2013 Examination Paper August
2013 Examination Paper August
INSTRUCTIONS TO CANDIDATES:
It is expected that candidates will present their answers in an engineering manner making
full use of diagrams, tables, and relevant circuits where applicable and showing full working
in calculations. Neatness in diagrams is essential and will be considered in the allocation of
marks. Questions are to be answered as a prospective manager of electrical engineering at
a NSW mine.
Year Incident
2013
• 2 events of longwall lights with lenses smashed after shot firing stone
off the shearer
• 2 events of man transporter head lights having smashed lenses found
in crib room
• 1 event of bolts found missing in fan starters after maintenance
• 4 events of damaged shuttle car cables showing evidence of arcing
• 3 events of cable arcs in other type of cables being evident
2012
• 3 events of cables pulled out of head lights on diesels
• 1 event of incorrect bolts found in shuttle car cable reel
• 4 events of IS telephones found to have hand sets missing
• 4 events of damaged shuttle car cables showing evidence of arcing
2011
• 4 events of damaged shuttle car cables showing evidence of arcing
• 2 events of damaged glands found on Exd enclosures
• 4 reports from cable repairers of evidence of arcing
• 2 events where plastic blanks were found in a shuttle car panel
a) On identifying these results what would be your initial course of action? (4 marks)
b) Who would be involved in any action you take? (2 marks)
c) Draft the executive summary section of your report, outlining your long-term strategies
to fix the high number of incidents. Your report should be suitable to send to the
Electrical Inspector. (4 marks)
b) What information should be included in your Power System Single Line Diagram?
(2 marks)
Page 2 of 8
CEE1 Application of Electrical Engineering to Mining August 2013
d) In managing the Fault Study for the mine power system, what would be considered as
triggers for a review of the study to ensure it is kept up to date? (3 marks)
e) The primary fundamental principle that should be applied to the design, selection and
installation of electrical protection and earthing systems at your mine is that the first
fault to be detected and cleared is always what type of fault? Why? (2 marks)
You have brought this to the attention of the Mine Manager who as asked you to develop a
strategy and identify what further actions the mine should take.
Page 3 of 8
SAFETY BULLETIN
Electrical hazards associated with
variable speed drives and earth fault
current limited systems
BACKGROUND
2. Where a machine is fitted with its own isolation transformer eg the VSD
traction drives on a longwall shearer the EMI filter on these drives will not
interact with any other VSD drives in the longwall panel.
RECOMMENDATIONS
Whilst the following recommendations are good engineering practice, additional
emphasis should be placed on them until a permanent engineering solution(s) is
provided.
1. The values for the earth continuity of machinery fed via reeling and trailing
cables, where VSD drives are utilised, need to be maintained at a minimum
value. This is the primary protection against excessive touch potentials and
should also be considered best practice in normal mining environments.
Note: The normal value for tripping of earth continuity relays is 45Ώ. This
upper value of possible earth resistance, allowing for known pilot resistance
of the cables, may result in potentially dangerous voltages appearing at a
machine. Measures should be used to ensure that the machine cable’s
earthing resistance remains as low as practical rather than potentially
operating at the upper limits of the pilot relay.
2. Equipment fed via reeling or trailing cables should be protected with earth
leakage units set for no intentional time delay ie ‘instantaneous’ initiation of
fault detection.
3. The length of all reeling and trailing cables, including those supplying DCBs
and Distribution Boxes should be kept as short as possible. Relocation of
transformers should be undertaken where possible, in preference to the use
of extension cables to machinery.
4. Effective mechanical protection should be provided to all cables fed from a
VSD drive to minimise the likelihood of damage to the cables.
5. Where possible rearrange the VSD operated machinery at the mine to
minimise the number of VVVF drives and associated EMI filters with any
single substation/transformer eg distribute VSD operated equipment evenly
between underground panels where such equipment does not have its own
onboard isolation transformer.
Page 3
NOTE: Please ensure all relevant people in your organisation receive a copy of
this safety bulletin, and are informed of its content and recommendations. This
safety bulletin should be processed in a systematic manner through the mine’s
information and communication process. It should also be placed on the mine’s
notice board.
