Document Controller Procedure1
Document Controller Procedure1
Date: 22/03/2014
Project Document Control Procedure Revision: 01
Revision Status
TABLE OF CONTENTS
1. Purpose 1
2. Scope 1
4. Responsibilities 3
5. Procedure 4
6. Records 9
2.0 Scope
This Document Control Procedure cover the methods of controlling the flow, the continuous
up-dating, filing, storage, archiving and retrieval of all project documents/data generated in
the course of performance of works relating to the project. The aim of the procedure is to
achieve an efficient documentation control throughout the project tenure during the various
phases of the project.
b. Document Control – The office responsible for control, storage, retrieval, distribution
and revision of all documents originated, or received
QMS/PR/DC/001
Document Control Procedure|Page 2 of 21
c. Correspondence Control – The policies and procedures for this section are to specify
correspondence controls and procedures. Project participants shall use uniform
document formats and consistent processing practices. This policy will apply to e-mail as
well as traditional correspondence means.
d. Baseline Documents are drawings, specifications, standards, design criteria, and
program plans including budget and schedule approved by the project management
(QC, Commercial)
e. Third Parties – Include Sub-Contractors, Suppliers / Manufacturers, Design Consultants
f. Distribution Matrix – A master distribution list for all controlled documents approved by
the project head.
g. Definition of Document Types
QMS/PR/DC/001
Document Control Procedure|Page 3 of 21
Manager on site. Normally when a client and a
contractor jointly inspect the site, and if the client
CVI (Confirmation of Verbal
Instruction) wants something to be done immediately which is not
part of the Contract, he verbally tells it to the
contractor and the contractor, in return confirms it in
writing.
WIR (Work Inspection Request) code requirements. After building permit is issued,
Engineer inspect Building to make sure it is done
according to the approved plans and Drawings
Document Transmittal is used to formally dispatch
4.0 Responsibilities
Document Control is the management and administration of the Project documents,
including technical and engineering design data, contract and procurement
documents and management approved procedures, manuals, plans,
correspondence etc. within an EDMS system (If any). The Project documents are
subject to controlled distribution to ensure that changes and updates to key
documents are made in a controlled and systematic manner and that all parties are
working to the latest version of the documents.
Key Responsibilities
a. To ensure that client receives all relevant documents in a timely manner, in accordance
with requirements of the Contract Agreement.
b. To ensure the continuous logging of the document-flow (in/out) in the relevant registers
c. To ensure that the documents are stamped with the relevant approval information.
QMS/PR/DC/001
Document Control Procedure|Page 4 of 21
d. To ensure the timely distribution of the documents to the relevant parties as per the
approved Distribution Matrix.
e. To ensure that the status of each document is continuously up-dated on the relevant
registers.
f. To ensure that the revised documents are re-submitted to the recipients of the previous
revisions.
g. To ensure that the proper identification of the documents, their indexing and storage is
carried out in a manner that enables an easy and quick retrieval.
h. To ensure that the project EDMS system is being used as a tool for control and
retrieval of all project documentation throughout the project duration and retention
period.
i. “General Log” & “Overdue Report” are issued every Thursday, to enable the project
management team to monitor and expedite receipt and dispatch of drawings and
documents in a timely manner.
5.0 Procedure
A. General
i. Document Controller to establish “Distribution Matrix” & secure project head
approval. Distribution Matrix to be circulated to all project department’s
Manager. (Appendix C)
ii. All documents are identified with Number and Revisions. (Appendix A-Without
any alternation).
iii. All technical documents must be reviewed by the concerned department
managers prior to issue.
iv. All obsolete / old Revision must stamped as “Superseded”
v. The document controller is the responsible to recollect the distributed
documents/drawings of the superseded revision and stamp it as superseded
vi. All hard copy documents are filed in accordance with the QMS filing and coding
system. (Appendix F)
B. Procedures
i. QHSE Manager is responsible for the distribution of Revised Procedure.
ii. All Procedures are identified by a Ref. No and Revision No. The QHSE
Manager/Department maintains a register of all company procedures.
