0% found this document useful (0 votes)
331 views8 pages

Leakage Control in CFRD

This document discusses concepts for controlling leakage in concrete face rockfill dams (CFRDs). It describes zoning designs that define the functions of different embankment zones, including a Zone 1 impervious soil blanket and Zone 2 semi-impervious rockfill layer near the concrete face. An important construction innovation called the "Itá Method" replaced compaction along the concrete face with an extruded concrete curb, improving construction. Case studies of large CFRDs like Campos Novos, Tianshengqiao 1, El Cajón, and Shuibuya illustrate maximum cross-sections and construction views. Strict rockfill construction methods like thin layers and vibration compaction were needed to control settlements of tall CFRDs

Uploaded by

Samoon Ibrahim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
331 views8 pages

Leakage Control in CFRD

This document discusses concepts for controlling leakage in concrete face rockfill dams (CFRDs). It describes zoning designs that define the functions of different embankment zones, including a Zone 1 impervious soil blanket and Zone 2 semi-impervious rockfill layer near the concrete face. An important construction innovation called the "Itá Method" replaced compaction along the concrete face with an extruded concrete curb, improving construction. Case studies of large CFRDs like Campos Novos, Tianshengqiao 1, El Cajón, and Shuibuya illustrate maximum cross-sections and construction views. Strict rockfill construction methods like thin layers and vibration compaction were needed to control settlements of tall CFRDs

Uploaded by

Samoon Ibrahim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

 

    ISSMGE Bulletin: Volume 3, Issue 4                       Page 11 

Case History
Concepts on CFRDs Leakage Control ‐ Cases and Current Experiences 

Manoel S. Freitas Jr. –   Consulting  Engineer   
[email protected] 
 
1. Introduction 
 
Concrete Face  Rockfill Dams (CFRDs) technique has been extensively used especially in 80s and 90s in design and construction of several rockfill 
dam structures with heights ranging from 140 to 190m, such as: Foz do Areia (Brazil, 160 m),  Xingó ( Brazil, 145m), Aguamilpa (Mexico, 187m) and 
Segredo ( Brazil, 145m).  This tendency has been effectively followed in the last decade too for some other iconic projects like: Tianshengqiao 1‐ 
TSQ.1 (China, 178 m), Sanbanxi (China, 186 m), Hongjiadu ( China, 192 m),  Barra Grande ( Brazil, 185 m), El Cajón  (Mexico, 188 m), Kárahnjúkar 
(Iceland, 190m),  Bakun ( Malaysia, 205m), Campos  Novos (Brazil, 202m) and Shuibuya (China, 233m)  the tallest CFRD  structure ever made.  Mazar 
(Ecuador, 166 m), Porce III  (Colombia, 160m) and La Yesca (Mexico, 210 m) and Jiangpinghe (China 219m)  ‐ still under  construction ‐  are equally 
excellent  examples  of  CFRDs  progress  and  use.    However,  during  the  90s  decade,    some  crack  events  occurred  in  several  CFRDs,  such  as:  Xingó, 
Aguamilpa, Itá and Itapebi (Brazil), and the dam leakage reached up to 1000 to 1800 l/s ( Itapebi and Ita CFRDs).  Remedial slab treatments have 
been  implemented  and  leakage  flow  rates  dropped  below  200  l/s  during  operation  period.    More  recently,  several  unpredicted  slab  ruptures 
occurred in Tianshengqiao 1 (2003 and 2004) during reservoir operation, and Campos Novos and Barra Grande in 2005, as well as in Mohale in 2006 
during first reservoir impounding.  In these CFRDs, due to the slab horizontal stresses, a sudden concrete spalling rupture along vertical joints at slab 
center areas was followed by significant dam leakages of around or higher than 1000 l/s  in Campos Novos and Barra Grande and 600 l/s in Mohale.  
Currently and mainly for CFRDs with heights > 190 m, rockfill zoning, compaction procedure control and changes of the perimeter and vertical joints 
design for slab strain control have been implemented.  However, tall CFRDs structures (heights > 250 m) face new dam behavior challenges and 
cracking control during impounding.  
 
