A. constraints.
B. scope statement.
C. scope management plan.
D. work breakdown structure.
2. Which of the following are the major processes for project integration
management?
3. Which of the following project would be the best for your company?
Project A has an NPV of $30,000 and will take six years to complete.
Project B has an NPV of $60,000 and will take three years to complete.
Project C has an NPV of $90,000 and will take two years to complete.
1. Project A
2. Project B
3. Project C
4. They all have the same value.
5. What would you do if you have created the project charter but could not
get it approved and your manager and his boss asked to begin the project
immediately?
A. Perform an impact analysis
B. Start work on only the critical path tasks
C. Set up an integrated change control process
D. Push to get the charter signed
7. Considering the following two projects. What will be the opportunity cost of
selecting project B?
Project A with an NPV of US $45,000;
Project B with an NPV of US $85,000;
A. US $130,000
B. US $85,000
C. US $45,000
D. US $40,000
A. a network diagram.
B. a detailed scope of work.
C. a detailed schedule.
D. deliverables and objectives.
9. Which of the following is the most appropriate sequence of the five project
management process groups that are linked by the results they produce,
e.g. the outputs of one often become the input to another?
A. -35% to + 75%
B. -10% to +10%
C. -10% to +25%
D. -25% to +75%
12. A project having which of the following benefit cost ratios would be the
BEST project when selecting from a list of possible choices?
A. 1.8
B. 2.2
C. -2.4
D. -1.8
13. Which of the following would be the BEST project amongst projects A, B,
C and D? Project A has an IRR of 12%. Project B has an IRR of 17%.
Project C has an IRR of 31%. Project D has an IRR of 21%.
A. Project A
B. Project B
C. Project C
D. Project D
14. Which of the following must a project manager do when he has been
assigned to a new project and has been given the completed project
scope?
15. The customer requests the new railroad cars be constructed from heavy
grade aluminum. After reviewing the requirements, two of your experts
inform you that the customer would be better off with steel cars. If you
again meet the customer over the issue and he directs you to go ahead
with the aluminum cars then what should you do?
A. Find a way to cut other costs and upgrade the cars to steel
B. Provide aluminum cars that meet the customer's requirements
C. Meet with your experts to find another proposal for the customer
D. Meet with the customer again to ensure that he understands the
expert opinions about using steel instead of aluminum
17. If the CEO of the company has assigned project manager to a project that
he wanted to do from a long time then what should the project manager
do?
Planning
A. constraints.
B. communications requirements.
C. technology available to transfer information.
D. description of information to be distributed.
A. Quality tools
B. Quality planning
C. Quality control
D. Quality assurance
A. Project sponsor
B. Project manager
C. Team
D. Functional manager
A. PERT
B. ADM
C. CPM
D. GERT
8. Negotiating across international cultures will involve mutual
interdependence between parties, so these negotiations should be
conducted in which atmosphere?
10. The examples of which of the following are adhere to legal requirements,
will satisfy competing needs, provide accurate and truthful representations
and disclose conflicts of interest?
11. A project manager immediately calls a team meeting to plan regarding the
change needed to material purchased for the project which he determines
during the execution of a project. What is this particular step called?
A. management by objectives.
B. lack of a change control system.
C. good team relations.
D. lack of a clear work breakdown structure.
A. Initiation
B. Closure
C. Planning
D. Execution
13. During the execution of the project, a new ISO version of standard 9000 is
issued and the project team is meeting with the quality department to
determine how the standard will apply to the project. This is part of which
quality process?
A. Quality analysis
B. Quality assurance
C. Quality control
D. Quality planning
14. Which of the following is one of the most important focuses of life-cycle
costing?
15. Which of the following is a decision rule where items from a lot are
randomly selected and accept or reject decision is based on cumulative
results?
A. single-sampling plan
B. double-sampling plan
C. sequential-sampling plan
D. random-sampling plan
16. If the task has an early start of day three, a late start of day 15, an early
finish of day nine and a late finish of day 23, then what is it called?
A. having a lag.
B. not on the critical path.
C. on the critical path.
D. progressing well.
17. If a project team is subdividing project work packages into smaller, more
manageable components then what is happening?
A. activity sequencing.
B. creating a WBS.
C. network diagramming.
D. decomposing.
A. Risk identification
B. Risk response planning
C. Risk response control
D. Risk quantification
19. If the project manager and project sponsor, who are discussing the project
costs and whether it is better to have their own company do part of the
project or hire another company to do the work, asked for your opinion,
then what will you say?
20. The project manager meets with the team and management to develop a
strategy, in response to a risk. After discussions, they decide that it would
be best to purchase insurance. Which principle are they using?
