0% found this document useful (0 votes)
141 views4 pages

Hydraulic Design Calculation For Hpu: Adcop - Abu Dhabi Crude Oil Pipeline Project Habshan - Fujairah

Uploaded by

Aditya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
141 views4 pages

Hydraulic Design Calculation For Hpu: Adcop - Abu Dhabi Crude Oil Pipeline Project Habshan - Fujairah

Uploaded by

Aditya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

ADCOP - ABU DHABI CRUDE OIL PIPELINE PROJECT

Habshan - Fujairah

HYDRAULIC DESIGN CALCULATION FOR HPU


P195-30-99-52-3608

EPC CONTRACTOR: PROJECT MANAGEMENT CONSULTANT: VENDOR / SUBCONTRACTOR:

China Petroleum Engineering ILF Consulting Engineers


& Construction Corporation P.O.Box 73250
Abu Dhabi Branch
Abu Dhabi, UAE CONSULTING
P.O. Box 127345 EN GI N EERS

PROJECT: ADCOP - ABU DHABI CRUDE OIL PIPELINE PROJECT


Habshan - Fujairah
EPC Contractor Doc. No.: ADCOP/C013/08 PAGE: 1 of 5
DOCUMENT No.: P195-30-99-52-3608 Rev. 0 Project No: E30153 DATE: 18-01-2017
REVISION RECORD

REV DATE ORIGINATOR REVIEWED APPROVED DESCRIPTION

RASHMI ANAND
A 27-7-2015 ANAND KUMAR ISSUED FOR APPROVAL
SHARMA KUMAR
0 18-JAN-17 RASHMI S ANAND K ANAND K ISSUED FOR CONSTRUCTION

© Copyright China Petroleum Engineering &Construction (Group) Corporation 2008 All rights reserved.
“This document is issued for the execution of Abu Dhabi Crude Oil Pipeline (ADCOP) project.
Copying this report without the permission of CPECC, ILF and IPIC is not permitted.

DOCUMENT TITLE : HYDRAULIC CALCULATIONS - HPU


Project No: E30153

PROJECT: ABU DHABI CRUDE OIL PIPELINE PROJECT


Page 2 of 5
Habshan - Fujairah
DOCUMENT No.: P195-30-99-52-3608 Rev. 0 DATE : 18-01-2017
HABSHAN FUJAIRAH OIL PIPELINE PROJECT
HYDRAULIC DESIGN CALCULATIONS
P.O.: 71407784

Hydraulic Calculations

PROSERV Document No.: PJ-05-000346-HYD

PROSERV PROJECT No.: PJ-05-000346

00 27-Nov-2014 Issued for Review/Comments VH HJ SK


Approval
Rev Date Reason For Issue Prep. Chkd. Apprd.
Status
HYDRAULIC DESIGN CALCULATIONS
Client :- EMERSON Proserv Doc. No :- PJ-05-000346-HYD

Project :- HABSHAN FUJAIRAH OIL PIPELINE PROJECT Revision :- 0


Document Title :- HYDRAULIC DESIGN CALCULATIONS Date :- 27.11.2014

Project :HPU
Equipment : Actuator of 19.04 liter volume NOTES
Adiabatic Constant = 1.40 Adiabatic expansion calculation used

Max Pressure Barg (P3) = 200.00 2900 psi Max Sys. pressure

Min Pressure Barg (P2) = 150.00 2175 psi Min Sys. Pressure

Precharge Pressure (P1)=(90% of P2) 135.00 1958 psi N2 Precharge Pr.

Fluid Swept Vol required Litres (between Max & Min Press) = 19.40

Number of Operations = 1.00

Total Fluid Swept Vol Litres (between Max & Min Press) = 19.4 Calculated Value

Total fluid and gas Volume calculated litres = 126.0 Total Oil AND Gas Volume Required calculated

Minimum amount of accumulator fluid volume required litres = 40.9 Min Calculated Value of Fluid needed

Total Accumulator fluid Volume selected = 42.00 Total Fluid Required

Over or under fluid volume selected = 1.1 Should be >=0

Minimum amount of Nitrogen gas volume required litres = 85.0 Min Calculated Value

Total Nitrogen Gas Volume selected = 86.00 Total Gas Required

Over or under Nitrogen Gas volume selected = 1.0 Should be >=0

Total Accumulator fluid and gas Volume selected = 128.0 Standard Accumulator Size selected

Total Accumulator over or under fluid and gas Volume selected = 2.0 Should be >=0

Actual amount of fluid stored between Min and Max Pressure = 19.7 Actual Amount Stored between MinP to MaxP

Total Accumulator over or under fluid Volume selected = 0.3 Should be >=0

Total Fluid Returned to Reservoir on shutdown = 41.6 Actual Amount stored between Zero to max P
Volume used to size Reservoir
Fluid Variance to selected volume of accumulators = 0.4 Should be >=0

Actual selection
Qty Each (litres) Total (litres)
PistonAccumulator 3.0 37.8 113.4
1.0 18.9 18.93
total fluid/gas volume : 132.33

Prepared Checked Approved Date


VH HJ SK 27-11-14