1. This document provides instructions for installing an ISKRAEMECO MT174 electricity meter with current transformer (CT) inputs. 2. It describes connecting the CTs to the meter terminals and phase wiring, and checking that voltages, currents, and energy flow directions are correctly sensed on each phase. 3. Installation checks include verifying phase voltages and rotations, isolating phases one at a time to check each CT is on the proper phase, and ensuring the energy flow arrow indicates power imported to the load rather than exported from it.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
658 views3 pages

MT 174 CT METER Installation

1. This document provides instructions for installing an ISKRAEMECO MT174 electricity meter with current transformer (CT) inputs. 2. It describes connecting the CTs to the meter terminals and phase wiring, and checking that voltages, currents, and energy flow directions are correctly sensed on each phase. 3. Installation checks include verifying phase voltages and rotations, isolating phases one at a time to check each CT is on the proper phase, and ensuring the energy flow arrow indicates power imported to the load rather than exported from it.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

1, Church Lane, Normanton, West Yorkshire, WF6 2DE Tel:01924 891049

ISKRAEMECO MT 174 5A CT METER INSTALLATION

Meter Installation:

DANGER !
 Note that this work should be only carried out by suitably qualified and trained
personnel.
 The meter circuit should be isolated while making changes to the wiring.

Connections to CT version of ISKRAEMECO MT174 Meter

ISKRA

+ Q
-P
- Q
+P L1 L2 L3 XXKwh
8.8.8.8.8. 8.8.8.8.8.8.8.8

MT174-D2xxxxxxxxXXx-Xxxxxx

10,000 imp/kWh

10,000 imp/kVAh

10,000 imp/kvarh

N0. 67 593 541

41 27
40 29
42

1 2 3 4 5 6 7 8 9 10 11 12

Reference
1A 1A 1A
voltage
fuses
41
A+ (Import energy)
Pulse 40
Outputs Common

SUPPLY S1 S2 42
(k) (l)
A- (Export energy)
PHASE
(BROWN) P1 P2
(K) (L) LOAD
CT 1
SUPPLY S1 S2
(k) (l)
PHASE
(BLACK) P1 P2
(K) (L) LOAD
CT 2 S1 S2
SUPPLY (k) (l)
PHASE P1 P2
(GREY) (K) (L) LOAD
SUPPLY CT 3
NEUTRAL
(Blue) LOAD

Note that in the case of equipment that generates energy, the “supply” side is usually
connected to the generator and the “load” side to the mains. For an “export” meter the
same applies.
If in doubt: ASK for advice.

Page 1 of 3
1, Church Lane, Normanton, West Yorkshire, WF6 2DE Tel:01924 891049
ISKRAEMECO MT 174 5A CT METER INSTALLATION

Installation Checks:
Supply Voltages:

 Check the L1, L2, L3, indicators on the meter display – these should all be on.

 Missing indicators show a phase voltage missing. Check supply and reference
voltage fuses.

 Flashing indicators show incorrect phase rotation – two pairs of phase voltage cables
must be swapped, e.g. exchange the L1 (both in & out cables) with the L2 (both in &
out cables).

Currents and Energy Direction:– How to check each phase separately IF IN DOUBT: ASK

 To perform this test a load must be drawing current from the supply so that the meter
is operating.

 Isolate 2 phases (normally by removing the relevant voltage reference fuses). Isolate
and short out the remaining 2 CTs CAUTION: Always ensure that CTs are shorted
or dangerous voltages can be present on CT cables

 Only keep the CT on the phase circuit to be checked. You are now working with one
phase voltage only – check that the P arrow indicators on the meter display show P+

 If there is no arrow and energy flow (Kw) is not present, either the installation is not
under load OR the CT being checked is not installed onto the relevant phase cable.

 Once checked, isolate this phase and CT and repeat this test for the other phases
checking for P+.

 If P- is showing instead of P+ the CT is the wrong way around the supply cable. P1
should be on the supply side (or direction of current flow side) of the cable. OR S1
and S2 are connected the wrong way on the meter terminals.

 Finally, re-connect all supplies and check all CTs are correctly terminated. As a final
check display the reverse (export) reading on the meter by accessing the additional
displays using the blue button as shown above. Make a note of the reading then
check a few minutes (or hours) later – the value should not increase.

 Note that some loads result in energy flow in two directions – e.g. a grid connected
wind turbine will draw a small current for its control circuitry in the reverse direction
when not generating.

Meter LEDS:
Once powered up and in operation you can check the operation by observing the LEDs on the
front of the meter:

LED operation:
OFF = No voltage to meter
ON = Voltage OK No current flowing through the meter
BLINKING = Energy registered by meter (proportional to load being measured)
See next page for sample of CT installation

Page 2 of 3
1, Church Lane, Normanton, West Yorkshire, WF6 2DE Tel:01924 891049
ISKRAEMECO MT 174 5A CT METER INSTALLATION

CT Installation Details:

JW Smart Meters CT SCTK68

P1 P2

Split CT Split CT
hinge Locking clip
P2

SPLIT CORE CT
SCTK68 1B - 35
150A/5A 1.0 1.5VA
50 – 60 Hz 0.72 /6KV
Direction of
current flow
S1 S2

CT- Meter Connection cables


2.5 sq mm length = 1.6m
S1 = white
S2 = Black

S1 S2

Cable hole
through the CT

Ensure the CT is
fully shut and the
locking clip is
closed

Split CT P2 Split CT
hinge Locking clip

SPLIT CORE CT
SCTK68 1B - 35
150A/5A 1.0 1.5VA
50 – 60 Hz 0.72 /6KV

S1 S2

CT- Meter Connection cables


2.5 sq mm length = 1.6m
S1 = white
S2 = Black

Instructions for installation:


Note: The system should not be energised whilst installing
 Check the meter CT ratio setting corresponds to the CTs supplied.
 Ensure all CTs are the same current ratio (e.g. all 100/5A).
 Open clip and fit the CT around the cable to be monitored. Follow the arrow on the side of the
CT for installation direction.
 Ensure all CTs are installed the same way.
 Ensure the CT is fully closed and the clip is secure.
 Make the ‘S1’ (white) & ‘S2’ (black) connections to the meter.
 Ensure that the relevant CT is terminated for each relevant phase (i.e. L1 phase = CT1 etc).
 Ensure all connections are tight and energise the meter.
 Carry out the tests as described above.

Page 3 of 3