0% found this document useful (0 votes)
77 views6 pages

Draft DIT - Barchart Kegiatan

This document provides a work schedule and budget for a construction project. It lists various work items, quantities, units of measurement, estimated durations, and planned timelines across multiple phases of the project. The work includes site preparation, structural work like foundations and framing, architectural elements like walls and finishes, and mechanical, electrical and plumbing systems. The schedule aims to complete all work within 240 calendar days across 7 phases of the project.

Uploaded by

Anisa Alfitri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
77 views6 pages

Draft DIT - Barchart Kegiatan

This document provides a work schedule and budget for a construction project. It lists various work items, quantities, units of measurement, estimated durations, and planned timelines across multiple phases of the project. The work includes site preparation, structural work like foundations and framing, architectural elements like walls and finishes, and mechanical, electrical and plumbing systems. The schedule aims to complete all work within 240 calendar days across 7 phases of the project.

Uploaded by

Anisa Alfitri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

BARCHART 

KEGIATAN
NAMA KEGIATAN NAMA PEKERJAAN PEMILIK
LOKASI
TAHUN ANGGARAN

Durasi
No. Item Pekerjaan Volume Sat. (Minggu) 240 Hari Kalender

I II III IV V VI VII VIII


PEKERJAAN LANTAI I
A. PEKERJAAN PENDAHULUAN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

A.1 Pekerjaan Persiapan

- Papan Nama Proyek 1.000 Ls


- Direksi keet 18.000 m2

- Membersihkan lapangan dan perataan 252.350 m2

- Bongkar bangunan lama 1.000 Ls

A.2 Pekerjaan Tanah

- Galian tanah 269.243 m3

- Urug pasir bawah pondasi t : 5 cm 12.549 m3


- Urug pasir bawah lantai t : 5 cm 17.185 m3

- Pengurugan sirtu padat 343.700 m3

- Pemadatan 343.700 m2
B. PEKERJAAN STRUKTUR

B.1 Pekerjaan Beton

- Strouss Ø 30 cm

Beton (Fc' - 24,9 ( K-300) ) 2.560 m3

Begesting 35.840 m2
Tulangan 2,323.610 kg

- Pile cap 140.140.30

Beton (Fc' - 24,9 ( K-300) ) 12.544 m3


Begesting 35.840 m2

Tulangan 2,927.343 kg

- Kolom 40/40

Beton (Fc' - 24,9 ( K-300) ) 15.360 m3

Begesting 153.600 m2
Tulangan 3,469.166 kg

- Sloof 20/30
Beton (Fc' - 24,9 ( K-300) ) 19.179 m3

Begesting 191.792 m2

Tulangan 3,383.729 kg

- Balok 30/50
Beton (Fc' - 24,9 ( K-300) ) 19.260 m3

Begesting 128.400 m2

Tulangan 3,393.869 kg
- Plat lantai 12 cm

Beton (Fc' - 24,9 ( K-300) ) 34.362 m3

Begesting 366.528 m2

Tulangan 4,324.801 kg

C. PEKERJAAN ARSITEKTURAL

C.1 Pekerjaan Pasangan


- Pas. Dinding 1 Bata 1:4 (Rollag) 57.538 m2