A. Transference.
B. Identification.
C. Avoidance.
D. Acceptance.
21. You are mentoring with another project manager who has completed risk
response planning and has a risk response plan. What should the project
manager do?
22. After a week into the project, the project sponsor informs you that the
executive steering committee has moved the project's finish date to two
weeks sooner than your published finish date. Assuming you are on
schedule and according to your project network diagram, if the critical path
for the project is six weeks then what will be the project slack?
A. Two weeks
B. Minus two weeks
C. Four weeks
D. Minus four weeks
23. A new testing center is going to be constructed over the next two years
and project sponsor and project manager have been identified. High-level
estimates begun and it is expected that the project can be completed
within budget and on schedule. If the only difficulty is in acquiring the
number of resources with the correct expertise to complete the work, the
project manager should spend more time creating which of the following?
A. responsibility chart.
B. resource-limited schedule.
C. responsibility assignment matrix.
D. risk analysis.
24. As a project manager, you are preparing your methods for quality
management. You are looking for a method that can demonstrate the
relationship between events and their resulting effects, in your project
management system. Which of the following would be the best choice for
accomplishing your objective when you want to use the method to depict
the events that cause a negative effect on quality?
A. Ishikawa diagram
B. Histogram
C. Control chart
D. Pareto chart
25. A project has four levels in the work breakdown structure and has been
sequenced using the arrow diagramming technique. As a project
manager, what would be your next time management activity after the
activity duration estimates for the above project have been received?
26. You are the project manager for a large manufacturing concern. Presently
it is working on a project that calls for a new building to be constructed for
housing a new clean system manufacturing process that is critical to the
success of the project. Construction is not a core competency of your
company. Your team has the ability to create a detailed SOW with
penalties if specific statements of work deliverables are not meet. You are
in procurement planning, evaluating which contract would work the best.
In this situation, which of the following type of contract should be
preferred?
A. Benchmark.
B. Statistical analysis.
C. Fishbone analysis.
D. Design of experiments.
28. The project team is creating a project plan. The management asks them
to identify project risks and provide some form of qualification output as
soon as possible. Which of the following should the team provide?
29. How is a transaction treated when the project manager is on a new project
and needs to purchase computers to do the project?
A. Diminishing cost.
B. Indirect cost.
C. Limited cost.
D. Fixed cost.
30. The members of a project team are arguing about the prospective sellers
who have submitted proposals. One team member is arguing in support of
one seller while another team member wants the project awarded to a
different seller. In such a case, the project team is said to be in which step
of the procurement process?
A. Source selection
B. Solicitation
C. Procurement planning
D. Solicitation planning
31. In which step, the project manager allocates overall cost estimates to
individual activities or work packages to establish a baseline for measuring
project performance?
A. Cost estimating
B. Cost management
C. Cost control
D. Cost budgeting
32. If a project manager uses a cause-and-effect diagram with the team to
determine how various factors might be linked to potential problems then
the project manager is in which step of quality management process?
A. Quality analysis
B. Quality planning
C. Quality assurance
D. Quality control
33. To manage a project effectively, work should be broken into small pieces
until which of the following?
34. You are the project manager and are determining the factors that might
influence specific quality variables. In case you have chosen to analyze
combination of color and size that will best contribute to the functionality of
the new product, then you are said to be in which step of quality
management process?
A. Quality planning
B. Design of experiments
C. Quality control
D. Quality assurance
35. A project team would need which of the following in order to adequately
develop a schedule when the project manager has received activity
duration estimates from them and is about to start schedule development?
A. Corrective action
B. Risk management plan
C. Change requests
D. Schedule change control system
36. You are the project manager of a large project. A team member from
research and development tells you that her work is too creative to provide
you with a fixed single estimate for the task. Both of you decide to use the
average time the task has taken in past projects, to predict the future.
This is an example of which of the following?
A. Monte Carlo
B. Parametric estimating
C. PERT
D. CPM
37. A project team is scattered across North America, South America and
Europe and there are seven companies working on the project with 67
core team members. Which of the following would have the greatest
impact on making the situation easier to manage the project team?
38. A project team has created a plan for implementing the quality policy. If
the plan is changed during the project then which of the following will also
change simultaneously?
A. WBS
B. Organizational policies
C. Staff management plan
D. Project scope statement
40. The concept of optimal quality level is reached at the point where the
incremental revenue from product improvement equals the incremental
cost to secure it. This statement directly refers to which of the following?
41. In order to handle a risk that one of your team has discovered about the
equipment, you have chosen to prototype the equipment. What is this
called?
A. Risk Avoidance
B. Risk Acceptance
C. Risk Mitigation
D. Risk Transference
42. A project team is arguing about the prospective sellers who have
submitted proposals. If one team member argues for a certain seller while
another team member wants the project to be awarded to a different
seller, then the project manager should remind the team to focus on which
of the following in order to make a selection?