QMS/PR/DC/001
Document Control Procedure|Page 5 of 21
iii. Each procedure has a control table as first page which is identifying the revision,
date of issue and who prepared, reviewed and finally approved the procedure.
iv. All procedures are to include the following sections:
Purpose
Scope
Definition of Terms
Responsibilities
Procedure
Records(Attachments)
D. Tender Documents
i. The contracts Department maintain the original copies of the tender
specifications and drawings after being awarded a contract. All drawings and
specifications are marked as “Tender”.
ii. One copy of each is stamped as “Controlled” and given to the Project Head.
iii. In case of any change, the Contracts Manager copies the amendments as one
set and issues it to the Project Head marked as “Revised”. Previous revisions
are marked as “Superseded” and dated and kept with the controlled documents.
E. Construction Drawings(Project)
i. Drawings are received back from the Consultant with approval code indicating on
Submittal form as (Approved, Approved with Comments.
ii. Any copies of the drawings are also to be stamped as per the status of document
which is given by Engineer. Under no circumstances any drawing is issued to the
site without a “For Construction” Stamp should have “For Information/Advance
copy” stamp with approval of project head.
QMS/PR/DC/001
Document Control Procedure|Page 6 of 21
iii. In case of a change to a drawing, the revision is issued by the Project Design
Manager upon approval by the Engineer to the site. The Construction Manager is
responsible for distributing the revised drawing to the concerned construction
personnel and retrieving the superseded drawings to be handed to the document
controller to stamp as Superseded. The project Quality Manager issues an
updated drawing log on the weekly basis using email to all construction
personnel to enable them to check the latest revision status of the drawings.
F. Incoming Correspondence
i. All correspondence is given directly to the Project document controller.
ii. The document controller stamps the correspondence, identifying the date
of receiving and put distribution stamp.
iii. The document controller updates the correspondence log.
iv. The Document Controller distributes the document as per the approved
Distribution Matrix
v. The document controller presents the correspondence to the Project head as
soon as he is available. If Project Head does any changes on the distribution
stamp (already ticked by the DC according to approved distribution matrix) either
through direct ticking or by email then document controller will redistribute the
documents accordingly. If the Project Head is on leave, his nominated
representative marks the distribution on his behalf. A copy, however, is made
and given to the Project Head on his return.
vi. The document controller updates the correspondence log with person(s)
responsible for action and a target date for it to be completed. (It is not
responsibility of DC to check the reply of the correspondence)
vii. The document controller scans the correspondence and distribute as “TO” to the
persons who have responsibility for “Action” and “CC” for “Information” using
Email/EDMS
G. Outgoing Correspondence
i. The originator provides a soft copy to the document controller. The document
controller formats the letter and ensures that the letter addressee is correct and
put reference as Appendix A.
ii. The document controller provides the letter to the Project Head for review. Upon
approval of the Project Head, the document controller prints the letter on FIBREX
Letterhead and presents to the Project Head for the signature.
iii. Once signed, the document controller arranges for the letter to be delivered. A
receiving copy is delivered with the letter, which is signed by the recipient with
the date. Upon return of the messenger document controller should get receiving
copy from him to update the log with submitted date.
iv. After updating the log, the received copy signed by recipient is filed along with
the copy of the outgoing correspondence.
QMS/PR/DC/001
Document Control Procedure|Page 7 of 21
H. Submittals
i. All submittals are prepared and / or reviewed by members of the project team.
When ready for submission to the Engineer, the document controller arranges for
the cover sheet and assigns number according to the project submittal
numbering system to be signed by the Project Head or nominated representative.
ii. When the Project Head has approved and signed the submittal it is returned to
the document controller.
iii. A receiving copy is issued with the submittal which is stamped and signed by the
Recipient. Upon return of the receiving copy, document controller updates the
submittal log.
iv. After update the log, the received copy is filed with the copy of submittal.
v. Submittal after reviewed by Engineer, it returns to the document controller. The
Document Controller stamps the submittal for distribution and distributes the
documents as per approved distribution Matrix and presents to the Project Head.
