Checklist For Normalization Before Energization Rev00

This document is a checklist for normalization before energization of electrical equipment. It contains 7 sections that outline steps to check circuits, equipment, cables, trip circuits, alarms, and auxiliaries. The checklist ensures connections and components are properly configured before energizing by having technicians verify things like CT and VT circuit connections, transformer components, cable terminations, trip link configurations, and auxiliary equipment connections. Upon completion, the checklist must be signed by technicians from the Customer Service Department, contractor, and transmission and construction contractor.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
242 views

Checklist For Normalization Before Energization Rev00

This document is a checklist for normalization before energization of electrical equipment. It contains 7 sections that outline steps to check circuits, equipment, cables, trip circuits, alarms, and auxiliaries. The checklist ensures connections and components are properly configured before energizing by having technicians verify things like CT and VT circuit connections, transformer components, cable terminations, trip link configurations, and auxiliary equipment connections. Upon completion, the checklist must be signed by technicians from the Customer Service Department, contractor, and transmission and construction contractor.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 4

NATIONAL GRID

Title: Index Number:


CL-NG-6460-003-001
Checklist of Normalization Before Energization Page Number: Revision Number:
1 of 4 00

1.0 Equipment General Data and Information

Substation
Bay/Panel
Equipment Serial No

2.0 Normalization Check List

Item Description Done Remarks


1. CT Circuits Normalization:
1.1. Make sure that all CT circuits are connected,
shorted, isolated, and single point earthed as per
the marked-up drawings.
1.2. Ensure proper connections and tightness for all CT
circuits by a screwdriver, and pull each wire gently
to ensure that all CT wires terminated properly.
2. VT Circuits Normalization:
2.1. Make sure that all VT circuits are connected, and
isolated as per the marked-up drawings.
2.2. Ensure proper connections and tightness for all VT
circuits by a screwdriver, and pull each wire gently
to ensure that all VT wires terminated properly.
3. Power Transformer & Outdoor Equipment:
3.1. Ensure that there is no temporary grounding or
shorting between phases of any
transformer/reactor winding (high side, low side,
and tertiary windings).
3.2. Confirm that all covers of mechanical protection,
outdoor boxes, and panels are properly closed,
tighten, and sealed.
3.3. Confirm that no oil leakage.
3.4. Confirm that NER grounding is properly earthed.
3.5. Confirm that there is no any temporary shorting
across the primary terminals of the NER.
Archiving System Website: http://ngridsa-apps/amas
NATIONAL GRID

Title: Index Number:


CL-NG-6460-003-001
Checklist of Normalization Before Energization Page Number: Revision Number:
2 of 4 00

3.6. On-load tap changer is set on the normal tap.


3.7. Confirm that capacitor bank door is locked and the
key is placed on its parking.
4. Power Cables:
4.1. Confirm that all power cables and its sheath are
terminated properly.
4.2. In the case of using a split core CT, confirm that all
cable sheaths are connected properly through ring
CT according to TES-P-104.08 figure 08-1.
4.3. Confirm that cable sheath is connected to link
boxes according to approved drawing.
4.4. Confirm that all cables are painted with anti-fire
paint.
4.5. Check that all cable entrances are filled with fire
stop material.
4.6. Check that all cable clamps are fixed properly.
5. Trip Circuits:
5.1. Ensure that all selector switches of instantaneous
over current and earth fault protection relay of bus
section and bus coupler are in out-position.
5.2. Confirm that all trip links (specially for UV and UF)
are connected as per approved final
settings/drawings.
6. Alarms:
6.1. Confirm that all links for alarms in all panels are
closed.
6.2. Make sure that there are no alarms on
annunciators, relays, and SAS HMI (as applicable).
7. Auxiliaries:
7.1. Confirm that there is no temporary shorting or
grounding available at auxiliary transformer & RMU
terminals.
7.2. Confirm that no oil leakage from the auxiliary
transformer.
7.3. Confirm that all cables are properly connected for
Archiving System Website: http://ngridsa-apps/amas
NATIONAL GRID

Title: Index Number:


CL-NG-6460-003-001
Checklist of Normalization Before Energization Page Number: Revision Number:
3 of 4 00

ACDB, DCDB, RMU, and auxiliary transformer.


7.4. Confirm that RMU fuses (if applicable) are properly
connected.
7.5. Tap changer of the auxiliary transformer is set on
the normal tap.

CSD Contractor T&C Contractor


Name
Sign.

Archiving System Website: http://ngridsa-apps/amas


NATIONAL GRID

Title: Index Number:


CL-NG-6460-003-001
Checklist of Normalization Before Energization Page Number: Revision Number:
4 of 4 00