A. Evaluation criteria
B. Procurement documents
C. Procurement management plan
D. Procurement audits
43. What is the standard deviation of the task, if the optimistic estimate for the
task is 12 days and the pessimistic estimate is 18 days?
A. 1
B. 1.3
C. 1.6
D. 3
44. What does the US $8,000 represent, in case of a risk event having 80%
chance of occurring, and the impact will be US $10,000?
A. Expected value
B. Risk value
C. Contingency budget
D. Present value
45. What is the PERT estimate, if the optimistic estimate is one, the
pessimistic estimate is nine and the most likely estimate is eight?
A. 6
B. 7
C. 8
D. 9
46. You have been assigned as a project manager for a large one-year
telecommunications project which is halfway done. The project team
consists of five sellers and 20 of your company's employees. Which of the
following should you refer to understand who is responsible for doing what
on the project?
A. Gantt chart
B. Resource histogram
C. Responsibility matrix
D. Project organization chart
47. A project team is in the design stage of a new mountain bike prototype.
The team is in the process of identifying the type of frame and material
that will provide high performance at a low cost. Which technique can be
used to determine these variables?
A. Design of experiments
B. System flowchart
C. Benefit/cost analysis
D. Ishikawa diagram
Execution
2. A project had four team members originally and now the scope has
expanded and there are a total of six people in the project team. What are
the total number of communication channels does the project have?
A. 9
B. 12
C. 15
D. 18
3. If a project manager says, "Why can't we solve this problem by all sides
giving in a little”, then what is the technique he is trying to use which also
conflicts the resolution?
A. Forcing
B. Compromising
C. Problem solving
D. Withdrawal
4. The project manager meets with both team members to uncover the reason
for the problem. If one of them complains that the other member has once
again failed to provide necessary information then this is an example of
which of the following?
A. Confronting.
B. Smoothing.
C. Withdrawal.
D. Compromising.
5. An equipment seller provided a buyer with all the O&M (operation and
maintenance) manual information on their equipment in electronic disk
format. The buyer's project manager demanded written copies of these
manuals. The seller refused, stating that the information had been supplied
in the "usable & complete" format required in the contract. This
disagreement is an example of an oversight made during which stage of the
project's development?
A. Contract administration
B. Quality control
C. Procurement planning
D. Scope verification
7. A project manager gives the following information by using the earned value
analysis of a software development project:
On June first, the CPI computes to 1.0 and the schedule variance is zero.
On June third, the banks of the nearby river overflow and flood the
development computer room, shutting down all operations for two weeks.
The project is struck by which of the following?
A. Known-unknown risk.
B. Unknown-unknown risk.
C. Foreseen risk.
D. Known risk.
8. Which of the following should be chosen if you are asked to select tools and
techniques to implement a quality assurance program to supplement
existing quality control activities?
A. Statistical sampling
B. Trend analysis
C. Quality audits
D. Pareto diagrams
10. A project manager has a large team consisting of people from many
functional areas of the company. Which of the following is the best
method to get the team's cooperation?
A. Reward Power
B. Formal Power
C. Referent Power
D. Penalty Power
11. If a project manager is spending all his time watching over the team and
team members feel that he is always second-guessing them then what is
the project manager called as?
12. A project manager is creating the agenda for a status meeting with the
team. He receives input from one of the team member that an item should
be added. Another team member says the team is not ready to resolve
the item during the meeting. After much discussion, the project manager
decides to put the item on the agenda as an initial discussion item only.
Which conflict resolution technique is used by the project manager?
A. Force
B. Smoothing
C. Withdrawal
D. Compromise
13. During project execution you discover that you are working on a task
requested by the customer but not included in the contract. The customer is
already upset about the cost of several items she claims your company left
out of the contract. No one in your company wants to discuss the change
with the customer for fear of losing the contract. What is the best course of
action?
14. A layoff has just been announced that will be taking place in the next
month. There is a good chance of including some of the people from your
project team. If you tell the team, "Let's calm down and get back to work,
maybe our performance in the next month will help keep us from losing
our jobs," when the team is discussing the layoff to the exclusion of
everything else then which conflict-resolving technique are you using?
A. Smoothing
B. Compromising
C. Withdrawal
D. Forcing
15. Someone from the quality department comes to see you for beginning a
quality audit of your project. As a project manager what should you explain
to the team about the purpose of a quality audit, if the team is under
pressure to complete the project as soon as possible?
A. Tight matrix
B. Functional matrix
C. Weak matrix
D. Strong matrix
17. During a critical design review meeting for a large project regarding a
major technical problem, one of the subcontractor's engineer mentions
that he experienced a similar situation and he had some ideas on how to
solve the current problem. Which of the following did the engineer use?
