Jsa English Hindi
Jsa English Hindi
Sequence of
S No
1) proper PPE’s be use at work site such as safety helmets, shoes,gloves,glass,nose mask, ear
Barricaded the
1 Slip/Trip/fall to other people hazards plugs, ear muffs etc, and inform to the site in charge with caution tape. (2) Always Use
working area
Roko Toko Method when there is an unsafe act or in an unsafe condition
1) Properly cleared the area where the hot work is going to be done.
2) Proper trained worker be placed at the site of hot work who has trained to extinguish the fire
extinguisher. 3) Do not do hot without the permission
Hot work( Body burn hazard/eyes injury/physical injury of the fire department. (4) Use a fire blanket to prevent welding spot;s .. (5) where we are going
4
welding work ) hazards, Fire Hazard to do hot work , there should be any flammable liquid , cloths , paper , which is a flammable
material .
(6) Water & fire extinguisher should keep near of hot work.(7) There should be CMS stickers
on the welding machine ..
(1) Properly cleared the area where the grinding work is going to be done.(2) Proper trained
worker be placed at the site of hot work who has trained to extinguish the fire extinguisher. (3)
Do not do hot without the permission of the fire department. (4) Use a fire blanket to prevent
Hot work
Slip / trip / Body burn / physical injury hazards grinding spot;s .. (5) where we are going to do grinding work , there should be any flammable
5 (Grinding
/ cut injury / grinding spot , Fire Hazard liquid , cloths , paper , which is a flammable material .
Work)
(6) Water & fire extinguisher should keep near of hot work.(7) There should be CMS stickers
on the grinder machine ..
(8) Grinder Gaurd should be muct on attached grinder machine
(1) Properly cleared the area where the cutting work is going to be done.(2) Proper trained
worker be placed at the site of hot work who has trained to extinguish the fire extinguisher. (3)
Do not do hot without the permission of the fire department. (4) Use a fire blanket to prevent
Hot work Slip / trip / Body burn / physical injury hazards cutting spot;s .. (5) where we are going to do cutting work , there should be any flammable liquid
6
(Cutting Work) / cut injury / cutting spot hazard , Fire Hazard , cloths , paper , which is a flammable material .
(6) Water & fire extinguisher should keep near of hot work.(7) There should be CMS stickers
on the cutting machine ..
(8) Cutting machine Gaurd should be muct on attached Cutting machine
(1) Properly cleared the area where the Gas Cutting work is going to be done.(2) Proper trained
worker be placed at the site of hot work who has trained to extinguish the fire extinguisher. (3)
Do not do hot without the permission of the fire department. (4) Use a fire blanket to prevent
Slip / trip / Body burn / physical injury hazards
Hot work (Gas Gas Cutting sparks .. (5) where we are going to do Gas Cutting work , there should be any
7 / cut injury / cutting spot hazard , Fire Hazard
Cutting work ) flammable liquid , cloths , paper , which is a flammable material .
, Fall hazard by cylinders ,
(6) Water & fire extinguisher should keep near of hot work.(7)before the work start checked the
gas cylinders by authorized person
(8)use a tsutable rolley to bring and carry Gas cutting cylinders
1) Proper trained and authorized worker only allow doing height work.
Falls (from heights); 2) Work at height (WAH) medical should be must.
Trench collapse; 3) Proper use of full body harness while doing height work.
Scaffold collapse; 4) Do work in the presence of site in charge.
Height work Electric shock and arc flash/arc blast; 5)Anchor the full body harness in a well organized place or at an angle to strong anchor point
8
Using scaffold Failure to use proper personal protective when climbing a height ..
equipment; and 6) Scaffolds should not be loaded with more weight than they were designed to support.
Repetitive motion injuries. 7) Green tag is must while working in scaffold and red tag when stop the
work.
1) Proper trained and authorized worker only allow doing height work.
2) Work at height (WAH) medical should be must.
Falls (from heights);
3) Proper use of full body harness while doing height work.
FRP work on Trench collapse;
4) Do work in the presence of site in charge.
9 height using Failure to use proper personal protective
5) If there is no anchor point to anchor the Full body harness at the height , the worker must use
Monkey Ladder equipment; and Repetitive motion injuries.
the lifeline
6) Employees are not permitted to work on height in bad weather or high winds unless a
competent person has determined that it is safe to do so
Fall the materials from height 1) Proper use of Safety belts. 2) Properly checked the JLG
Collusion Hazards. machine. 3) Properly checked the Hydraulic jacks of the JLG machine.
Height Work
Hydraulic jack of machine failure 4) Authorized person is only allowed to
10 JLG Machine
Hazards. operate JLG machine. 5) Indictors and
use
Leakage of lubricants of machine hazards. back horn is must. 6) Lubricant part of the Machine should be checked
before operating it.
1) Hand Bracker M/c must be inspected daily by a Competent Person, typically the operat .
Dismantling 2) The worker is not allowed to use mobiles phone while working with bracker m/c
High sound level makes the people deaf/fall the
work by 3) Before using CMS checking sticker should be attached on M/c with
12 tools/physical injury hazards / eyes injury
JCB/HAND Permit. 4) Proper Use the PPe's such as safety Gloves, goggles,
hazards
bracker machine ear plug , nose mask , etc... 5) While breaking the concrete ,
cover it form all sides with polythene so that its dust not move here and there ..
Eyes injury hazards 1) Proper handling the materials while doing brick work and plaster work.
