Barangay : __ CHUA
Municipality Bagumbayan
√ No Climate Change Expenditure (Please tick the box if your LGU does not have any climate change expenditure)
Amount of Climate
Amount
Schedule of Change PPAs
Implement Implementation
(in Thousand Pesos) (in Thousand Pesos) CC
AIP Reference Program/Project/Activity ing Office/ Expected Funding
Typology
Code Description Departme Outputs Source
Code
nt Comple Climate Climate
Date
ted PS MOOE CO Total Change Change
Started
Date Adaptation Mitigation
1 2 3 4 5 6 7 8 9 10 11 12 13 14
At least 100%
1000-01-002 Overtime Pay of Barangay Officials BLGU Jan. Dec. compensated
Gen. Fund 100,000.00 100,00.00
At least 1 set
Procument for 1 set computer with
1000-01-003 computer with Gen. Fund
printer printer procured
BLGU Jan. Dec. 40,000.00 40,000.00
At least 100%
1000-01-004 Procurement of Forniture & Fixture BLGU Jan. Dec. furniture & fixture Gen. Fund
procured
80,000.00 80,000.00
1 unit portable
Procuremnet of Portable Sound
sound system Gen. Fund
System procured
1000-01-005 BLGU Jan. Dec. 50,000.00 50,000.00
At least 100%
Mentainance of Barangay Vehicle Satisfactory
Gen. Fund
1000-01-006 BLGU Jan. Dec. 50,000.00 50,000.00
Provision for Fuel of Barangay At least 2,000
Gen. Fund
1000-01-007 Vehicle BLGU Jan. Dec. Liters procured 80,000.00 80,000.00
At least 100%
Honorarium of Barangay Driver compensated
Gen. Fund
1000-01-008 BLGU Jan. Dec. 30,000.00 50,000.00
At least 100%
1000-01-009 Electric & Wifi Bills BLGU Jan. Dec. Satisfactory
Gen. Fund
40,000.00 40,000.00
At least 100%
1000-01-010 Provision for Liga ng Barangay BLGU Jan. Dec. Satisfactory
Gen. Fund
60,000.00 60,000.00
Provision for Training and Seminars At least 100%
Gen. Fund
of Barangay Officials Satisfactory
1000-01-011 BLGU Jan. Dec. 150,000.00 150,000.00
Provision for Mobilization of At least 100%
Gen. Fund
1000-01-012 Barangay officials (TEV) BLGU Jan. Dec. Satisfactory 150,000.00 150,000.00
At least 100%
Provision for Janitorial Services compensated
Gen. Fund
1000-01-013 BLGU Jan. Dec. 20,000.00 20,000.00
At least 100%
Provision for Office Supplies and
1000-01-014 BLGU Jan. Dec. Office supplies & Gen. Fund
Materials materials procured
40,000.00 40,000.00
At least 100%
Gen. Fund
Satisfactory
1000-01-015 Provision for Auditing Services BLGU Jan. Dec. 10,000.00 10,000.00
At least 100%
1000-01-016 Provision for Fidelity Bond BLGU Jan. Dec. Satisfactory
Gen. Fund
10,000.00 10,000.00
At least 100%
Gen. Fund
1000-01-017 Provision for BCLP BLGU Jan. Dec. Satisfactory 10,000.00 10,000.00
17 sitio leaders
1000-01-018 Provision for Sitio Leaders Uniform BLGU Jan. Dec. uniform procured
Gen. Fund
17,000.00 17,000.00
At least 10 km
8000-01-001 Rehabilitation of Road BLGU Jan. Dec. road rehabilitated 20% DF 500,000.00 500,000.00
Completion of Multi-Purpose Hall Mini-GYM
8000-01-002 (Mini-GYM) BLGU Jan. Dec. Completed 20% DF 400,000.00 400,000.00
Completion of Multi-Purpose Hall New Barangay
8000-01-003 (Barangay Hall) BLGU Jan. Dec. Hall Completed 20% DF 100,000.00 100,000.00
Halfway home
8000-01-004 Completion of Halfway Home BLGU Jan. Dec. completed 20% DF 50,000,00 50,000.00
At least 100%
8000-01-005 Compoletion of MPB (Sinagandal) BLGU Jan. Dec. accomplished 20% DF 25,000.00 25,000.00
Rehabilitation of Solar drier At least 100%
8000-01-006 (Maranatha) BLGU Jan. Dec. accomplished 20% DF 25,000.00 25,000.00
Other Development
8000-02 Program/Projects (External
Sources)
PLGU/ PLGU/
Construction of I Storey MPB Congressio 1 story building Congressio
8000-02-001 (daycare center) @ Spur-6 nal Fund Jan. Dec. constructed nal Fund 1,000,000.00 1,000,000.00
20mx30m drying
Construction of Drying Pavement @ pavement
8000-02-002 Little Baguio MLGU/DA Jan. Dec. constructed MLGU/DA 300,000.00 300,000.00
20mx30m drying
Construction of Drying Pavement @ pavement
8000-02-003 Sitio Spur-6 MLGU/DA Jan. Dec. constructed MLGU/DA 300,000.00 300,000.00
Cogression Cogressiona
al /National Tribal hall l/National
8000-02-005 Construction Tribal hall Fund Jan. Dec. Constructed Fund 1,000,000.00 1,000,000.00
PLGU/ PLGU/
Concreting of 1 Storey MPB @ Sitio Congressio 1 Storey MPB Congressiona
8000-02-006 Falcata nal Fund Jan. Dec. Constructed l Fund 500,000.00 500,000.00
PLGU/ PLGU/
Construction of 1 Storey MPB @ Congressio 1 Storey MPB Congressiona
8000-02-007 Macapagal nal Fund Jan. Dec. Constructed l Fund 500,000.00 500,000.00
PLGU/ PLGU/
Construction of 1 Storey MPB @ Congressio 1 Storey MPB Congressiona
8000-02-008 Salatan nal Fund Jan. Dec. Constructed l Fund 500,000.00 500,000.00
PLGU/ PLGU/
Construction of 1 Storey MPB @ Congressio 1 Storey MPB Congressiona
8000-02-009 Pinatikan nal Fund Jan. Dec. Constructed l Fund 500,000.00 500,000.00
9000- Other Services
9000-01-04 Provision for Covid-19 BLGU Jan. Dec. 100% Satisfactory BDRRM 60,000.00 60,000.00
Immediate Response to the Affected
Families/Farmers by Calamities &
9000-01-05 Disasters BLGU Jan. Dec. 100% Satisfactory BDRRM 50,000.00 50,000.00
At least 100% of
roads, creeks &
Rehabilitation of Roads Creeks & canals
9000-01-06 Canals BLGU Jan. Dec. rehabilitated BDRRM 50,000.00 50,000.00
30% QRF (In Kind in Case of
9000-01-07 Emergency Disaster BLGU Dec. 100% Satisfactory BDRRM 90.000.00 90,000.00
TOTAL 12,053,826.00