A. Referent Power
B. Experience Power
C. Manipulative Power
D. Expert Power
18. You are developing a complex product that does not resemble anything
your organization has done before. You are using a resource to develop
this product that is in high demand elsewhere in your organization.
Though the project's timeframe is very aggressive, in order to meet the
schedule, only a limited amount of testing is done. Once the testing is
completed, the resource is released. The product works fine when being
tested, but in production, it performs badly. This results in a substantial
amount of rework and extra costs to reacquire the resource on an
overtime basis. Which of the following is the cause for this situation?
19. During project execution the project manager calls a meeting of the
affected stakeholders to work through the problem. He comes to know that
they feel the project cannot meet its quality standards. The project
manager is in which of the following phase?
A. Quality analysis
B. Quality planning
C. Quality assurance
D. Quality control
20. You are the project manager of a new project. The project deliverables
have changed three times. The functional managers keep removing
people from the team and the project baseline schedule has been
adjusted four times in the first week. Which of the following is the
company lacking?
21. You are trying to explain how a contract control system differs from a
project control system. If a project manager is working on his first project
with outside sellers and is familiar with project control systems but not
contract control systems then which of the following is best to point out
about contract control system?
22. You are the new project manager and worked as a project expeditor for the
past three years for a construction project in a neighboring state. The
construction crew has worked together for a number of years. One of the
project manager's tasks is to pursue all of the historical risk information
available. But you don't have enough time to access all available sources.
Relying least on which of the following will help you in serving better?
23. In a meeting with the team member the project manager says, "I know you
want to become involved in meetings with the customer. Because of your
performance on the project so far, I have rearranged things so you can
become involved with the customer.” Which power is the project manager
using in this case?
A. team building.
B. constraints.
C. team alignment.
D. reward power.
24. The project manager evaluates the change that is requested by a customer
for adding a new filtration system to the project in place of a cleaner bag. It
is most important for the project manager to consider the impact to which of
the following?
A. subsequent tasks.
B. communication plan.
C. triple constraint.
D. sponsor.
25. Which of the following will not help the project manager while he is
finalizing the resources for the project team?
26. Considering a corner office as which of the following results in the thought
“giving a team member a corner office is different than giving him health
benefits”?
A. Fringe benefit.
B. Example of formal power.
C. Perquisite.
D. Use of the expectancy theory.
27. You are the project manager of a large project. You have a firm fixed price
contract with a clause stating that all changes in the scope of work must be
written. Which of the following should you use, as a conflict management
strategy with the team member, if one of your team members verbally
instructed the seller to add a change that resulted in a 100% task overrun?
A. Problem solving
B. Punishment
C. Withdrawal
D. Negotiating
28. If you are in the middle of a complex negotiation and the other party says,
"We need to finish in one hour because I have to catch my plane" then
which of the following negotiation strategies is used by the party?
A. Extreme demands
B. Delay
C. Good guy, bad guy
D. Deadline
29. You are the project manager of a large project. A project team member
comes to you during project execution and tells that the project cannot meet
the quality standards based on his analysis. In which quality management
process are you, if you meet all the relevant parties to analyze the situation?
A. Quality analysis
B. Quality planning
C. Quality assurance
D. Quality control
30. What should a project manager use if he wants to report on the actual
project results that are planned?
A. Forecasting report.
B. Variance report.
C. Trend report.
D. Status report.
31. You are the project manager of a software project. The construction phase
of a new software product is near completion and the next phase is testing
and implementation. Which of the following should be most concerned for
you before moving onto the final phase, when the project is two weeks
ahead of schedule?
A. Performance reports
B. Cost control
C. Scope verification
D. Quality control
32. As a project manager, you are working on a complex project with people
from around the world. Using which of the following can you easily control
the situation, if the project schedule is set, but the tasks require detailed
integration with other tasks being done by the buyer?
A. Configuration management
B. Change control board
C. Work authorization system
D. Historical information
33. Who should determine the priorities among projects in a company, if one of
your team members informs you that he does not know which of the many
projects he is working on is the most important?
A. Senior management
B. Project manager
C. Team
D. Sponsor
34. What might be the reason if the project you are working on has an increase
in cost effectiveness, increased productivity and increased morale?
35. You are the project manager of a new software development project in
progress and working with the quality assurance department. Which of the
following should be done before they start the process of improving
everyone's confidence, that the project will satisfy the quality standards?
A. Rework
B. Quality management plan
C. Completed checklists
D. Results of quality control measurements
36. During project execution, a new ISO version of standard 9000 is issued.
The team meets the quality department to determine how the standard will
apply to the project. The project team is said to be involved in which of the
quality management process?
