Underpinning
Underpinning
this is
of the pile cap should be
achieved
as conservative as
possible and
usually by having overhang of 150 mm. The Federation
an
of
Piling Specialists have issued the following guide table as to suitable pile
cap depths having regard to both design and cost requirements:
Pile diameter (mm) 300 350 400 450 500 550 600 750
23
Depth of cap (mm) 700 800 900 1 000 1 100 1 200 1 400 1800
The main reinforcement is two-directional, formed in bands over the
Underpinning
pile heads to spread the loads and usually take the form of a 'U' shaped
bar suitably bound to give a degree of resistance to surface cracking of the
faces of the pile cap see typical details shown in Fig. III.39.
-
In many piling schemes, especially where capped single piles are used,
the pile caps are tied together with reinforced concrete tie beams. The
beams can be used to carry loadings such as walls to the pile foundations-
see Fig. II. 39.
PILING CONTRACTS
The formation of piled foundations is a The main objective of underpinning is to
specialist's task and as such a piling contractor may be engaged to carry transfer the load carried by an existing fou ndation trom its present bearing
out the work by one of three methods: level to a new level at a lower depth. It can also be used to replace an
existing weak foundation.
1. Nominated subcontractor. Underpinning may be necessary for one or more of the following
2. Direct subcontractor.
reasons:
3. Main contractor under a separate contract.
227
226
1. Notice should be
served to the adjoining
the intention to
owners setting out in detail 5. Estimated spanning ability of existing foundation.
proceed with the proposed works and giving ful 6. Subsoil conditions encountered.
details of any proposed temporary supports such as shoring.
2. A detailed
survey of the building to be underpinned should be made The generally specified maximum length for bays used in the
recording any defects, cracks, supplemented by
agreed with the building owner where photographs and underpinning of traditional wall construction is 1.500 m with the proviso
3. Glass possible. that at no time should the sum total of unsupported lengths exceed 25%
slips
or 'tell tales' should be fixed across
any vertical and
lateral cracks of the total wall length.
to give a visual indicator of
any movement taking
place. Bays are excavated and timbered as necessary after which the bottom
4. A series of check levels should be taken of the excavation is prepared to receive the new foundation. To give the
against a reliable datum or new foundation strip continuity, dowel bars are inserted at the end of each
alternatively metal studs can be fixed to the external wall and
their
levels noted. These levels should be bay. Brick underpinning is toothed at each end to enable the bonding to
checked periodically as the work
proceeds to enable any movements to be recorded and the be continuous whereas concrete underpinning usually has splice bars or
necessary
remedial action taken. dowels projecting to provide the continuity. Brickwork would
normally be
in a brick bedded in 1 :3 cement mortar laid in
5. Permission should be
all flues and
obtained, from the adjoining owner, to stop up class'B English bond for
strength. Concrete used in underpinning is usually specified as a 1:2:4/20
fireplaces to
prevent the nuisance and damage which
can be caused by falling soot. mm
aggregate mix using rapid hardening cement. The final pinning mix
6. It should consist of 1 part rapid hardening cement to 3
underpinning required is to counteract
unacceptable settlement of parts of well graded
the existing foundations an fine aggregate from 10 mm down to fine sand with a
investigation of the subsoil should be 0.35. In both methods the projection of the
water/ cement ratio of
carried out to determine the cause and to forecast any future existing foundation is cut
that the underpinning design will be adequate.
back to the external wall line so that the loads are transmitted to the
movement so new
foundation and not partially dissipated through the
7. The loading on the structure should be reduced as much as
possible original
foundation
strip on to the backfill material - see Fig. III.40.
by removing imposed fioor loads and installing any shoring that
may be ne cessary.