 
2. Rockfill  Zoning 
 
CFRDs zoning designations is one of the most important concepts (Cooke and Sherard 1987). They clearly define the functions and requirements of 
each zone of the embankment and allow the exchange of information between CFRDs designers and constructors. These zoning  concepts are still 
present in the large majority of the dams.  Figure 1 reproduced from Cooke and Sherard (1987) show the original zoning designations. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Figure 1 Zone designations for CFRD of Sound Rockfill (Cooke and Sherard,1987) 
 
“Zone 1 – A compacted blanket   impervious soil“ was placed on the lower part of the concrete face at Alto Anchicaya Dam (1974). This detail has 
since been repeated on the Areia, Khao Laem, and Golillas Dams and in several other tall dams. The purpose is to cover the perimeter joint and slab 
in the lower elevations with impervious soil, preferably silt, which would seal any cracks or joint openings. In addition, dams without this upstream 
Zone 1, have been completely successful.  
 “Zone 2 – Such select grading of Zone 2 provides a semi‐impervious barrier, preventing any large leakage, even if a leakage path develops through a 
crack in the concrete slab or a defective water‐stop. Crusher‐run minus‐15‐7.5 cm rock fill has been used”. The semi‐pervious property is of value 
near the perimeter joint, and to an elevation where flood retention during diversion could rise, before the placement of the concrete face. The early 
and primary purpose of the thin zone of finer rock directly under the slab (cushion zone) was to provide uniform and firm support for the concrete 
slab. 
     ISSMGE Bulletin: Volume 3, Issue 4                       Page 12 

Case History 
Concepts on CFRDs Leakage Control ‐ Cases and Current Experiences 
(continued) 

An important and revolutionary construction procedure was introduced at Itá CFRD ( 1999) by the main civil constructor (Resende, Materón, 2000). 
An extruded concrete wall built as support for the concrete face replaced all the troublesome operations of compaction along the slope of zone 2 
and eliminates the asphalt emulsion or the shotcrete spray.  Benefits of this curb, nominated by Cooke like “The Itá Method” and from 1999 on has 
been adopted in all CFRDs already constructed in the World. Figures 2a and b, show the curb details and curb extruding machine. 
 

79‐75 Kg 
60‐75 Kg
Cement/m33
Cement/m

(a) Curb Detail   
(b) extruding machine (El Cajón CFRD)  
(Méndez, Marengo, 2008) 
Figure 2: The ”Itá Method” ( Resende, Materón , 2000) 
 
Figures  3,  4,  5,  and  6,  present  for  Campos  Novos,  Tianshengqiao  1,  El  Cajón  and  Shuibuya,  respectively,  maximum  cross    section    zoning,    and  
upstream view , as well.   
 

(a)  (b) 
Figure 3: Campos Novos : cross section – (a) (Courtesy of Oficina de Textos, Editor)  and (b)  upstream view   in the end of construction 
 
 

(a)   
(b) 
Figure 4: Tianshengqiao 1 (TSQ.10 : cross section – (a) (Courtesy of Oficina de Textos, Editor)  and  (b) upstream view   in the end of construction 
(2000) 
     ISSMGE Bulletin: Volume 3, Issue 4                       Page 13 

Case History
Concepts on CFRDs Leakage Control ‐ Cases and Current Experiences 
(continued)

(a) 
(b) 
Figure 5: El Cajón : cross section – (a) (Courtesy of Oficina de Textos, Editor)  and  (b)  upstream view   in the end of construction (2006) 
 

(a)  (b) 
Figure 6: Shuibuya : cross section – (a) (Courtesy of Oficina de Textos, Editor)  and (b) upstream view   in the end of construction (2007) 
 