- Pas. Dinding bata merah 1:4 500.649 m2

- Plesteran 1:4 t : 15 mm 1,001.297 m2

- Acian dinding bata merah 1,001.297 m2

- Benangan 98.000 m1

C.2 Pekerjaan Kusen-Daun Pintu & Jendela


- Pintu P1

Kusen alumunium 4" putih 24.400 m1

Daun pintu kaca 5 mm frame alluminium 8.000 m2


Engsel pintu 12.000 bh

Grendel pintu 8.000 bh

Lever handle 8.000 bh

Kunci selot 8.000 bh

- Pintu P2
Kusen alumunium 4" putih 12.200 m1

Daun pintu double teakwood 6 mm+rangka alumunium 2/4+finish lapis HPL 4.000 m2

Engsel pintu 6.000 bh

Grendel pintu 4.000 bh

Lever handle 4.000 bh

Kunci selot 4.000 bh

- Jendela J1
Kusen alumunium 4" putih 43.680 m1

Slimar alumunium 87.360 m1

Kaca bening 5 mm 19.008 m2


Engsel jendela 24.000 bh

Kait angin 24.000 bh

Spring knip 12.000 bh


No. Item Pekerjaan Sat.
Volume

- Jendela J2

Kusen alumunium 4" putih 27.600 m1

Slimar alumunium 55.200 m1


Kaca bening 5 mm 15.120 m2

Engsel jendela 12.000 bh

Kait angin 12.000 bh

Spring knip 6.000 bh

C.3 Pekerjaan Plafond

- Plafond gypsumboard 9 mm + rangka hollow galvallum 228.750 m2

C.4 Pekerjaan Keramik


- Lantai keramik 60/60 unpolished 71.150 m2

- Lantai keramik kamar mandi 25/25 unpolished 10.800 m2

- Plint keramik 10/60 180.754 m1


- Pemasangan Vinyl Lantai khusus anti noda dan anti bakteri 143.220 m2

- Pemasangan Vinyl Dinding anti noda dan anti bakteri 500.500 m2

- Keramik dinding kamar mandi 20/40 5.790 m2

C.5 Pekerjaan Finishing

- Finishing cat interior 378.070 m2

- Cat plafond 288.750 m2


- Finishing cat weathershield 68.100 m2

D. PEKERJAAN MEP
D.1 Pekerjaan Sanitasi Air

- Kamar mandi Umum

Shower spray 2 unit


Mixer shower 2 unit
Kloset duduk 2 unit
Floordrain 3 unit
Kran diameter 1/2" 3 unit
- Pipa PVC tipe AW diameter 1/2" (air bersih) 56.7 m1
- Pipa PVC tipe AW diameter 3/4" (air bersih) 56.7 m1
- Pipa PVC tipe AW diameter 1" (air bersih) 56.7 m1
- PVC tipe D diameter 3" (air kotor) 72 m1
- PVC tipe D diameter 4" (kotoran padat) 72 m1
- Wastafel 3 unit
- Septic tank Biofil 8.000 l 2 unit
- Resapan 2 unit
- Pompa Pendorong 12 v 2 Unit
D.2 Pekerjaan Elektrikal
- Lampu TBS (3x18 watt) 10.000 Bh

- Lampu tidur 6.000 Bh

- Armature Downlight 5" (inbouw) + Lampu 20 W (lengkap) 17.000 Bh

- Pasang Exhaustfan Plafond 2.000 Unit

- Stop Kontak Dinding 1 Phase 13.000 Bh


- Saklar Seri (ex. Broco) 4.000 Bh

- Saklar Tunggal (ex. Broco) 12.000 Bh

- Pasang Titik Inst. Penerangan (ex. Supreme) 33.000 Titik


- Pasang Titik Inst. Stop Kontak 1 Phase (ex. Supreme) 1.000 Titik

- Pasang Titik Instalasi Exhaustfan Plafond 2.000 Titik

- Pasang Panel 1.000 Unit

- Kabel antar panel NYY 4x16 mm2 (Supreme atau sekw)

a. Panel Lt.1 ke Panel Induk 136.000 M'

