0% found this document useful (0 votes)
480 views4 pages

Bungalow Schedule

1) The document provides a schedule of materials and quantities needed for construction of a building including substructure, ground floor frame, upper floor, and roofing elements. It lists various construction materials such as concrete, reinforcement bars, formwork, and EPS panels along with their required quantities and unit costs. 2) The total cost for materials for the substructure element is KSH 584,180. The total cost for materials for the ground floor frame element is KSH 1,326,200. 3) Materials for the upper floor element have a total cost of KSH 1,174,300. However, the document does not provide a total cost for materials for the roofing element as it is

Uploaded by

Kelvin Waweru
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
480 views4 pages

Bungalow Schedule

1) The document provides a schedule of materials and quantities needed for construction of a building including substructure, ground floor frame, upper floor, and roofing elements. It lists various construction materials such as concrete, reinforcement bars, formwork, and EPS panels along with their required quantities and unit costs. 2) The total cost for materials for the substructure element is KSH 584,180. The total cost for materials for the ground floor frame element is KSH 1,326,200. 3) Materials for the upper floor element have a total cost of KSH 1,174,300. However, the document does not provide a total cost for materials for the roofing element as it is

Uploaded by

Kelvin Waweru
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

SCHEDULE OF MATERIAL

ITEM DESCRIPTION QTY UNIT RATE AMOUNT(Ksh)

ELEMENT No. 1: SUBSTRUCTURE


Site preparation & Excavation
Clear site of bushes, undergrowth, grass, small
a trees and the like including grubbing up their roots 183 Sq m 60 10,980.00
(376sm)
Excavate oversite average 150mm deep to remove
b 183 Item
vegetable soil and remove from site (376sm)
c Excavate foundation trench not exceeding 1.4 180 Sq m 90 16,200.00
Earthwork & Backfilling
d Planking and strutting
Earth backfilling, well rammed and consolidated
e 1 Item
around foundations
f Hardcore 11 Trips 20,000 220,000.00
200mm Bed leveled murram, blinded to receive
g 8 Trips 10,000 80,000.00
polythene membrane (measured separately)
Soil sterilization
Aldrin 0.50% solution applied at a rate of 7
h 17 Ltr 1,500 25,500.00
Liters per square meter to hardcore bed (209sm)
Ditto at rate of 8 Liters per linear meter per
300mm depth per
i 5 Ltr 2,000 10,000.00
235mm width to backfilling to one side of wall
foundations (50Lm)
Damp-proof membrane & Brc reinforcement
1000 Gauge polythene sheet damp -proof
j 3 Roll 3,500 10,500.00
membrane; 200mm lapped joints (302sm)
k BRC A66 3 Roll 4,500 13,500.00
FOUNDATION CONCRETE WORK & WALLING
a Sub-structure Column & strip footing Concrete work
Cement 116 Bags 650 75,400.00
Sand 14 Tonnes 2,000 28,000.00
ballast 29 Tonnes 2,000 58,000.00
b Reinforcement (1bar length =12m)
8mm diameter 15 Bar 520 7,800.00
12mm diameter 15 Bar 1,220 18,300.00
Binding wire 1 Roll 4,000 4,000.00
c Formwork Item 6,000.00

Total carried to collection 584,180.00

Ace Developers'
Foundation Walling

a Stone jointed in cement mortar 1:3 Wall


225mm block 1800 Pcs 50 90,000.00
Hoop iron 1 Roll 3,000 3,000.00
b Concrete (1;3) materials for jointing & filling
Cement 40 Bags 650 26,000.00
Sand 8 Tonnes 2,000 16,000.00
c In situ slab concrete (1:2:4)
Cement 172 Bags 650 111,800.00
Sand 20 Tonnes 2,000 40,000.00
Ballast 41 Tonnes 2,000 82,000.00

d In situ subfloor concrete (1:3)