WALL UNDERPINNING
PRETEST METHOD OF
Traditional underpinning to walls is carried
out by excavating in stages alongside and underneath the existing
UNDERPINNING
This method is designed to
prevent further
foundation, casting a new foundation, building up to the underside of the settlement of foundations after
foundation in brickwork or concrete and finally pinning between underpinning has been carried out by
existing consolidating the soil under the new foundation before the load from the
the old and new work with a rich dry mortar. underpinning is applied. The perimeter of the wall to be underpinned is
To prevent the dangers of fracture or settlement the underpinning excavated in stages as described for wall
underpinning, the new foundation
Stages or bays should be kept short and formed to a definite sequence strip is laid and a hydraulic jack supporting a short beam is placed in the
This will enable the
pattern so that no two bays are worked consecutively. centre of the bay under the
existing foundation. A dry mortar mix is laid
the void created underneath
existing foundation and wall to arch span between the top of the beam and the existing foundation and before it has
or
and length of the bays will depend finally set the jack is extended to give a predetermined load on the new
prior to underpinning. The number
factors: foundation, thus pretesting the soil beneath.
upon the following
This process is repeated along the entire
1. Total length of wall to be underpinned.
underpinning length until the
whole wall is being supported by the
hydraulic jacks. Underpinning is
2. Width of existing foundation. carried out using brickwork or conerete
walling
between the jacks which
3. General condition of existing substructure. are later removed and replaced with underpinning to complete the
foundation.
4. Superimposed loading of existing operation.
228 g 229
working trench width
clear to give sufficient
working space 1.000
minimum
JACK OR MIGA PILE
walls
UNDERPINNING
to be This is
underpinned following circumstances:
a method which can be used in the
1.
Depth of suitable
bearing capacity subsoil is
traditional wall underpinning deep to make too
1.200 to 1.500 long 2. Where a system
practical or economic.
working bays or
legs giving no vibration is
required. It is worth noting
that this method is also
3. If
practically noiseless.
a
syste mof flexible depth is required.
Z1LZLA Z The system consists of short
3524 642 53 the ground until a suitable
precast concrete pile lengths jacked into
subsoil is reached see Fig. III.41.
jack pile has reached the required When the
depth the space between the top of the
Typical underpinning schedule
pile and underside of the existing foundation is filled
with a pinned
concrete cap. The
working existing foundation must be in a good condition since in
space the final context it will act as a
beam spanning over the
tion and hence the piles. The condi-
wall
spanning ability of the existing strip foundation will also
to be underpinned- determine the spacing of the piles.
Projection -timbering to
existing foundation removed excavation
as required NEEDLE AND PILES
If the wall be
foundation that is considered unsuitable for underpinned
to has
timbering left in final weak a
wall to be pump-
underpinned -
existing
foundation
val
R.C existing
timbering9 needle foundation
to excavation
as required
smal small diameter
diameter bored piles
bored
pressure pipe piles designed to
suit conditions
- - first section
small diameter
bored piles
wall
Prestressed concrete: short
precast concrete blocks
existing foundations as the brickwork are inserted
over the
is removed. The blocks are formed
to allow for post
anchored
tensioning stressing tendons to be
inserted, stressed and
to form a
continuous beam. Final
underpinning. pinning completes the
It should be noted that all forms of
beam underpinning can also be used
to form a lintel or
beam, in any part of a wall,
large opening.
to the prior formation of a
FINAL PINNING
Although final pinning is usually carried out
by ramming a stiff dry cement mortar mix into the space between the new
underpinning work and the existing structure, alternative methods are
available such as:
1. Flat jacks circular or rectangular hollow plates of various sizes
-
made from thin sheet metal which can be inflated with high
pressure
water for temporary pinning or, if work is to be permanent, with a
strong cement grout. The increase in thickness of the flat jacks is
approximately 25 mm.
2. Wedge bricks - special bricks of engineering quality of standard face
length but with a one brick width and a depth equal to two courses
The brick is made in two parts, the lower section having a wide
sloping channel in its top bed surface to receive the wedge shaped
and narrower top section. Both parts have a vertical slot through
which the bedding grout passes to key the two sections together,
235
234
UNDERPINNING COLUMNS
This is a more difficult task than
wall. It can be carried out on brick or stone columns by
pair of precast concrete underpinning a
be carried
foundation to be
II.44. The underpinning of the column foundation can now out
hydraulic jack
as fulcrum -
pair of jack
foundation to
or bored piles-
be underpinned