Brick
Skin damage hazards by cement powder mixed 2) Proper PPE’S be used. Safety gloves and safety goggle is must.
17 work/plaster
in RCC/PCC. 3) Proper trained worker be placed for work. 4) Use the strong rope while working on
work
height material shifting work ..
1) Proper handling the materials while working on Hot Bitumin wok 2) Properly cleared the
area where the bitumin work is going to be done. 3) Proper use the ppe,s such as safety, helmet,
Gloves , nose mask , goggle , Shoes etc , 4) The worker should be must aware for Road safety
rules 5) Proper trained worker be placed at the site of hot work who has trained to extinguish the
Bitumin Road Fire Hazards , Fire Explosion hazard , Eyes fire extinguisher. (6) Do not do hot without the permission of the fire department. (7) where we
21
Work Hazards , Slip trip Fall , Physical Injury Hazard are going to do Bitumin road work , there should not be any flammable liquid , cloths , paper ,
which is a flammable material .
(8) Water & fire extinguisher should keep near of hot work(9) Use Water Spray To Cool The
Fire Exposed Container.(10) Properly Control Traffic(11) Be Aware of Your Surroundings
(12)Avoid Blind Spots
1) Proper handling the sheet while working on height 2) Used good quality
OR standard rope to lift or lower the sheet 3)
Proper use the ppe,s such as safety, helmet, Gloves , nose mask , goggle etc
Sheet
Cut injury or steel splinters to hands and 4) Move the sheet up or down through at least two & three workers
Installation &
22 arms,/Eyes injury hazards/Fall hazard/ Physical 5) Use full bodyharness if you are higer than 1.8 m
Removing Work
injury Hazard/ Slip hazards 6) The worker should be must attached full body harness on Anchor point ..
@Height
7) One worker should be muct on holding the ladder while working the height work
8) While opening & instaling the sheet , the workers should stand at least 5
mtr away from the ground below
Thanks
नौकरी सुर ा िव े षण
बु िनयादी नौकरी
संभािवत खतरे सुर ा/िनयं ण थािपत िकए जाने चािहए
के चरणों का म
मां
साम ी को ऊंचाई से
िगराएं
1) सुर ा बे का उिचत उपयोग। 2) जेएलजी मशीन
िमलीभगत के
की ठीक से जांच की। 3) जेएलजी मशीन के
खतरे ।
ऊंचाई काय हाइडोिलक जैक की ठीक से जांच की। 4) अिधकृत
10 जेएलजी मशीन का को केवल जेएलजी मशीन संचािलत करने की
मशीन की िवफलता का
उपयोग अनुमित है । 5) इं िडकेटर और बैक हॉन ज री है । 6)
हाइडोिलक
मशीन को चलाने से पहले उसके ेहक भाग की
जैक
जाँच की जानी चािहए।
खतरे ।
1) े न/फराना का िनरी ण एक स म ,
िवशेष प से ऑपरे टर ारा ितिदन िकया जाना
चािहए।2) रगस और िस ल यों को यो होना
चािहए।3) SLI (सेफ लोड इं िडकेटर) और बैक हॉन
उ िन र लोगों को ज री है ।4) ऑपरे टर को हाइडा/बत के साथ काम
फराना एम/सी .
बहरा बना दे ता है /उपकरणों करते समय मोबाइल फोन का उपयोग करने की
ारा उपयोग करके
को िगरा दे ता है और साम ी अनुमित नही ं है ।5) हाइडा का उपयोग करने से पहले
11 ऊंचाई पर
को ऊंचाई/शारी रक चोट के चेकिल परिमट के साथ संल की जानी चािहए।6)
िनराकरण और
खतरों/आं खों की चोट के अिधकृत को ही हाइडा/ े न संचािलत करने
िनमाण काय
खतरों से न कर दे ता है की अनुमित है ।7) हाइडा मशीन के िलए ील गाड
ज री
है ।
खुदाई गई साम ी या अ
व ुएं जो िमकों पर िगरती
ह। 1) उ नन िकये जाने वाले े को काय ार
करने से पूव उिचत प से िच त एवं िकया
िवद् युतीय जायेगा।2) अिधक उ नन से बचने के िलए एक
खतरा। सव क ारा समय-समय पर खुदाई की गहराई की
जांच की जाएगी।3) अिधकृत को ही जेसीबी
उ नन े म पड़ता मशीन संचािलत करने की अनुमित है ।4) उस े के
हाथ से और जेसीबी है । अिधकृत की अनुमित के िबना उ नन काय
13
से खुदाई का काम न कर।
कट चोट/आं खों की चोट के 5) जब जेसीबी काम कर रहा हो तो उससे 3 से 4
खतरे । मीटर की दू री पर खड़े हों।6) थल भारी की
उप थित म काय
खुदाई िकए गए ग े /बैक कर।
िफिलंग म कामगारों का
िगरना।
1) आरसीसी/पीसीसी काय करते समय साम ी का
आं खों की चोट के
उिचत संचालन।2) उिचत पीपीई का इ ेमाल िकया
खतरे
जाए। से ी स और से ी गॉगल ज री है ।
3) उिचत िशि त कमचारी को काम पर रखा जाए।
आरसीसी/पीसीसी म िमि त
आरसीसी/पीसीसी/ 4) कं ीट का काम करते समय गम बूट्स अव
14 सीमट पाउडर से चा को
कं ीट काय होने
होने वाले नुकसान के
चािहए।
खतरे ।