0% found this document useful (0 votes)
91 views4 pages

Enhancing The Life Span of 500 MVA ICT Through Controlled Switching Devices 230306 113912

ISOSCELES SALES & SERVICES PVT LTD successfully installed a controlled switching device (CSD) on a 500 MVA transformer at a 765/400/220 kV substation in India to address sparking issues during switching. During initial energization of the transformer without a CSD, sparks were observed near tank joints due to high inrush currents. ISSPL installed a CSD which reduced the average inrush current by 250% during testing. Repeated switching operations with the CSD installed saw smooth operation with no sparking and low inrush currents below 117 amps in each phase. The CSD installation successfully resolved the sparking issues during switching of the 500 MVA transformer.

Uploaded by

Zeeshan Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
91 views4 pages

Enhancing The Life Span of 500 MVA ICT Through Controlled Switching Devices 230306 113912

ISOSCELES SALES & SERVICES PVT LTD successfully installed a controlled switching device (CSD) on a 500 MVA transformer at a 765/400/220 kV substation in India to address sparking issues during switching. During initial energization of the transformer without a CSD, sparks were observed near tank joints due to high inrush currents. ISSPL installed a CSD which reduced the average inrush current by 250% during testing. Repeated switching operations with the CSD installed saw smooth operation with no sparking and low inrush currents below 117 amps in each phase. The CSD installation successfully resolved the sparking issues during switching of the 500 MVA transformer.

Uploaded by

Zeeshan Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Success Story: Enhancing the Life Span of 500

MVA ICT through Controlled Switching Devices


In the last two blogs, we have shared our knowledge on the technique of controlled switching to
enhance the life expectancy of assets in the electrical network and improve system stability. By
discussing how life span of  reactors, capacitor bank  assets and  power transformers  can be
enhanced through controlled switching, we have underscored the criticality of this technique vis-à-
vis  the electrical network.

In this post, we will cover how SCOPE’s service company – ISOSCELES SALES & SERVICES
PVT LTD (ISSPL) successfully installed controlled switching device (CSD) for 500 MVA ICT at a
765/400/220 kV substation.

https://www.windpowerengineering.com/controlled-switch-device-improves-medium-voltage-transformers-circuit-breakers/

The Challenge

A transmission licensee, one of the largest in India, began implementing the project which involved
the construction of 765kV & 400kV substations along with 765kV single circuit & 400kV double
circuit lines. The commissioning of two 765kV substations in this project was among the first
instances of EHV voltages being commissioned by a licensee other than the Central Transmission
Utility.

The project scope required the installations of Control Switching Devices (CSDs) at the 765kV and
400kV ICT and Reactors, however one 500MVA ICT at the substation was not provided with a
CSD. During first charging of this 500MVA transformer, sparks were observed near the tank joint.
The picture below describes the observed sparks:
Fig 1: Sparks observed during Fig 2 : Sparks observed during Uncontrolled Switching
Uncontrolled Switching
This persistent sparking represented a major danger as
possible consequences included both safety and economic
loss. A serious failure on the transformer could lead to premature retirement of the power
transformer, possibly blasting of transformer causing damage to nearby assets and therefore the
associated replacement costs, overall system failure and violation of service agreements entered
into with the beneficiary licensees. Given the gravity of the problem, ISSPL was approached with a
mandate to provide a solution to the problem.

The Solution

On examining the issue on the field and reviewing the case history, service experts at ISSPL
concluded that the sparks observed were due to inrush current. In line with our experience with
similar issues encountered by our customers, ISSPL recommended that a CSD be installed to
rectify this persistent problem of spark on the transformer tank.   

Thus, ISSPL installed SCOPE marketed CSD – SynchroTeq Plus on the 500 MVA ICT.

CSD Configuration Strategy

The service experts of ISSPL, bringing together their wealth of experience in providing innovative
solutions, recommended that the technique of closing the first phase on the peak voltage be used.
This is a widely used strategy which energises power transformers without considering the residual
flux on the magnetic core.

During field tests, one of the CB poles was closed by SynchroTeq Plus CSD at peak voltage and
other poles were closed simultaneously. The average inrush current was reduced with an average
of 0.55 PU, an improvement of 250% over uncontrolled switching.
It should be noted that the peak inrush current resulting from this technique depends on the
network topology. Reference setting files are shown below:

Fig 3 : Final Opening Setting

Fig 4 : Final Closing Setting

Results

During the first CLOSE operation, we found smooth operation in all 3 phases, on account of
absence of residual flux in the transformer core. No spark was observed on the transformer tank.

To review, OPEN operation was done with the same settings and in the next CLOSE operation, we
found 47Amp, 117Amp and 47 Amp (Peak) current in R, Y and B phase respectively. No spark was
observed on the transformer tank due to very low value of inrush current.

Repeated operations were done to confirm consistency during which no spark was observed on
the transformer tank due to very low inrush currents in all 3 phases. Given below are peak current
values of last 4 CLOSE operations.

Sr.no Event R- Ph max peak Y-ph max peak B-ph max peak

You might also like