Rockfill construction specified thickness layers restricted to 0.5 m to 1 (one) meter  (max.) at upstream zone,  dumping  and  spreading facilities 
avoiding  intense segregation,  compaction  by using 10 to 12 ton vibrator rollers ( 6 to 8 passes) and rockfill watering facilities ≥ 250 liters/s  have 
been  implemented as international proceedings.  Remarkable  vertical settlements were recorded for high CFRDs, such as:   Foz do Areia : 3,80 m; 
Segredo  :  2,22m;  Xingó  :  2,90  m;  TSQ.1  :  3,20  m.    Monitoring  data  showed    that  80  to  90  %  of  the  total    dam  settlements  (construction  + 
impounding)   were recorded during construction period.   
CFRDs as an inherent safe structure  have  been designed and constructed, so far,  as an interesting alternative in time and costs comparatively with  
RCC ‐ Roller Compacted Concrete dam alternative. 
Recorded deformations on construction and after impounding showed  that  rockfill  construction methodology and valley shape factor effect (A / 
2
H  ; where A is the face slab area; H is the max. dam height)  have  influenced  significantly  CFRDs deformations  at  plinth abutment areas and  slab 
center parts.  In 80s and 90s,  CFRDs  design  have specified selected sound or  low weathered rock from required excavation for upstream shell 
zone.  Construction deformation modulus ranged from 40 to 70 MPa, such as Foz do Areia, Segredo, Xingo, Khao Laem.  Weathered  rocks  were 
used ( Xingó and Tianshengqiao 1) with special consideration of rock properties, placement procedures, zoning and drainage provisions (Cooke, J.B., 
1991). Alluvium coarse materials (deformation modulus ranged from  100 to 350 MPa),  were successfully used in several dams: Salvajina, Golillas 
and Aguamilpa (upstream shell).  Table 1 shows several   CRFDs features.   
 
3. Plinth and Conceptual evolution of the Perimeter joint 
 
The plinth as is usually the name used for the toe slab has an important role in the performance of CFRD structures: the control of the flow through 
the foundation, because in the upstream side is the reservoir and behind the plinth the rock fill. Foundation requirements as mentioned by Cooke 
and Sherard are essential. Whenever the foundation is not in sound rock, other treatments are specified.  
     ISSMGE Bulletin: Volume 3, Issue 4                       Page 14 

Case History 
Concepts on CFRDs Leakage Control ‐ Cases and Current Experiences 
 (continued) 
Good  correlations  have  been  obtained  between  geomechanical  classification  of  the  rock  foundation  and  the  required  gradient  to  be  applied  to 
prevent the erosion of the plinth (Cruz, Materón, Freitas, 2008). Plinth structure is usually on “ hard, nonerodible fresh rock which is groutable. For 
less  favorable  foundation  rock,  after  a  trench  is  made  to  an  estimated  acceptable  foundation,  many  methods  are  available  to  treat  local 
imperfections. The criterion is to eliminate the possibility of erosion or piping in the foundation. Careful excavation is used to minimize fracturing of 
the rock surface on which the toe slab is placed. Air or air‐water cleanup, just prior to placing concrete, is required to obtain a bonded contact of the 
concrete to the foundation.” ( Cooke, Sherard, 1987) 
 
Since  1970´s,  the  main  factors  that  caused      perimeter    joint    movements  and  potentially  intense  dam  leakage    were:    rockfill    differential 
settlements from  construction  stages,  rock type  (upstream and downstream shells ), plinth  abrupt geometry foundation (at abutment areas) and 
valley geometry.  
Perimeter  joint design evolution has progressed from  the “simple concept” ‐  one central rubber waterstop and/ or  bottom copper backed by a 
concrete pad,  Cethana Dam– 1971,    to a    “double  or multiple defense concept”, as  Alto Anchicaya Dam ‐1974,   with two waterstops, one made 
of  copper  (bottom)  and  a  center  one  made  of  PVC,  and  a  mastic  cover.    Foz  do  Areia,    Segredo  and    Xingó    CFRDs  followed  similar  concept.  
However, Segredo and Xingó  have eliminated the center waterstop to ensure a better  concrete quality.  A sand‐asphalt pad and a filter material (φ 
max  =  1  ½”  )  under  the  slab    as    a  safe  and    leakage  control  feature,  have  been  designed  as  an  additional    defense  line,  as  an  international  
proceedings issue. 
An earthfill blanket at upstream deepest sections in river bed at  plinth and slab lower areas has been   built  as an international  practice, and  an  
additional protection in case of  cracking issue. 
Pinto and Mori (1988) presented a new defense concept, using  a “dirty fine sand”  over the perimeter joint.  Segredo (1993) and Xingó ( 1994)  have 
been designed  with a  “ fine sand  layer” over the perimetric joint as  an additional protection (“ clogging effect”), in case of the damage of the 
mastic.  Aguamilpa ( 1993) and Tianshengqiao 1( 2000), besides  double  waterstops placement,  a fly ash  material protected  by a geotextile wrap 
and a  metallic plate  (perforated) completed the perimeter joint design ( Figure 4, b).  In EL Cajon ( 2006)  a  multiple defense concept, similar  as 
designed for Aguamilpa and Tianhengqiao 1, was adopted and complemented by a addition of copper waterstop at joint upper part. 
 