A. Quality assurance
B. Quality analysis
C. Quality planning
D. Quality control
A. independent estimate.
B. screening system.
C. weighting system.
D. part performance history.
38. The total distribution 3 sigma from the mean equals which of the
following?
A. 95.40%
B. 99.99%
C. 99.73%
D. 68.26%
39. A contract has a requirement that the seller will submit monthly
acceptance tests to the project manager. If the seller does not submit such
acceptance tests then the seller is said to be:
41. Which is the most important thing a project manager should ensure when
he is in the process of scope verification of a deliverable with the
customer?
A. Completeness
B. Acceptance
C. Timeliness
D. Accuracy
42. Which of the following is the motivational theory that explains what
motivates people is the work itself including things like responsibility, self-
actualization and professional growth?
A. McGregor
B. Herzberg
C. Maslow
D. Deming
43. Which of the following can create the most misinterpretation in the
statement of work?
A. Quality management
B. Quality control
C. Quality planning
D. Quality assurance
45. A project has several teams. Team C has missed several deadlines in the
past. This has caused Team D to crash the critical path several times.
Whom should the project leader of Team D meet?
46. Which of the following is the best strategy for a project team working on
an important and complex project that requires a lot of coordination?
47. During a team meeting, the team argued about the method of integration
for 30 minutes and then the project manager rescheduled the issue for the
next team meeting as it resulted to nowhere. For which of the following
this is an example?
A. withdrawal.
B. forcing.
C. smoothing.
D. compromising.
Controlling
A. Quality planning
B. Quality control
C. Quality analysis
D. Quality assurance
3. If a task needs more time and the project manager determines that there
is enough reserve to accommodate then who needs to approve the
change?
A. Project manager
B. Team member
C. Functional manager
D. Management
4. If the customer wants to expand the project scope after the performance
measurement baseline has been established then which document will the
customer need to submit?
A. Statement of work
B. Change request
C. Invoice
D. Revised project schedule
5. If a project manager gets a report from the risk owner that a risk did not
occur then what should the project manager do?
6. Under which of the following circumstances would you use a Gantt chart
instead of a network diagram?
A. flowcharts.
B. benchmarks.
C. PERT charts.
D. Gantt charts.
10. Which of the following will be your position when you have just completed
a cost estimate on the project and you're assuming there's a 15+ACU-
chance to exceed this estimate?
12. Which of the following you should do first when a risk occurs during
project execution and has a greater impact on the project than was
anticipated?
15. Which of the following would be the best way to determine the status of a
project when the buyer asks the project manager for the status of the
project?
16. What should you do first when a customer requests a change to the
project that will increase the project risk?
A. Project sponsor
B. Project manager
C. Stakeholder
D. Project team
19. A project requires 100 widgets to be built in five weeks and the project
manager has just begun week three with an overall budget of +ACQ-
10,000. To date +ACQ-2,000 have been spent with 40 widgets built
successfully. In this situation what will the cost variance tell the project
manager about the project?
A. On budget.
B. Proceeding at 100+ACU- of the expected rate.
C. Getting +ACQ-2 of work for every dollar spent.
D. +ACQ-2000 under budget.
20. Measuring the height of one of the tables manufactured by your company
to determine whether it meets your quality standards is an example of
measuring what?
A. a sample.
B. a population.
C. statistical dependence.
D. statistical independence.
21. The current update to the schedule performance report shows no variance
in the schedule. Basing on this you tell the client that the project is on
time. If your team members know that you just missed a major milestone
and the project will not meet its startup date then what is this called?
22. After two months of the start of designing the project, the customer
requested a modification to the product. The changes were made without
notifying the project manager. The changes resulted in different final
results in the tests than expected. This scenario is an example of which of
the following?
23. You are a project manager for a small construction project that is
budgeted for +ACQ-72,000 over a six week period and as of today +ACQ-
22,000 of the budget has been spent. To complete work that is originally
expected would cost +ACQ-24,000. Being a project manager according to
your schedule, you should have spent +ACQ-30,000 by this point.
Considering the above facts what is the situation of your budget?
A. on budget.
B. over budget.
C. under budget.
D. not having enough information provided.
24. If a project team budgeted+ACQ-3,000 for the work performed and has
spent +ACQ-4,000 to date then what will be the cost variance when they
budgeted +ACQ-5,000?
A. +ACQ-1,000
B. +ACQ-2,000
C. (+ACQ-1,000)
D. (+ACQ-2,000)
25. You are deciding whether to lease or buy an item for the project. The
daily lease cost is +ACQ-240 and the cost of purchasing the item is
+ACQ-6,800 for the investment cost and +ACQ-70 for the daily cost. How
many days will it take for the lease cost to equal the purchase cost?
