WELDING COSTS - CONTINUED
Job Knowledge 97
Part 1
Flux cored arc welding
The previous two Connect articles dealt with the mechanics of costing a weld: how to
calculate the weld volume and how to calculate the amount of welding consumables
required to fill a weld preparation.
The final step in costing a weld is to determine the length of time to deposit this weight of
weld metal. This is obviously a function of the deposition rate of the process. The deposition
rate is generally expressed as kgs/hr or lbs/hr deposited at a given welding current, welding
continuously and without any breaks for electrode changing or deslagging.
https://www.twi-global.com/technical-knowledge/job-knowledge/welding-costs-continued-097 1/6
12/30/22, 11:20 AM Welding Costs - Continued - TWI
The deposition rate will be affected by many factors and it will not be possible within the
limitations of these articles to list the precise deposition rates for any specific process or
welding current. Such data can be found in publications referenced below or by a web
search. The ranges of approximate deposition rates for the commoner arc welding
processes are listed in Table 1.
Table 1 Indicative deposition rates - arc welding processes
Deposition Rate
Welding kgs/hr
Process
min max
MMA 0.4 5.5
To obtain an accurate figure for the specific parameters to be used is a relatively simple
exercise. Weighing a plate, depositing weld metal using the required parameters on this
plate for a fixed time and then re-weighing the plate will give an accurate figure that may be
used for estimating purposes.
There is one golden rule for minimising the cost of making a weld and, whilst this may seem
to be self-evident, it is worth repeating: deposit the minimum amount of the highest quality
weld metal with the largest gauge electrode or wire at the highest current in the shortest
possible time. This is obviously the ideal and can seldom be achieved in practice because of
limitations on heat input, access etc.
The implications of applying the golden rule are:
1. To deposit the minimum amount of weld metal the designer, aided by the
welding engineer, must select the smallest weld preparation that is capable of
providing the required weld quality. If the included angle is too narrow then lack
of side wall fusion is a possibility with the consequent costs of repair; too wide
an angle is wasteful in terms of deposited weld metal. Remember, though, that
the cost of providing a weld preparation (by flame-cutting, edge planning,
milling etc) must also be included in any costing exercise as must the cost of
https://www.twi-global.com/technical-knowledge/job-knowledge/welding-costs-continued-097 2/6
12/30/22, 11:20 AM Welding Costs - Continued - TWI
assembly. Machined weld preparations are more accurate than flame cut edges
and this may result in faster set-up times and a reduced weld repair rate.
It may be possible to use a square edge preparation by using the deep
penetration characteristics of some of the welding processes; electron beam
and laser welding are the best examples of this technique. Plasma-TIG and
activated flux TIG can penetrate up to 10mm in a single pass; the 'finger'
penetration of spray transfer MAG welding can penetrate up to 6mm and a
submerged arc weld can penetrate up to 15mm. There is also the benefit when
using a square edge preparation in that the consumption of filler metal is
substantially reduced, the bulk of the weld metal being provided by the parent
material.
The final option on reducing costs when butt welding is for the designer to
specify a partial penetration joint. The most expensive weld pass in any full
penetration butt weld is the root pass and if this can be eliminated by using
partial penetration joints then substantial savings can be made. However, the
decision to use partial penetration welds should not be taken lightly but only if
service conditions permit the presence of a large crevice at the weld root. The
designer will therefore need to consider whether fatigue, creep, corrosion etc
are likely to occur and must clearly specify where the joints are permitted and
the minimum acceptable weld throat.
2. Depositing the highest quality weld metal infers that the weld repair rate will be
reduced. Repair weld metal is very costly, particularly if the unacceptable
defects are detected late in the fabrication programme; perhaps after final
assembly where access is difficult or after post weld heat treatment. Accurate
weld preparations and fit-up, easy access for the welder, welds made in the flat
position and well trained welders will all help to minimise the weld repair rate.
https://www.twi-global.com/technical-knowledge/job-knowledge/welding-costs-continued-097 3/6
12/30/22, 11:20 AM Welding Costs - Continued - TWI
3. Depositing weld metal with the largest electrode or wire at the highest current
will obviously give the highest weld deposition rate and shortest joint
completion time. The deposition rate figures in Table 1 give the minimum and
maximum deposition rates at minimum and maximum welding currents. As an
example, a 1.2mm diameter MAG wire at 120amps will deposit around 1.2
kgs/hr, at 380amps around 8 kgs/hr. To enable high welding currents to be used
the item must be placed in the flat position and there must be easy access for
the welder. One benefit of using the high welding currents is that the number of
weld runs to fill the joint will be reduced and this, in most circumstances, will
result in less distortion than a large number of low current weld passes.
Remedial work to correct distortion can therefore be reduced. A further benefit
when welding the ferritic steels is that high current and therefore high heat
input may allow any preheat to be reduced or eliminated entirely.
However, there are limitations to this approach to improving productivity. If achieving high
toughness is a factor then it is likely that heat input will need to be controlled when welding
the ferritic steels, placing a limit on the welding current and travel speed. High welding
currents also imply a large, fluid weld pool and it may not be possible to control this pool
when welding in any other than the flat position - for example, MAG welding cannot be
performed using spray transfer (high welding current) in the vertical position due to the
absence of a flux to hold the pool in place. Using a manual process at such high currents
also results in increased welder fatigue resulting in a reduced duty cycle. A solution to this
problem is to mechanise or automate the process.
To achieve the most cost effective solution to producing a welded structure is therefore not
simply to increase duty cycle or deposition rate but to consider all aspects of fabrication
from the design stage to final inspection, involving all members of the team from designer
to welder.
This article was written by Gene Mathers.
References:
https://www.twi-global.com/technical-knowledge/job-knowledge/welding-costs-continued-097 4/6
12/30/22, 11:20 AM Welding Costs - Continued - TWI
Procedure Handbook of Arc Welding, Publ Lincoln Co.
Standard Data for Arc Welding, Publ TWI (out of print)
Welding Handbook Vol 2 Welding Processes, Publ American Welding Society
For more information please email:
[email protected]
Granta Park, Great Abington, Cambridge, CB21 6AL, UK
+44(0)1223 899000
[email protected]
Subscribe to our newsletters
Copyright © 2022 TWI Ltd. All rights reserved.
Terms Privacy Cookies Modern Slavery Statement TWI Research Integrity Statement
Safeguarding Policy
https://www.twi-global.com/technical-knowledge/job-knowledge/welding-costs-continued-097 5/6
12/30/22, 11:20 AM Welding Costs - Continued - TWI
https://www.twi-global.com/technical-knowledge/job-knowledge/welding-costs-continued-097 6/6