Table 1 : CFRDs  Features 

Settlement Max. 
Complection  Dam  max.   Valley Shape  Settlement 
Dam (country)  Rock type  2 / dam max. 
Year  Height H (m)  Factor ‐ A/H   Max. (m) 
height (%) 

Alto Anchicayá 
1974  Hornfels ‐Diorite     140   1.1  0.77  0.55 
(Colombia) 
Basalt/Basaltic  
Foz do Areia (Brazil)  1980     160   5.4  3.52  2.20 
breccia  

Aguamilpa (Mexico)  1993  Gravel/Rockfill    187   3.9  1.70  0.90 

Basalt/Basaltic 
Segredo (Brazil)  1993    140   4.4  2.23  1.59 
breccia 

Xingó (Brazil)  1994  Granite‐Gneiss    140   6.9  2.90  2.07 

Itá( Brazil)  2000  Basalt     125   7.0  1.30  1.04 


Limestone/Mudst
TSQ.1 (China)  2000    178   5.7  3.32  1.87 
one 
Machadinho (Brazil)  2002  Basalt    125   6.0  1.60  1.28 
Barra Grande (Brazil)  2005  Basalt   185   3.0  3.40  1.84 
Campos Novos (Brazil)  2005  Basalt   202   2.6  3.10  1.53 
El Cajón (Mexico)  2006  Ignimbrita   188   3.2  0.85  0.45 
Mohale (Lesotho)  2006  Basalt    145   3.6  2.86  1.97 
Kárahnjúkar (Iceland)  2007  Basalt   190   2.7  1.53  0.81 
Limestone / 
Shuibuya ( China)  2008   233   2.6  2.47  1.06 
Mudstone 
Bakun (Sarawak –  Greywacke/shale
2008*   205   3.0  2.28 *  1.37 
Malaysia)  /mudstone 

Mazar (Ecuador)  2009*  Quartzitic schists   166   1.7  1.28*  0.77 

(*) end of construction 
 
     ISSMGE Bulletin: Volume 3, Issue 4                       Page 15 

Case History
Concepts on CFRDs Leakage Control ‐ Cases and Current Experiences 
(continued)
In China,   rubber  sealing materials  have been used as “GB” and “ SR”  replacing the  “IGAS” material  (Guocheng and Keming, 2000).  GB filler 
material  combined  with  a    corrugated  GB  rubber    joint,    (  Figure  7)  designed  and  manufactured    by    China  Institute  of  Water  Resources  and 
Hydropower Research (IWHR), Beijing, were applied  in  Shuibuya, Bakun and currently Mazar  CFRD  (166 m, under construction),  (Cruz, Bayardo, 
Freitas, 2009). 
For CFRDs structures higher than 200m such as Shuibuya, 233m (2008),  Bakun, 205m (2008), Campos Novos,  202m, ( 2005  ), a perimeter joint  
“multiple defense concept”  has  been successfully designed and implemented.  
 