The Project Head then marks as action/information for missed people during the
distribution.
vi. The document controller update the submittal log to record the date of response
from the Engineer, whether the submittal is approved or not. The document
controller scans the submittal cover sheet with attached comments(if any) and
distribute to the persons who have responsibility for “Action” and CC’s those for
“Information”
I. E-Mails
i. All Outgoing and incoming e-mails are to be copied to the project-email
address
ii. Document controller monitors the project e-mails address. As e-mails are
received, document controller sorts them into each person’s folder.
iii. Document controller shall be able to retrieve the email & forward to Project
Head. Then Project Head may then instruct to document controller
whether the e-mail is to be distributed the email.
QMS/PR/DC/001
Document Control Procedure|Page 8 of 21
Turnover Documents
K. Archiving of Documents.
i. The Document Controller is responsible for archiving of documents during and
upon completion of the project.
ii. The QHSE Manager or project Quality Manager with the help of Commercial
Department prepares a list of all documents required to be archived.
iii. A register of all documents archived is maintained by the concerned document
controller. Any documents added or removed from the archive are recorded on
that register. The archive is kept neat and tidy so that all documents are
identifiable and retrievable. Access to the archive is restricted only to persons
nominated by the Project Head.
iv. An Electronic Backup of documents.
Below is the process of DLP and Document Controller has to maintain a proper
DLP log
1. DLP Coordinator Inspect and Verify that the Outstanding Works have
been Satisfactorily Completed by Fibrex or Fibrex Subcontractor.
2. In case the defect was not closed proplerly, the DLP coordinator calls the
QMS/PR/DC/001
Document Control Procedure|Page 9 of 21
Contractor to Remedy Detected Defects
1. Upon the completion of DLP work the Employer will Issue Defects
Liability Certificate
After receiving the DLP certificate the Contractor shall issue the final
testing with below documents attached
1. Final Statement submittal
2. Issuance of Final Certificate
3. Final Report
QMS/PR/DC/001
Document Control Procedure|Page 10 of 21
APPENDIX A
Requirements of DC Room
QMS/PR/DC/001
Document Control Procedure|Page 11 of 21
APPENDIX B
Document Numbering System
QMS/PR/DC/001
Document Control Procedure|Page 12 of 21
APPENDIX C
Standard Document’s Templates
QMS/PR/DC/001
Document Control Procedure|Page 13 of 21
APPENDIX D
Hard Copy Distribution List
QMS/PR/DC/001
Document Control Procedure|Page 14 of 21
APPENDIX E
Authority of Key Participation
QMS/PR/DC/001
Document Control Procedure|Page 15 of 21
APPENDIX F
Document Flow Diagram
QMS/PR/DC/001
Document Control Procedure|Page 16 of 21
APPENDIX G
Filing Index
QMS/PR/DC/001
Document Control Procedure|Page 17 of 21
APPENDIX H
Box File Label
QMS/PR/DC/001
Document Control Procedure|Page 18 of 21
APPENDIX I
Drawing Register/Summary Sheet
Note:-
QMS/PR/DC/001
Document Control Procedure|Page 19 of 21
APPENDIX J
Correspondence Register
Note:-
QMS/PR/DC/001
Document Control Procedure|Page 20 of 21
APPENDIX K
Submittal Register/Summary Sheet
Note:-
QMS/PR/DC/001
Document Control Procedure|Page 21 of 21
APPENDIX L
Stamps
QMS/PR/DC/001
Q & A For Document Control Job
A1.
Document control establishes a central point where all project related correspondence and
documents are logged and tracked. The purpose of document control is to ensure that all project
required documents and/or correspondence is processed as required, and in a timely manner. A
delay in processing of required documents and/or correspondence could cause a delay to the
overall project completion and result in substantial additional costs. Therefore, this process is an
important element of construction management and project delivery, and should not be
underestimated. The size of the project/program will determine how simple or complex the
document control system needs to be.
NCR (Non Conformance Report) This report will list all of the elements in construction that
do not meet or conform standards that are required by the
law
WIR (Work Inspection Request) requirements. After building permit is issued, Engineer
inspect Building to make sure it is done according to the
approved plans and Drawings
Document Transmittal is used to formally dispatch any
A3.
Controller? A4.
submittal? A5.
Handover? A6.
Project documents?
Q8. If on project there is no Document Control Procedure then what is your strategy to handle the
Correspondence Log
A7.
REMARKS
Q & A For Document Control Job
Q9. How to Improve the Document Control System?
System? A10.