A. 80
B. 55
C. 40
D. 35
26. Which of the following is a helpful tool in focusing on the most difficult
issues that represents information presented in its order of priority?
A. A fishbone diagram
B. A Pareto chart
C. Flow charts
D. A control chart
27. If a management team will continue working on a project that has spent
+ACQ-500,000 and the original estimate for work completed to date was
+ACQ-200,000 then what is the difference between the actual cost and
the original estimate (+ACQ-300,000) known as?
A. sunk cost.
B. example of how bad the schedule was.
C. customer cost.
D. direct cost.
28. When it comes to changes, the project manager's attention is best spent
on which of the following?
A. making changes.
B. preventing unnecessary changes.
C. informing management of changes.
D. tracking and recording changes as they happen.
29. Suppose the project has just begun and one of the stakeholders asks the
project manager about making a change to the format of the deliverable
for task Y. If she wants to know how to go about submitting the change
for review then the project manager should direct her to which of the
following?
30. When the project stakeholders are invited by a project team to help them
inspect quality of the project, then what would not be the output of the
activity?
A. Completed checklists
B. Quality management plan
C. Acceptance decisions
D. Rework
31. You are the project manager of a project that is seriously delayed. Earned
value analysis shows that the project needs to be completed 10+ACU-
faster than the work has been going. To get the project back on track,
management wants to add 10 people to a task currently assigned to one
person, but you disagree and tell that noting of such plans will increase
the speed. Which of the following principle are you using?
A. Fast tracking.
B. Life-cycle costing.
C. Earned value.
D. Law of diminishing returns.
32. Being the project manager what would be better for you, if you are
spending a lot of time solving problems that arise during project
execution?
33. If the management wants to know how long the project will take without
the nine resources per month that are committed to your project earlier
then what kind of activity is this called?
A. Leveling
B. Crashing
C. Fast tracking
D. Floating
34. What would be the range of estimates that will involve the LEAST risk if it
is assuming that the ends of a range of estimates are 3 sigma from the
mean?
35. You are the project manager of a six month project and have held bi-
weekly meetings with your project sponsors. After five-and-a-half months
of work the project is on schedule and budget, but the sponsors are not
satisfied with the deliverables. This results in delay of project completion
by one month. What is the most important process that could have
prevented this situation?
A. scope planning.
B. scope change control.
C. risk monitoring and control.
D. schedule control.
36. You are the project manager of a project that has had a major defect. You
have involved the project team and process engineers in analyzing the
situation. If one of the groups says that the real fault is the age of the
equipment and another says it is the lack of a material for the correct
quality then you decide to use an Ishikawa diagram to address the root of
the problem. In this situation, the group is said to be involved in which of
the quality management process?
A. Quality control
B. Quality analysis
C. Quality planning
D. Quality assurance
A. behind schedule.
B. on schedule.
C. ahead of schedule.
D. having not enough information provided.
38. A team member notices that the plan worked only marginally during the
implementation of a contingency plan. What should he recommend for, if
there were three similar contingencies plans developed for other risks that
have not yet happened?
39. The widget production project is well underway. The requirements are
clear that each widget must weigh between .320 and .325 ounces. The
first day of test production resulted in 1247 widgets. Of the widgets
inspected 47+ACU- fell within the acceptable weight range. For which of
the following this is an example?
A. Variable sampling
B. Control charting
C. Attribute sampling
D. Flow charting
A. scope management.
B. change management process.
C. scope decomposition.
D. quality analysis.
41. The customer wants to expand the project scope after the performance
measurement baseline has been established. The customer needs to
follow which of the following procedure?
A. Time management
B. Scope control
C. Configuration management
D. Cost control
42. The testing results for a new computer modulation project indicate a
problem with the on-board computer sensors. If the project manager calls
a meeting with the team to analyze the problem then he is said to be
involved in which of the following?
A. quality management.
B. quality control.
C. quality assurance.
D. quality planning.
43. A project manager faces a problem with how two of the parts fit together
on the new computer and how the software uploads to the system. To
plan a strategy for resolving these problems, it is best to determine
whether the problems are:
A. impacting quality.
B. non-conforming.
C. normally distributed.
D. statistically independent.
44. Which approach is most often used when current variances are seen as
typical of future variances?
A. EAC = AC + ETC
B. EAC = AC + BAC – EV
C. EAC = ( AC + (BAC – EV)/CPI)
D. EAC = ( AC + (BAC + EV)/CPI)
A. increased risk.
B. decreased cost risk.
C. lower customer satisfaction.
D. decreased morale.
46. When two people on the same project team found that they are working
on the same scope of work then it is due to lack of which of the following?
A. a matrix organization.
B. good work breakdown structure.
C. status meetings.
D. sponsor direction.
47. Which of the following includes reviewing the work products and results to
ensure that all were completed satisfactorily and formally accepted by all?