 
Figure 7– Corrugated Joint adopted in Shuibuya ( China), Bakun ( Malaysia) and  Mazar (Ecuador) 
Cruz, Materon, Freitas , 2009  ( Courtesy of OFICINA DE  TEXTOS,   Editor)  
 
Reinforcing bars placed in plinth (perimeter joint) and in the face slab seek to reduce concrete  shrinkage, and to  minimize cracks  developed  from  
bending strains imposed mainly during  reservoir impounding. Two layers of longitudinal steel have sometimes been used in the past. Recently, it is  
generally accepted that a single layer should be used. The steel is put 10 ‐ 15 cm clear of the upper surface as temperature steel, where it is hooked 
by the anchors: 0,3% each way appears adequate.  The purpose of the anchors is simply to pin the concrete to the rock. The anchors are not to 
resist any given uplift loads. 
Plinth  construction  progress  continually  in  sections  (each  50  to  80m  aprox.),  with  construction  joints,  without  waterstops.  The  longitudinal  
reinforcement steel passing through the construction joint represents as a good practice solution (Cruz, Bayardo, Freitas,  2008). Construction joint 
green cutting joint treatments are used commonly before re‐start concrete pouring. 
 
4. Vertical and horizontal joints  
 
4.1 Horizontal joints 
 
Horizontal  construction  joints  have  been  designed  and  constructed  according  to  the  face  slab  construction  stages,  2  to  3,  as  an  international 
practice.  Horizontal joints treatment before next slab stage consist  in removing some centimeters of the  pre‐existent concrete,  surface cleaning 
with air or green cutting facilities to remove exposed aggregates. The reinforcement steel being continue is overlapping the next concrete pouring 
stage. Construction joint should not be considered as contraction joints, waterstops are not required as unnecessary and expensive according to 
good engineering practices. 
 
4.2  Slab – plinth connection joints 
 
Aiming  to sealing protection (in case of cracks)  improvement,  at a “L” distance (often ranged from 10 to 20 m) from the plinth,  an additional joint 
sealer (besides of the copper joint sealer at the slab bottom) has been installed in some  CFRDs structures.  In TSQ.1, an additional PVC joint sealer 
has been designed embedded along slabs vertical joints at a distance of L = 20m from the plinth.  
In Barra Grande and Campos Novos CFRDs,  a PVC cover has been designed over the slab vertical joint top at a distance L = 20m from the plinth.  
However, these sealing protection systems have often shown troubles during construction stages to keep a good concrete pouring in these restrict 
parts, besides difficulties in maintaining the alignment of the PVC joint during the slipping form works (Cruz, Bayardo, Freitas,  2009).  
Drainage  facilities  at  upstream  lower  areas  during    construction    are    mandatory  to  control    and    to  protect  against  slabs    uplift    (bulging 
displacements)  along perimeter joint due to relevant  piezometric head   pressures  in  rockfill river bed low parts at  plinth areas.   
 
4.3 Vertical joints 
 
Vertical joints are “contraction joints” ‐ between slabs, which means, no steel bars trespassing between slabs are required, ‐ current international 
practice. Two different design concepts have been followed according to slab areas:  at abutments (tension zones) and center part  (compression 
zone).    At  abutment  areas  (tension    zones),  where    joint    openings  are  predicted,  tension  joint  designs    have    progressed    to  a  double    defense 
concept  as  a common practice,  a copper joint sealer  installed at the  slab bottom,  and a second joint sealer (JEENE type, or  PVC) on the joint top.   
     ISSMGE Bulletin: Volume 3, Issue 4                       Page 16 

Case History 
Concepts on CFRDs Leakage Control ‐ Cases and Current Experiences 
(continued) 
 
This practice has been  adopted   in several  CFRDs, such as : Itá  (1999), Itapebi (2002),  Machadinho (2002), Campos Novos ( 2005) and  Barra 
Grande ( 2005) (Figure 8 b).  
Aguamilpa and Tianshengqiao 1 followed the similar concept, a double water stop (copper at bottom and a PVC at center part) and an additional  fly 
ash ( coal ash in case of TSQ.1) on the joint top, protected by a geotextile wrap and metallic perforated cover.   
In Itá CFRD was introduced the extruded curb, for the first time, over   the upstream slope (cushion  zone) protection thus replacing the traditional 
compaction and asphalt coat protection alternative.    

