficient sign boards shall be provided (traffic sign, mandatory sign,
prohibition sign warning sign; emergency contact numbers sign boards etc.)
Only qualified and experienced personnel will conduct the operation.
The safety of the works will be closely monitored by Competent Safety Officer.
Approved method statement and task specific risk assessment shall be followed.
Daily inspection of the equipment involved must be implemented, resourced and recorded.
Temporary rest shelter and drinking water must be arranged at site, but with safe from any
construction activities.
Manual handling training to be conducted for all workers prior to the works.
Task specific lifting plan shall be submitted prior to any lifting activity at the site premises.
Since it is summer, all necessary precaution related to safety in heat will be followed.
Prior to start the TAB works, equipment’s cable termination to Electrical DB shall be ensured
and only competent worker shall be engaged.
Lock-out Tag-out procedure shall be followed.
V. RESPONSIBILITIES
The following Personnel are responsible for the Testing & Air Balancing works under the control of
Contractor and supervision of Consultant.
1) Project Manager
Responsible for co-ordination with Commissioning Engineer and Sub Contractors for
execution of work
2) Commissioning Engineer
Responsible for co-ordination with Main Contractor and all Sub-Contractors, for execution of
the work.
Co-ordination of Daily site activities with Project Supervisors of each discipline.
Attend Commissioning progress meetings.
Client Lead Consultant Main Contractor
MEP T&C:
Contractor:
Project Title: MAYAN YAS ISLAND LIVING
Document No. YAS-MYN-ARK-
ME-MST-00002(00)
Method Statement for Testing & Balancing of FCU Revision No.: 00
Date: 24/06/2020
Page: 5 of 9
Prepare, monitor and review and schedules and reports.
3) EHS Manager
The Main Contractor EHS Manager is responsible to review MSRA and ensure all EHS
requirements are followed.
4) EHS Officer
The Sub Contractor EHS Officer shall conduct briefing along with supervisor to all work
group on the MSRA and ensure all EHS requirements are followed.
5) Project Supervisor
Testing & Air Balancing of FCU
Overall responsibility for each discipline of works – Reports to Commissioning Engineer.
6) Technicians
Testing & Air Balancing of FCU
Responsible for execution of work in site in co-ordination with project supervisors. Reports
to Commissioning Engineer & project Supervisor of each discipline.
VI. TOOLS & EQUIPMENT
Air Balancing Monitor
Micrometer
Anemometer
Tachometer
Clamp meter
Thermometer
Ladder
Tool Box
Client Lead Consultant Main Contractor
MEP T&C:
Contractor:
Project Title: MAYAN YAS ISLAND LIVING
Document No. YAS-MYN-ARK-
ME-MST-00002(00)
Method Statement for Testing & Balancing of FCU Revision No.: 00
Date: 24/06/2020
Page: 6 of 9
VII. MANPOWER:
Sufficient manpower, as required to meet the safe, satisfactory and timely completion of the job
shall be deployed and these will consist of; but not limited to the following:
← T&C Engineer - 2 Nos
← Specialized Technician - 4 Nos. (Min.)
← Supporting Helpers - As required.
VIII. EXECUTION OF WORKS
1. PRE START CHECKS
The purpose of these procedures is to check that the installation is in a satisfactory and safe
condition before starting up
All the equipment and duct installation as per “As built” drawing and approval from
consultant is available before start up
Installed equipment and project specifications are same
All Terminals are fitted and VCD are open
Thermostat installation is as per drawings
Ductwork, chambers and components are cleaned
All fire dampers are fully open
Air leakage tests are successfully completed
Filter installation is correct and condition is good
Cooling Coil condition is good
Fan and motor bearings are properly lubricated
Access doors are securely fitted
Fan Impellers rotates freely
Client Lead Consultant Main Contractor
MEP T&C:
Contractor:
Project Title: MAYAN YAS ISLAND LIVING
Document No. YAS-MYN-ARK-
ME-MST-00002(00)
Method Statement for Testing & Balancing of FCU Revision No.: 00
Date: 24/06/2020
Page: 7 of 9
Motor insulation tests are complete
Electrical terminal box is clean
2. START UP CHECKS
The systems will be tested in manual operation.