A. Risk management
B. Quality control
C. Change control management
D. Scope verification
Closure
5. All the technical work of the project is completed. Which of the following
still remains to be done?
A. Project budget
B. Lessons learned
C. Risk management plan
D. Staff management plan
6. Which of the following are the outputs of the Contract Closeout process?
7. Two of the team members are currently documenting and verifying the
product. The other two are collecting project records, analyzing project
success and archiving lessons learned. In this case the team is engaged
in which of the following?
A. Administrative closure
B. Contract administration
C. Performance measurement documentation
D. Contract closure
8. Your company and its seller are in the middle of a long dispute over the
costs of terminating the contract. You determine that the only way to
resolve the problem is to have it heard and resolved by a neutral party. As
a project manager, you should use which of the following?
A. arbitrator.
B. lawyer.
C. functional resource manager.
D. conflict solution expert.
10. What is the status of the contract in case a seller completes the work as
specified, with a clear scope but the buyer is not pleased with the results?
A. Waived.
B. Null and void.
C. Incomplete.
D. Complete.
11. A mentor is worried about the first procurement audit he is going to face.
When he approaches you for help, as a project manager what is the
reason or the explanation you give to avoid his worry?
12. In which of the following phase is the project when the project team has
completed all the work specified in the contract scope of work and the final
deliverable has been sent to the client?
A. Closure
B. Completion
C. Scope verification
D. End of execution
13. After completion of administrative closure for the project execution phase
you will have project archives, formal acceptance and what else?
14. None of the stakeholders were confident the project would meet the end
date. Due to this reason instead of celebrating the end of the project, they
are breathing a sigh of relief. Which of the following is not a reason for the
project to have difficulty?
A. Lack of milestones
B. Lack of a staffing management plan
C. Lack of a payback period
D. Lack of a communication plan
Professional Responsibility
1. You are told to pay a US $6,000 fee to the government permit officer to
obtain the facility permit required by law to start construction visiting the
country where a new branch office is being built. This is a standard
practice and is required by the law. Which of the following step you should
take?
2. The software development project is not going well. There are over 50
stakeholders who are not agreeing on the project objectives. One
stakeholder believes the project can achieve a 40% improvement while
another believes a 70% improvement is possible. The project manager
thinks a 20% improvement is more realistic. What is the BEST course of
action in such a case?
A. Move forward with the project and hope more information comes to
light later to settle the issue
B. Average the numbers and use that as the goal
C. Perform a feasibility analysis
D. Ask the sponsor to make the final decision
Explanation: This type of issue must be settled early in the project
because the content and extent of the entire project plan depends on the
deliverables and objectives. The best way to resolve the issue is choice C,
which is a problem solving method. The other choices are really
smoothing or forcing.
3. The management of WIPRO has decided that all orders will be treated as
"projects". The project managers will be used to update orders daily,
resolve issues and ensure that the customer formally accepts the product
within one month of completion. The revenue from the individual orders
can vary from US $1000 to US $250,000. There is no need of project
manager to perform planning or provide documentation other than daily
status. How can we define such a situation?
5. You are in the middle of a new product development project for Wipro
Company. You discover that the previous project manager made a US
$300,000 payment that was not approved in accordance with the company
policies. Luckily, the project CPI is 1.2. What should you do now?
A. Bury the cost in the largest cost center available
B. Put the payment in an escrow account
C. Contact the manager
D. Ignore the payment
Explanation: The only data that definitely tells something is SPI. Less
than one is bad, so the project is currently predicted to be behind
schedule.
8. At the stage of the completion of the project, the project manager realizes
that he needs to decrease project costs. After researching options, he
comes up with the following choices. Which of the following choices would
Decrease Project costs?
Explanation: Choice A will not decrease project costs, just costs over the
life of the solve the problem. Choice A will not solve the problem. Choice B
will almost always lead to higher costs, and choice C could affect costs
later.
10. Assume that you are halfway through a major network rollout. There are
200 locations in Banglore with another 20 in Mumbai. A software seller
has released a major software upgrade for some of the equipment being
installed. The upgrade provides the customer with functionality requested
by them which is not available at the beginning of the project. What is the
BEST course of action that can be taken under such circumstances?
Explanation: Because the schedule and scope are already approved, all
changes must go through the change control process that was defined
during the project planning process.
11. While you are working on research and development project, your
customer asks to include a particular component in the project. You
realize that this will be new work, and you are in shortage of funds. What
is the immediate action that can be taken by you?
A. Delete another lower priority task to make more time and funds
available
B. Use funds from the management reserve to cover the cost
C. Follow the contact change control process
D. Ask for more funds from the project sponsor
12. You are a project manager for one of many projects in a large and
important program for WIPRO. At a high-level status meeting, you have
noticed that another project manager has reported his project on
schedule. Looking back on your project over the last few weeks, you
remember many deliverables from the other project arrived late. What is
the action that should be taken?