Cement 28 bags 650 16,900.00


Sand 4 Tonnes 2,000 8,000.00
e Sawn formwork to Length 100 Ft 60 6,000.00
Staircase (1:2:4)
a Cement 24 Bags 650 15,600.00
Sand 3 Tonnes 2,000 6,000.00
Ballast 6 Tonnes 2,000 12,000.00
b Reinforcement High yield steel (1 bar length = 12 meters)
8 diameters 15 bars 520 7,800.00
12 diameters 25 bars 1,220 30,500.00
Binding wire 4 Roll 4,000 16,000.00

Columns Reinforcement (ground to 1st floor)


8 diameters; Stirrups 50 bars 520 26,000.00
12 diameters; Main bar 95 bars 1,220 115,900.00
TOTAL 621,700.00
Total brought forward 584,180.00
Total carried to collection 1,205,880.00

Ace Developers'
Element 2; GROUND FLOOR FRAME
EPS PANELS (1panel dimension = 3x1.2 Mtrs)
Double wall panels 100 Board 8,500 850,000.00
Concrete fill in EPS (1:2:4)
Cement 172 Bags 650 111,800.00
Sand 20 Tonnes 2,000 40,000.00
Ballast 41 Tonnes 2,000 82,000.00

Wall Mortar ratio (1;3) Inner & outer side; and slurry sum included
Cement 244 Bags 650 158,600.00
Sand 41 Tonnes 2,000 82,000.00
Lime; for Slurry 13 Bags 200 2,600.00
Total carried to collection 1,326,200.00
Element 3; UPPER FLOOR
In situ slab concrete (1:2:4-18mm aggregate)
Cement 180 Bags 650 117,000.00
Sand 22 Tonnes 2,000 44,000.00
Aggregate 18mm 45 Tonnes 2,000 90,000.00
EPS Panel for Slab (1panel dimension = 1.2x2.5 Mtrs)
Floor/Slab panel 50 Boards 6,500 325,000.00
Concrete fill in EPS (1:2:4)
Cement 132 Bags 650 85,800.00
Sand 15 Tonnes 2,000 30,000.00
Ballast 32 Tonnes 2,000 64,000.00
Wall (inner and outer) & Slab Mortar
Cement 195 Bags 650 126,100.00
Sand 33 Tonnes 2,000 66,000.00
Slab and Beam Reinforcement, High yield steel (1 bar length= 12 meters)
10mm diameter 105 Bar 820 86,100.00
12mm diameter 115 Bar 1,220 140,300.00

Total carried to collection 1,174,300.00

Ace Developers'
Element 4; ROOFING (flat roof with eps)

EPS Panel for Roof Slab (1panel dimension = 1.2x2.5 Mtrs)


Slab/Roof panel 50 Boards 6,500 325,000.00
In situ roof slab concrete (1:2:4-18mm aggregate)
Cement 200 Bags 650 130,000.00
Sand 26 Tonnes 2,000 52,000.00
Ballast 50 Tonnes 2,000 100,000.00
Reinforcement
8 diameters 70 Bars 520 36,400.00
12 diameters 80 Bars 1,220 97,600.00
Mortar
Cement 65 Bags 650 41,600.00
Sand 11 Tonnes 2,000 22,000.00

Total carried to collection 804,600.00

SUMMARY
Element No. 1: Substructure 1,205,880.00
Labour 10% 241,120.00
TOTAL SUBSTRUCTURE 1,447,000.00
Element No. 2: Ground floor 1,326,200.00

Element No. 3: 1st floor 1,174,300.00


Element No. 4: Roof 804,600.00

TOTAL 3,305,100.00

Labour 20% 661,100.00

TOTAL GROUND/UPPER FLOOR & ROOF 3,966,200.00


SUB TOTAL: 5,413,200.00
SUPERVISION 2% 108,300.00

SUB TOTAL: CARRIED TO GENERAL SUMMARY 5,521,500.00

Ace Developers'

You might also like