PEKERJAAN LANTAI II
A. PEKERJAAN STRUKTUR
A.1 Pekerjaan Beton

- Kolom 40/40
Beton (Fc' - 24,9 ( K-300) ) 10.240 m3

Begesting 102.400 m2

Tulangan 2,746.982 kg
- Plat lantai 12 cm

Beton (Fc' - 24,9 ( K-300) ) 30.282 m3

Begesting 373.478 m2
Tulangan 4,764.116 kg

- Balok 30/50

Beton (Fc' - 24,9 ( K-300) ) 18.060 m3

Begesting 120.400 m2

Tulangan 3,182.413 kg
No. Item Pekerjaan Sat.
Volume

B. PEKERJAAN ARSITEKTURAL

B.1 Pekerjaan Pasangan

- Pas. Dinding bata merah 1:4 126.645 m2


- Plesteran 1:4 t : 15 mm 253.290 m2

- Acian dinding bata merah 253.290 m2

- Benangan 64.000 m1

- Pekerjaan Dinding Partisi 135.120 m2


B.2 Pekerjaan Kusen-Daun Pintu & Jendela

- Pintu P1

Kusen alumunium 4" putih 6.100 m1


Kaca bening 8 mm 3.740 m2

Pintu kaca frameless 2.000 bh

- Pintu P2

Kusen alumunium 4" putih 18.300 m1

Daun pintu double teakwood 6 mm+rangka alumunium m2


6.000
2/4+finish lapis HPL

Engsel pintu 54.000 bh

Grendel pintu 18.000 bh


Lever handle 18.000 bh

Kunci selot 18.000 bh

- Jendela J1

Kusen alumunium 4" putih 43.680 m1

Slimar alumunium 87.360 m1

Kaca bening 5 mm 19.008 m2


Engsel jendela 24.000 bh

Kait angin 24.000 bh

Spring knip 12.000 bh

- Jendela J2

Kusen alumunium 4" putih 27.600 m1

Slimar alumunium 55.200 m1


Kaca bening 5 mm 15.120 m2

Engsel jendela 12.000 bh


Kait angin 12.000 bh

Spring knip 6.000 bh

B.3 Pekerjaan Plafond

- Plafond gypsumboard 9 mm + rangka hollow galvallum 252.350 m2

B.4 Pekerjaan Keramik

- Lantai granit 60/60 252.350 m2


- Plint Keramik 95.900 m1

- Lantai keramik kamar mandi 25/25 unpolished 6.750 m2

- Keramik dinding kamar mandi 20/40 13.155 m2

B.5 Pekerjaan Finishing

- Finishing cat interior 261.765 m2

- Cat plafond 252.350 m2


- Finishing cat weathershield 126.645 m2

C.1 Pekerjaan Sanitasi Air


- Kamar Mandi

Shower spray 3.000 unit

Mixer shower 3.000 unit

Kloset duduk 3.000 unit

Floordrain 3.000 unit

Kran diameter 1/2" 3.000 unit


- Pipa PVC tipe AW diameter 1/2" (air bersih) 53.550 m1

- Pipa PVC tipe AW diameter 3/4" (air bersih) 54.600 m1

- Pipa PVC tipe AW diameter 1" (air bersih) 55.300 m1

- PVC tipe D diameter 3" (air kotor) 47.600 m1

- PVC tipe D diameter 4" (kotoran padat) 47.600 m1


- Wastafel 9.000 unit

- Water Heater 100 lt 1.000 Unit

C.2 Pekerjaan Elektrikal


- Lampu TBS (3x18 watt) 10.000 Bh

- Lampu tidur 6.000 Bh

- Armature Downlight 5" (inbouw) + Lampu 20 W (lengkap) 17.000 Bh

- Pasang Exhaustfan Plafond 2.000 Unit

- Stop Kontak Dinding 1 Phase 13.000 Bh


- Saklar Seri (ex. Broco) 4.000 Bh

- Saklar Tunggal (ex. Broco) 12.000 Bh

- Pasang Titik Inst. Penerangan (ex. Supreme) 33.000 Titik


- Pasang Titik Inst. Stop Kontak 1 Phase (ex. Supreme) 1.000 Titik

- Pasang Titik Instalasi Exhaustfan Plafond 2.000 Titik

- Pasang Panel 1.000 Unit

- Kabel antar panel NYY 4x16 mm2 (Supreme atau sekw)

a. Panel Lt.1 ke Panel Induk 136.000 M'


