Project Management Path Analysis

The document presents an activity-on-node (AON) network for Carl Betterton's construction project which consists of 8 activities with various predecessors. The critical path for the project is activities A-C-F-H with a total project duration of 21 days. It also shows the early start, early finish, late start, late finish, and slack times for each activity.

Uploaded by

Châu Giang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
337 views16 pages

Project Management Path Analysis

The document presents an activity-on-node (AON) network for Carl Betterton's construction project which consists of 8 activities with various predecessors. The critical path for the project is activities A-C-F-H with a total project duration of 21 days. It also shows the early start, early finish, late start, late finish, and slack times for each activity.

Uploaded by

Châu Giang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 16

Problem 3.

5
Carl Betterton's construction project

IMMEDIATE
ACTIVITY PREDECESSOR(S) TIME (DAYS)
A - 3
B A 4
C A 6
D B 6
E B 4
F C 4
G D 6
H E, F 8

Draw the activity-on-node (AON) project network associated with the following activities for Carl Betterton's construction p

START A E

Forward Pass Backward Pass


Activity Immediate Predecessor(s) Time(days) ES EF LS LF
Start 0 0 0
A - 3 0 3 0 3
B A 4 3 7 5 9
C A 6 3 9 3 9
D B 6 7 13 9 15
E B 4 7 11 9 13
F C 4 9 13 9 13
G D 6 13 19 15 21
H E, F 8 13 21 13 21
Total 41

How long should it take Carl and his team to complete this project?
Ans: 21 days
What are the critical path activities?
Ans: A-C-F-H
for Carl Betterton's construction project

D G

Slacks (LS-ES) On CP

0 Yes
2 No
0 Yes
2 No
2 No
0 Yes
2 No
0 Yes
Problem 3.6
Given the activities whose sequence is described by the following table:

IMMEDIATE
ACTIVITY TIME (DAYS)
PREDECESSOR(S)

A - 5
B A 2
C A 4
D B 5
E B 5
F C 5
G E, F 2
H D 3
I G, H 5
Draw the appropriate activity-on-arrow (AOA) network diagram

B D
22 3

A
B

11 4

A
22 55
C F

Forward Pass Backward Pass


Activity Immediate Predecessor(s) Time(days) ES EF LS LF
Start 0 0 0
A - 5 0 5 0 5
B A 2 5 7 6 8
C A 4 5 9 5 9
D B 5 7 12 8 13
E B 5 7 12 9 14
F C 5 9 14 9 14
G E, F 2 14 16 14 16
H D 3 12 15 13 16
I G, H 5 16 21 16 21
Total 36
a) Which activities are on the critical path?
Ans A-C-F-G-I
b) What is the length of the critical path?
Ans 21 days
D
7
H

8 I
E

G
66
F

Slacks (LS-ES) On CP

0 Yes
1 No
0 Yes
1 No
2 No
0 Yes
0 Yes
1 No
0 Yes
Problem 3.8
Roger Ginde

IMMEDIATE
ACTIVITY TIME (DAYS)
PREDECESSOR(S)

A - 2
B - 5
C - 1
D B 10
E A, D 3
F C 6
G E, F 8

a) Develop an AON network for this problem

A E

START B D

C F

Forward Pass Backward Pass


Immediate Slacks (LS-
Activity Time(days) ES EF LS LF
Predecessor(s) ES)
Start 0 0 0
A - 2 0 2 13 15 13
B - 5 0 5 0 5 0
C - 1 0 1 11 12 11
D B 10 5 15 5 15 0
E A, D 3 15 18 15 18 0
F C 6 1 7 12 18 11
G E, F 8 18 26 18 26 0
Total 35

b) What is the critical path?


Ans B-D-E-G
c) What is the total project completion time?
Ans: 26 days
d) What is the slack time for each individual activity?
Activity A B C D E F G
Slack time 13 0 11 0 0 11 0
E

On CP

No
Yes
No
Yes
Yes
No
Yes
Problem 3.9
Jim Goodale's Carbondale, Illinois

TIME (IN IMMEDIATE


ACTIVITY HOURS) PREDECESSORS
A 6.0 -
B 7.2 -
C 5.0 A
D 6.0 B, C
E 4.5 B, C
F 7.7 D
G 4.0 E, F

a) Draw the project network using AON

A C E

START

B D

Immediate
Activity Time(hours) ES EF LS LF Slacks (LS-ES)
Predecessor(s)

Start 0 0 0
A - 6 0 6 0 6 0
B - 7.2 0 7.2 3.8 11 3.8
C A 5 6 11 6 11 0
D B, C 6 11 17 11 17 0
E B, C 4.5 11 15.5 20.2 24.7 9.2
F D 7.7 17 24.7 17 24.7 0
G E, F 4 24.7 28.7 24.7 28.7 0
Total 40.4

b) Identify the critical path


Ans A-C-D-F-G
c) What is the expected project completion time?
Ans 28.7 hours
d) Draw a Gantt chart for the project.

Gantt Chart of Jim Go


0:00 2:24 4:48 7:12 9:36 Duratio
12:00
Tasks Start Time End Time
Duration Gantt Chart of Jim Go
(Hour:Minute)
0:00 2:24 4:48 7:12 9:36 Duratio
12:00
A 8:00 14:00 6:00
B 8:00 15:12 7:12 A
C 15:12 20:12 5:00
D 8:00 14:00 6:00 B
E 8:00 12:30 4:30
F 14:00 21:42 7:42 C
G 8:00 12:00 4:00
D

Task
E

G
E G

D F

On CP

Yes
No
Yes
Yes
No
Yes
Yes

Gantt Chart of Jim Goodale's Task


4:48 7:12 9:36 Duration
12:00 14:24 16:48 19:12 21:36 0:00
Gantt Chart of Jim Goodale's Task
4:48 7:12 9:36 Duration
12:00 14:24 16:48 19:12 21:36 0:00
Problem 3.10
Howard Corporation in Kansas

IMMEDIATE
ACTIVITY TIME
PREDECESSOR(S)

A - 9
B A 7
C A 3
D B 6
E B 9
F C 4
G E, F 6
H D 5
I G, H 3

a) Draw the appropriate AON PERT diagram for J.C.Howard's management team

START A

C F

Forward Pass Backward Pass


Immediate Slacks
Activity Time ES EF LS LF On CP
Predecessor(s) (LS-ES)
Start 0 0 0
A - 9 0 9 0 9 0 Yes
B A 7 9 16 9 16 0 Yes
C A 3 9 12 18 21 9 No
D B 6 16 22 20 26 4 No
E B 9 16 25 16 25 0 Yes
F C 4 12 16 21 25 9 No
G E, F 6 25 31 25 31 0 Yes
H D 5 22 27 26 31 4 No
I G, H 3 31 34 31 34 0 Yes
Total 52

b) Find the critical path


Ans A-B-E-G-I
c) What is the project completion time?
Ans 34 days