 
 
Slab Central areas (compression zones): vertical joints in center areas (compression  zone)  have been designed with a  bottom  copper joint only as 
standard  solution  (Figure  8a).    In  addition,    a  V‐  notch  (  10  x  10  mm)  at  upper  part    and  an  asphalt  paint was  applied  along  concrete  joint.  This 
practice  was  adopted until year 2005.   
Cracking and concrete spalling phenomenon was initially recorded in  Tianshengqiao 1 (2003, 2004),  after three years of operation ‐ Figures 9 and 
10.      Barra  Grande  ‐  Figure  11,    and  Campos  Novos  (2005),  Figure  12,    and  Mohale  (2006),  Figure  13,    during  the  reservoir  impounding,  have 
recorded similar spalling issues. Slab horizontal compression strains due the combination of following dam features: dam height, low construction 
rockfill deformation modulus and valley shape ( Pinto, N. , 2007),  seem  to give  an explanation for this problem. 
To mitigate this cracking phenomenon,  a new vertical joint concept has been adopted, according to  the following items: i) mortar pad imbedded  
into the  curb  extruded concrete  (keeping the original slab thickness design); ii) flexible filler along vertical joint (wood, neoprene); iii) to reduce 
(maximum 2 mm) or eliminate the upper V notch;   iv) anti‐spalling reinforcement.   
 
   
   
   
   
   
   
   
   
   
   
   
   
Figure 9 ‐ Tianshengqiao 1 concrete spalling along  Figure 10 ‐ Tianshengqiao 1 : horizontal reinforcement 
Center slabs L3 and L4 ( 2003)  bending  along vertical joint (slabs L3 & L4) 
 

Figure 11 ‐ Barra Grande   Figure 12 ‐ Campos Novos  Figure 13 ‐ Mohale (March 2006) 


(Sept. 2005)  ( Oct. 2005) 
 
     ISSMGE Bulletin: Volume 3, Issue 4                       Page 17 

Case History
Concepts on CFRDs Leakage Control ‐ Cases and Current Experiences
(continued)
In TSQ.1,  concrete spalling at face slabs were caused  by  concentrated  stress along vertical joints slabs L3 and L4.  A  maximum horizontal strain 
recorded was ‐912μ  ( in strain gage SGH20)  (where minus means compression) in June 2003 ( Keming and al. 2007) just before rupture and spalling 
( Figures 9 and 10).     This monitored  strain corresponds to a  failure compressive  rupture ≈ 22 MPa ( Econc = 24.000 MPa).  In Mohale,   during 
concrete  spalling    along  vertical  joint  L  17/  L18  ,    horizontal  strains    ranging  from  ‐600  to  –  620  μ  have  been  recorded,  which  means  a  failure 
compressive  rupture   ≈ 20 M Pa (  Palmi,   Tohlang, 2007). The usual specified concrete is a pozzolanic cement with strength between 20 and 25 
MPa  at 28 days,  (sometimes this strength  is specified for 60 or 90 days).  Therefore,  Mohale and TSQ.1 slabs should not  have  collapsed  probably 
by horizontal compressive  strain only, but due to the bending stresses. Horizontal reinforcement  bending  (Figures  10  and 13) confirmed this 
hypothesis.  Barra Grande ( Figure 11) and Campos Novos with a similar spilling phenomenon ( Figure 12) must be followed the same behavior.  
 