No. Item Pekerjaan Sat.
Volume

PEKERJAAN LANTAI III


A. PEKERJAAN STRUKTUR

A.1 Pekerjaan Beton

- Kolom 35/35

Beton (Fc' - 24,9 ( K-300) ) 7.840 m3

Begesting 78.400 m2
Tulangan 2,103.158 kg

- Plat atap 10 cm

Beton (Fc' - 24,9 ( K-300) ) 31.710 m3


Begesting 391.090 m2

Tulangan 4,988.776 kg

- Balok 30/50

Beton (Fc' - 24,9 ( K-300) ) 31.710 m3

Begesting 211.400 m2

Tulangan 5,587.725 kg
B. PEKERJAAN ARSITEKTURAL
B.1 Pekerjaan Pasangan

- Pas. Dinding bata merah 1:4 106.885 m2

- Plesteran 1:4 t : 15 mm 213.770 m2

- Acian dinding bata merah 213.770 m2

- Benangan 220.000 m1
B.2 Pekerjaan Kusen-Daun Pintu & Jendela

- Pintu P1

Kusen alumunium 4" putih 6.100 m1

Kaca bening 8 mm 3.740 m2

Pintu kaca frameless 2.000 bh

- Pintu P2
Kusen alumunium 4" putih 18.300 m1

Daun pintu double teakwood 6 mm+rangka alumunium m2


6.000
2/4+finish lapis HPL
Engsel pintu 54.000 bh

Grendel pintu 18.000 bh

Lever handle 18.000 bh

Kunci selot 18.000 bh

- Jendela J1

Kusen alumunium 4" putih 43.680 m1


Slimar alumunium 87.360 m1

Kaca bening 5 mm 19.008 m2

Engsel jendela 24.000 bh

Kait angin 24.000 bh

Spring knip 12.000 bh


- Jendela J2

Kusen alumunium 4" putih 27.600 m1

Slimar alumunium 55.200 m1


Kaca bening 5 mm 15.120 m2

Engsel jendela 12.000 bh

Kait angin 12.000 bh

Spring knip 6.000 bh

B.3 Pekerjaan Plafond

- Plafond gypsumboard 9 mm + rangka hollow galvallum 252.350 m2


B.4 Pekerjaan Keramik

- Lantai granit 60/60 252.350 m2

- Plint Keramik 95.900 m1

- Lantai keramik kamar mandi 25/25 unpolished 6.750 m2


- Keramik dinding kamar mandi 20/40 13.155 m2

B.5 Pekerjaan Finishing

- Finishing cat interior 261.765 m2

- Cat plafond 252.350 m2

- Finishing cat weathershield 126.645 m2


C. PEKERJAAN MEP

C.1 Pekerjaan Sanitasi Air

- Kamar Mandi

Shower spray 3.000 unit

Mixer shower 3.000 unit


Kloset duduk 3.000 unit

Floordrain 3.000 unit

Kran diameter 1/2" 3.000 unit


- Pipa PVC tipe AW diameter 1/2" (air bersih) 53.550 m1

- Pipa PVC tipe AW diameter 3/4" (air bersih) 54.600 m1

- Pipa PVC tipe AW diameter 1" (air bersih) 55.300 m1

- PVC tipe D diameter 3" (air kotor) 47.600 m1

- PVC tipe D diameter 4" (kotoran padat) 47.600 m1

- Wastafel 9.000 unit


- Tandon Air 5000 l 3.000 unit
No. Item Pekerjaan Sat.
Volume

C.2 Pekerjaan Elektrikal


- Lampu TBS (3x18 watt) 10.000 Bh

- Lampu tidur 6.000 Bh

- Armature Downlight 5" (inbouw) + Lampu 18 W (lengkap) 17.000 Bh

- Pasang Exhaustfan Plafond 2.000 Unit

- Stop Kontak Dinding 1 Phase 13.000 Bh

- Saklar Seri (ex. Broco) 4.000 Bh


- Saklar Tunggal (ex. Broco) 12.000 Bh

- Pasang Titik Inst. Penerangan (ex. Supreme) 33.000 Titik

- Pasang Titik Inst. Stop Kontak 1 Phase (ex. Supreme) 13.000 Titik
- Pasang Titik Instalasi Exhaustfan Plafond 2.000 Titik

- Pasang Panel 1.000 Unit

- Kabel antar panel NYY 4x16 mm2 (Supreme atau sekw)

a. Panel Lt.1 ke Panel Induk 136.000 M'

- Kabel Ground Panel BC 16 mm2 (Panel Lt.3 ke Panel Induk) 36.000 M'
C.3 Pekerjaan Instalasi Penangkal Petir

- Pasang Penangkal Petir -Kurn Radius 85 m atau sekw. 2.000 Bh

- Bak Kontrol Pentanahan 1.000 Bh


- Pasang Grounding Penangkal Petir 1.000 Titik

- Sertifikasi Instalasi Penangkal Petir 1.000 Titik

You might also like