WORK METHODOLOGIES FOR
INTERIOR FITOUT WORKS
GYPSUM CEILING
INTRODUCTION
➢ WHAT IS GYPSUM
CEILING?
Gypsum false ceiling consists
of gypsum boards that are
being supported by Metal
Framework. The joints of
gypsum boards are then taped
and finished with gypsum
jointing compound.
➢ BENEFITS OF GYPSUM CEILING
Services friendly – Its easy to install and maintain all the
services, light fixtures etc. inside the gypsum ceiling.
Dry construction – The gypsum ceiling don’t require water
either for the installation or curing.
Fire rating – are also available with fire rating.
Light weight – The gypsum ceiling are also light in weight.
Thermal insulation – Gypsum boards are good in thermal
resistance.
Sound Isolation – Gypsum ceiling Prevents the transfer of
unwanted sound to adjoining areas.
GYPSUM CEILING TOOLS
• Fixing Tools
NAME TOOLS USAGE APPLICATION
To Fix metal supports
Gas Gun on true slab
Hammer Drill To drill a hole in to
Machine the structure
To fix Gypsum board on
Battery Drill metal frame with
Machine screws
Screwdriver for To fix screws inside
Leverage board
To fix angle bead at
Stapler external corner of
Drywall & step ceiling
For fixing of
Drill Bit Holder screws on Gypsum
board
GYPSUM CEILING TOOLS
• Cutting Tools
NAME TOOLS USAGE APPLICATION
Metal Cutter For cutting of main
beam & perimeter
channel
Crocoplac To cut gypsum board.
To make hole in
5 Hole saw set gypsum board
To create additional
5 Hole saw set round cut out
To make Circular
HSS step Drill opening in Gypsum
board to 3
accommodate smoke
detectors
• Carrying Tools
NAME TOOLS USAGE APPLICATION
Transplac To carry one
gypsum board
To carry two
DuoPlac gypsum
boards
GYPSUM CEILING TOOLS
• Marking Tools
NAME TOOLS USAGE APPLICATION
Marking of reference
Chalk Line Line on structure
To check the
Water Level alignment of the
gypsum boards
To determine the
Levelling Hose/ Laser ceiling level
Level
• Finishing Tools
NAME TOOLS USAGE APPLICATION
Sanding of cut edges
Board Sander of Board
4
To Finish Internal
Corner Tool Corner of Drywall &
ceiling
Taping Knife To embed tape on
board joints
To spread the jointing
Applicator compound on board
joints
GYPSUM CEILING MATERIALS
Perimeter Channel
It is fixed along the periphery of false ceiling
area. It is fixed to wall with help of screws and
serves as supports of intermediate channels.
Intermediate Channel
These are the primary sections to support the
ceiling sections.
Ceiling Section
The main supporting section to fix gypsum
board.
Ceiling Angle
To provide suspensions from the structural
soffit.
Hanger Wire
12-gauge wire used to suspend intermediate
channel from ceiling fasteners.
Fasteners
Attach hanger wire to ceiling joists.
Quick Hang hardware
Hanger wire alternative; a faster, easier way to
install and level a drop ceiling. Hardware
includes hooks and brackets.
WORK METHODOLOGY AND SEQUENCE
Gypsum False Ceiling is a secondary ceiling that hangs below
the main ceiling. Gypsum False Ceiling is quite an economical
feature that is easy to install.
Firstly all required measurements & levelling of ceiling.
To hang or support False ceiling from main ceiling, Anchor
fasteners are used. Anchor fasteners provide great support
to secondary ceiling.
Ceiling sections are then fitted to the main foundation
forming much précised framing that enables
attaching plasterboard or any other material used for false
ceiling.
Click icon to add picture
• LEVEL MARKING
A Good practices Process
Draw the required false
Ceiling Finish line from the
1
finish Floor by using Laser
line marker or Water Level.
Transfer this line on all
corners of room. Mark a line
2
on periphery of wall by using
chalk line.
• FRAMING
B Good practices Process
7
Fix the wall angle at the
periphery of wall on grid line
1
along with the fasteners
placed at 600 mm.
Mark the position of fasteners
2 on true slab at 1200 mm c/c
both direction.
At junction of two lines, drill
a hole with the help of 8 mm
3 dia. drill bit of Power
Fastener Driver & 45 mm
long Rawl plug inside a hole.
Fix the soffit cleat to the
Fastener at 1200mm c/c.
4 Ensure the nut of fastener is
properly tightened with
Soffit cleat
B Good practices Process
Fix the Ceiling angle of
suitable length to the
5
soffit cleat at 1200mm c/c
with help of screw.
Take a levelling hose for
levelling and transfer the
6 perimeter top flange level on
to the Ceiling Angle. Then
mark the position of
Intermediate Channel.
Fix the intermediate channel
to the flange of Ceiling angle
7 with screws. Ensure
Intermediate channel resting
on Channel.
Fix ceiling section
perpendicular to the
8
intermediate channel by
using connecting clip
Ensure distance between two
ceiling section should not be
9
more than
457mm c/c
Ensure the overlapping of
Ceiling section &
Intermediate channel
10
should not be less the
150mm. Used metal to
metal screws
Cross -Check the level of all
11 frame work to ensure entire
frame is in Line & Level
• OPENING FOR SERVICES
C Good practices Process
9
Cut the Ceiling section at the
location of opening like Light
1
opening / Ac Opening /
Access panel
9
Ensure additional support at
both cutting ends by using
2
intermediate channel suspended
from soffit
Put perimeter channel at the
3
periphery of opening
• BOARDING
D Good practices Process
Do boarding by using 8x4ft
9
gypsum board. Ensure that
the length of board
1 perpendicular to Ceiling
Section. ( Square Joint of
Board screw fix on Ceiling 9
section)
Put the 25mm drywall screws on
board at 150mm on periphery of
2 Ceiling & at 230mm on ceiling
section. Staggered the board
joints
Ensure that, the drywall screws
are 10mm away from tapered
3 edge & 13mm away from square
edge to avoid breakage of the
gypsum board
Tentative quantities based on a typical project of 20,000 Sq. Ft
Area Tentative quantity of gypsum ceiling.
Considering a
typical project 4,500 Sq. Ft.
of 20,000 Sq. Ft
Remark: The above mentioned quantity is based upon a specific project of 20,000 Sq. Ft. The actual
quantities for any given project may vary according to the Layout and design of Project.
Manpower & Manhours Requirement
Area Timeline/Manhours
Type of Labour Required
Considering an
area of 4,500 sq. 6-8 Days
ft. For 8 Skilled Workers (Inclusive of Measurement, installation of
installation of 4 Unskilled Labors framework, installation of gypsum ceiling
Gypsum boards)
Partition .
Remark: The timelines is based on typical labor output on 8 hours working days and single shift a day. If
no. of working hours a day is lessor, it may take more days for completion of job. In case of projects with
short deadlines, the man power may be increased to reduce the time required for given task.