13. You have always been asked by your management to cut your project
estimate by 20% after you have given it to them. The scope of your new
project is unclear and there are over 50 stakeholders. Management
expects a 35% reduction in downtime as a result of the project. Which of
the following is the BEST action to be taken in this situation?
Explanation: There is no indication that the labor dispute has caused any
problems, so there is no need to cease doing business with the corn any
or to pull them off the project. The best choice would be to inform others in
your company.
15. You found out that a major subcontractor for your project consistently
provides deliverables late. The subcontractor approaches you and asks
you to continue accepting late deliverables in exchange for a decrease in
project costs. For which of the following is the above an example?
A. Confrontation
B. Compromise
C. Smoothing
D. Forcing
16. The Management has promised you a part of the incentive from the
customer if the project is completed early. Later while finalizing a major
deliverable, your team informs you that the deliverable meets the
requirements in the contract but will not provide the functionality the
customer needs. If the deliverable is late, the project will not be completed
early. What action should be taken in such a situation?
17. While testing the strength of concrete poured on the project, you notice
that over 35% of the concrete does not meet your company's quality
standards. You feel certain the concrete will function as it is, and you don't
think the concrete need to meet the quality level specified. What is that
you need to do?
18. Suppose you are the project manager for a new international project, and
your project team includes people from four other countries. Most of the
team members have not worked on similar projects before and the project
has strong support from senior management. What is the BEST thing you
can do to ensure that cultural differences do not interfere with the project?
A. Spend a little more time creating the work breakdown structure and
making sure it is complete
B. As the project manager, make sure you choose your words
carefully whenever you communicate
C. Ask one person at each team meeting to describe something
unique about their culture
D. Carefully encode all the project manager's communications
Explanation: You should have noticed that choices A and C involve more
people then just the project manager. Since this is an issue involving
everyone, everyone should be involved. Choice A may be a good idea in
all cases, however, it does not specifically address cultural issues.
Therefore, the answer must be C.
A. Issue the deliverable and get formal acceptance from the customer
B. Note the problem in the lessons learned so future projects do not
encounter the same problem
C. Discuss the issue with the customer
D. Inform the customer that the deliverable will be late
A. Risk identification
B. Risk quantification
C. Risk response planning
D. Risk monitoring and control
Explanation: This is a new project and even though assessing the range
of possible outcomes is done in a later step, risk identification should be
done first.
22. The customer on a project tells the project manger that he has run out of
money to pay for the project. What is the action that has to be taken by the
project manager initially?
A. Shift more of the work to later in the schedule to allow time for the
customer to get the funds
B. Reduce the scope of work and enter closure
C. Release part of the project team
D. None of these
23. You are the project manager for a large project under contract with the
government. The contract is for two year and the multi-million project is
signed six months ago. You were not involved in contract negotiations or
setting up procedures for managing changes. But now you are flooded
with changes from the sponsor and from people inside your organization.
Who is normally responsible for reviewing major changes to the
project/contract formally?
25. The previous project manger for the project in your company managed it
without much project organization. There is a lack of management control
and no clearly defined project deliverables. Which of the following would
be the BEST choice for organizing the project in a better way?
Explanation: Choice D will help, but not help both control and
deliverables for each phase. Choice C would help control each phase but
would not control the integration of the phases into a cohesive Whole.
Choice B would help improve subsequent phases but would do nothing for
control and deliverables. Effective project management requires a life-
cycle approach to running the project. Choice A is t-Re only answer that
covers both control and deliverables.
26. You are taking over a project and noticed that six other individuals have
signed the project charter. Which of the following should be MOST
concern for you?
Explanation: This situation implies that there are six areas concerned
with this project. In addition to added communication requirements, you
should be concerned with competing needs and requirements impacting
your efforts on configuration management.
27. You are the project manager for a large construction project. The project
objectives is to construct a set of outbuildings to house the Olympic
support team that will be arriving in your city 12 months form the project
start date. You've been given a budget of $20 million to complete this
project. Resources are easily attained. Which of the following of the triple
constraints is the primary constraint for this project?
28. You are project manager for a large construction project. The project
objective is to construct a set of outbuildings to house the Olympic support
team that will be arriving in your city 12 months form the project start date.
Resources are not readily available as they are currently assigned to other
projects. An expert crane operator is needed for this project two months
from today. Which of the following skills will you use to get the crane
operator assigned to your project?
29. You are project manager with technical expertise in the pharmaceutical
industry. You've decided to try your hand at project management in the
entertainment industry. Which of the following is true?