Barra Grande, Campos Novos and Mohale CFRDs, have in common low construction modulus of deformability (40 – 70 MPa) and relatively narrow 
valley (Valley Shape Factor of 3.0, 2.6 and 3.6 respectively). (Pinto N.,2007).  Tianshengqiao 1   has also low construction modulus of deformability ,  
ranged 30 – 48 MPa. (Wu, Freitas and al., 1999), but a high Valley Shape Factor ( 5.7).  
Despite the necessity of having a high rockfill modulus of deformability (> 90 MPa), in order to avoid high deformations, narrow Valley Factor deep 
influence  in  rockfill  performance  and  slab  deformations  are    not  clearly  explained,  so  far,  in  this  author  view.    Reservoir  water  level  pressure  
induces rockfill deformations from center areas toward dam top and consequently slab high deflections along all these areas.  Since  CFRDs spalling 
issues ( 2003 – 2006), center vertical joints have been designed  with  a flexible filler  material between slabs,  consisting of wood or PVC or similar 
materials, to mitigate compression stresses (Materón, 2008). This “compressive fill concept” along the vertical joint was applied during the repairing 
works at Barra Grande and  Campos Novos. Currently has been adopted in several tall CFRDs, such as: Shibuya, El Cajón, Kárahnjúkar  (Figure 14) , 
Bakun and Mazar.  
 
 
 
 
 
 
 
 
 
Figure 14  Kárahnjúkar face slab at central compression zone, modified design ( Perez, 
Joahannesson & Stefansson,  2007). 
 
Slabs current   experiences show a tendency to generate high stresses close to abutments. Therefore, the use of 0.5% reinforcing in area of 25‐30m 
perpendicular to the plinth alignment has been recommended. Also in high dams located in narrow valleys anti‐spalling compression rebars have 
been located in two layers increasing the percentage to 0.5%  as protection against high compression stresses.  For current CFRDs, the following 
design  criteria  are  being  adopted  along  vertical  joint:  i)    keep  the  slab  design  thickness  by  imbedding  the  mortar  pad    into  the    curb    extruded 
concrete; ii) use flexible filler along vertical joint ( wood, neoprene, etc ); iii)  reduce (maximum 2 mm) or eliminate the upper V notch;   iv) anti‐
2
spalling reinforcement.  In addition, for narrow valleys ( Shape Factor   A / H  ≤ 3.0), additional vertical joints (7.5 m slab wide) must be considered 
at abutments  areas to mitigate stresses, as  adopted  at Shuibuya, Bakún and  Mazar CFRDs.  
 
4.4 Expansion joints: are placed  as a connection between the slab upper part  and the parapet wall crest wall. Although localized some meters 
above the Normal Water Level operation, the expansion joint design is a key point for a good slab leakage control. A copper waterstop is often used 
in this expansion joint. 
 
5. Final Comments 
 
Mathematical models and numerical FEM analysis are interesting designing tools to estimate the deformation pattern and slab bending movements 
of  the  embankment  deformations  during  construction  and  impounding,  and  in  the  long  run  (dam  operation)  due  to  the  rock  fill  creep  effect.  
However, empirical design and construction  details   from  experience and observation of CFRDs performance still prevails, significantly, so  far.  
Tall CFRDs structures ranging between 250 and 300m are being currently in feasibility studies. Therefore, basic criteria design proposed by Cooke 
and Sherard in  1987, are under  review. A better   estimation  of the  rockfill and  concrete face displacements and  inter face stresses  of rockfill, 
extruding curb and concrete slab must be  deeply concerned  in  mammoth CFRDs structures taller than 300m,  to avoid ruptures and high leakage 
issue.  Central  vertical  (compression)  joints  current  design  concept,  introducing  wood,  neoprene,  flexible  materials,  has  aiming  to  mitigate  high 
compression and bending stresses and bending movements along vertical joints. Slab spalling ruptures recorded in  Mohale and Tianshnegqiao 1  
CFRDs,  cannot  be  explained  as  horizontal  compression  stress  issues,  only.    Bending  stresses  seem  to  have  caused  bending  of  the  rebars  and 
concrete spalling  as the main effect. Similar phenomenon occurred in Barra Grande and Campos Novos, in this author opinion. 
Bond‐breaker design concept, as asphalt emulsion or other materials, placed between the slabs and curb face have not clearly proved as a good 
solutions to mitigate interface friction in the contact curb x slab, in this author view.  
The  spalling mentioned  accidents that occurred just confirm the inherent safety of the  tall CFRDs dam type. A recent earthquake (2008) of 8.0  
(Richter)  magnitude  occurred  in  Zipingpu  CFRD  (China,  160  m  height),  with  the  epicenter  at  10  km  from  the  dam,    registered  a  horizontal 
acceleration of 2g at crest level. A settlement of 40 cm in the crest, some slabs damaged and an increase in the  
     ISSMGE Bulletin: Volume 3, Issue 4                       Page 18 