Direction and rotation of fan is proper
Motor, drive and fan are free from vibration or undue noise
Run the fan and check the motor current. Ensure that its design full load value is not exceeded
Measure the total flow rate at the terminals since there is only few terminals for FCU’s
Check and verify the motor speed control with thermostat.
Check Actuator is working in accordance with thermostat
Measure the flow rate at different speeds
Note: Before starting the testing, it is essential that the building ceiling, partition doors and
windows are installed. Ensure windows and doors are in their normal or closed state. If spaces are
not architecturally sealed, abnormal pressure distributions will unbalance the system and lead to
inconsistent results.
3. WORK PROCEDURE
FCU’s are having lesser terminals and hence the duct air flow measurement is not applicable. The
system flow rate is measured in the terminals and the sum obtains the result. Take initial reading in
terminals and calculate the actual percentage flow rate in terminals. Do the proportional balancing
for the calculated flow rate in terminals. Adjust the VCD for terminal having higher flow rate and
bring it to the required proportional flow rate. The other terminals will be automatically adjusted.
Do the same on each terminal and mark the VCD position. Now take the final terminal flow rate and
check the values for tolerance limit. Measure the Suction and discharge static pressure values
Note: Vane Anemometer and Balometer Hoods will be used to measure the air flow rate in grills
and diffusers as per their size.
Client Lead Consultant Main Contractor
MEP T&C:
Contractor:
Project Title: MAYAN YAS ISLAND LIVING
Document No. YAS-MYN-ARK-
ME-MST-00002(00)
Method Statement for Testing & Balancing of FCU Revision No.: 00
Date: 24/06/2020
Page: 8 of 9
IX. QUALITY CONTROL PROCEDURE
All works shall be ensured by the Project Manager and T&C Engineer to conform with the
MOS, specification and manufacturer recommendation.
Upon completion of Testing & Air Balancing of each equipment, Inspection Request (WIR)
shall be raised to consultant approval as per Inspection test plan.
QA/QC shall double check the work procedure along with the site team, if it is compiled as
per approved MOS, project specification and manufacture recommendation.
QA/QC will invite the Engineer for work inspection at site.
Once WIR is approved, further activity will proceed.
If WIR is rejected, QA/QC immediately inform the site team to rectify the Engineer’s
comments. Once rectification completed, Work Inspection Request (WIR) shall be raised
again to consultant approval as per Inspection test plan.
X. ENVIRONMENTAL
All waste shall be segregated and disposed as per waste management plan.
Dust shall be suppressed by water spraying as and when required.
Necessary dust bin or waste collection box will be provided to collect the wastages.
Appropriate drinking water shall be provided according to the man power.
Main contractor will ensure emergency procedure as per the site HSE Plan.
All the chemicals shall be stored, handled and disposed as per MSDS only
XI. EMERGENCY PROCEDURE
General: Site general safety procedures will be followed. In case of emergency the Safety
Officer will stop the work. He will put into action the emergency arrangements and report to
assembly points as indicated during the Site Induction Course.
Fire Precautions: No significant fire risk is associated with this activity but general fire
prevention measures will be taken. In case of small fire use the fire extinguisher, if you
know how to use the fire extinguisher.
Client Lead Consultant Main Contractor
MEP T&C:
Contractor:
Project Title: MAYAN YAS ISLAND LIVING
Document No. YAS-MYN-ARK-
ME-MST-00002(00)
Method Statement for Testing & Balancing of FCU Revision No.: 00
Date: 24/06/2020
Page: 9 of 9
In case of Eye and skin contact of coating chemicals : Immediate information will be
given to site male nurse who will be provide first aid treatment.
Heat stress management plan: Approved heat stress management procedures shall be
followed without any deviation.
XII. ATTACHMENTS
Check list
ITP
Risk Assessment
Sample Test Sheets