Case History 
Concepts on CFRDs Leakage Control ‐ Cases and Current Experiences 
(continued) 
leakage flow from 10 to 15 l/sec were the only consequences. The dam resisted quite well the earthquake, confirming inherent safety conditions 
(Zeping X.,  2009). 
 
6. References 
 
1. Cooke, J.B.; Sherard, J.L.(1987) , “ Concrete Face Rockfill Dams: 1. Assessment;II. Design.  
Journal of Geotechnical Engeineering, ASCE,v.113,1987. 
2. Resende, F.; Materón, B., (2000) “ Itá Method – New Construction Technology for the Transition Zone of CFRDs. ICOLD, Beijing, China 2000. 
3. Méndez F.; Marengo, H.M, ( 2008) , “ Extruded curb technology and a fast‐track high CFRD” Key Technology for High CFRDs Construction – 
International Sympos., Hong Kong,    China. 
4.  Cooke, J.B.,(1991), “ The Concrete‐faced rockfill dam” – Water Power & Dam Construction – January 1991. 
th
5.  Pinto, N.L.S., Mori, R.T. ( 1988),   “ A New Concept of a Perimetric Joint for Concrete Face Rockfill Dams”  – Proceedings , 16  Congress of  
ICOLD , Q61,  San Francisco, USA, 1988. 
6  Guocheng, J., Keming, C. (2000), “ Concrete Face Rockfill Dams in China“ ‐ Proceedings  of  International Symposium on High Earth‐Rockfill 
Dams, Vol. I –Oct.  1993, Beijing, China. 
7.  Cruz, P., Bayardo ,M., Freitas, M.S., (2009) ” Concrete Face Rockfill Dams” , Oficina de Textos, Editor, 2009.  
8.  Cruz, P., Bayardo ,M., Freitas, M.S.,  (2008) “ Design Criteria for CFRDs “, Key Technology for High CFRDs Construction – International 
Symposium , Hong Kong, China. 
9.  Pinto, N.J. de S. ( 2007) , “ The Design and Construction of Extra High CFRDs, Third International Symposium on CFRDs, Florianopolis, SC, 
Brazil. 
10.  Keming, C, Zhongping and Caichang Guang (2007) ,  “ Design Research for very High  CFRD” ,  Workshop on High Dam Know‐How, May 22 ‐24, 
Yichang, China. 
11. Johannesson, P., Tohlang, S., ( 2007), “ Updated Assessment of Mohale Dam Behavior, including of slab cracking and seepage evolutation”, 
Third Symposium on CFRD –Dams, Oc. 2007, Florianopolis, SC, Brazil. 
12. Wu, G., Freitas, M.S. and al. (1999), “ Tianshengqiao 1 CFRD‐ Monitoring of the Rockfill Dam displacements”, Proceedings of 99` Internacional  
Conference on Dam Safety and Monitoring”, Three Gorges Project Site, 1999, China. 
13. Materón, B. ( 2007) : “ State of Art of Compacted Concrete Face Rockfill Dams “(2007) ,   Workshop on High Dam Know‐How, 2007, Yichang, 
China . 
14.  Perez, H.J.; Johannesson, P.;Stefansson, B., (2007) “ The Kárahnjúkar CFRD in Iceland Instrumentation and First Impoundment Dam Behavior”, 
Third International Symposium on CFRDs, Florianopolis, SC, Brazil. 
15. Zeping Xu, ( 2009) , “ Performance of Zipingpu CFRD during the Wenchuan earthquake”, Hydropower & Dams, Issue three, 2009. 
 
 
 
 

You might also like