Signed
Rob Regan
DIRECTOR
MINE SAFETY OPERATIONS BRANCH
NSW TRADE & INVESTMENT
View more safety bulletins at www.dpi.nsw.gov.au/minerals/safety/safety-bulletins. If you would like to receive safety
bulletins by email, enter your contact details at www.dpi.nsw.gov.au/minerals/safety/signup
CEE1 Application of Electrical Engineering to Mining August 2013
It also details commissioning; testing and documentation requirements to ensure safety; and
compliance with relevant Standards for different types of explosion protection apparatus, and
reliable operation of the equipment while in service. It also makes reference to pre-overhaul
equipment audits
a) How would you identify when Exd equipment should be overhauled? (1 mark)
b) What is the purpose of the pre overhaul inspection? (1 mark)
c) When should the initial pre overhaul inspection be carried out? (1 mark)
d) When should a second pre overhaul audit be carried out? (1 mark)
e) What is the expected period between pre-overhaul audits? (1 mark)
f) Who should conduct a pre-overhaul audit of Exd equipment? (1 mark)
g) Whilst undertaking a pre-overhaul audit, a competent person identifies ‘L’ and ‘l’
dimensions that do not comply with the certification drawings. Outline your possible
options to resolve the problem. (4 marks)
Page 7 of 8
CEE1 Application of Electrical Engineering to Mining August 2013
The project manager has sourced an electric pump that will pump 7500 litres of water per
minute at a maximum 300m of head. The calculated maximum head will be approximately
120m with a flow of 10000 litres per minute derived from the pump curve.
Assume the density of the mine water to be the same as that of pure water
Document any assumptions made in your calculations.
a) The power requirements to drive the pump at the nominated maximum head and flow-
rate (3 marks)
b) The expected time frame to de-water the area, also allowing for maintenance and
breakdowns (2 marks)
c) The approximate power consumed to de-water the area (2 marks)
d) The size of generator that you would require to run the pump (2 marks)
e) What contingencies would you put in place for this installation? (1 mark)
END OF QUESTIONS
END OF PAPER
Page 8 of 8
(CEE2)
INSTRUCTIONS TO CANDIDATES:
It is expected that candidates will present their answers in an engineering manner making
full use of diagrams, tables, and relevant circuits where applicable and showing full
working in calculations. Neatness in diagrams is essential and will be considered in the
allocation of marks. Questions are to be answered as a prospective manager of electrical
engineering at a NSW mine.
d) With the use of a diagram identify what “Exclusion Zones” refer to for a continuous
miner in this standard. (AS4240.3:2013) (3 marks)
a) In your Electrical Engineering Management Plan, what systems and standards should
be in place to deal with these types of issues? (4 marks)
b) With respect to the management systems and plans outlined in your previous answer,
what are some of the specific rules you would have in place to help ensure that the
risk of cable damage is minimised at your mine? (6 marks)
CEE2 Legislation and standards applicable to underground coal mines August 2013
b) AS4836 – “Safe working on or near low voltage electrical installations and equipment”
requires a number of safety precautions to be undertaken or considered before and
during testing. List 6 of these requirements (3 marks)
c) AS4836 mentions the following terms. In your own words describe your
understanding of these terms, in relation to the standard.
• On or Near (1 mark)
• Safety Observer (1 mark)
• Competent Person (1 mark)
d) List two (2) risk control methodologies identified in the Hierarchy of Controls listed in
AS4836 and give practical examples of how these would be applied in the
management of risks associated with live low voltage testing. (2 marks)
Initial investigations by the tradesman have identified major burning at the crush point on
the cable; the supply circuit breaker in the DCB has a welded set of contacts; and the
supply transformer has tripped on the back-up earth leakage protection.
a) On being made aware of the incident, what would be your initial concerns with respect
to the operation of the electrical protection? (3 marks)
c) With regard to the operation of the protection system, what would your investigation
cover? (2 marks)
d) Draw a simple single line diagram as an example of how these systems may operate
with respect to your operation. (3 marks)
CEE2 Legislation and standards applicable to underground coal mines August 2013
b) For the purposes of this standard, what is the difference between type testing and
routine testing by a manufacturer? (1 mark)
d) For Earth Fault Protection Devices installed on IT systems, what is the minimum
recommended trip ratio between the earth fault limitation device and earth fault trip
value? (1 mark)
e) For an Earth Fault Lockout device, what is the minimum permissible insulation
resistance between a phase conductor and earth? (1 mark)
f) For Frozen Contactor Protection, a trip time of up to 20 secs is permitted for detection
of voltage on the load side of a contactor after it is expected to be in the open
position. Under what circumstances would such a long trip time be required? (2
marks)
g) The standard recommends a maximum time delay for an earth fault should not
exceed 500mSec. Under what circumstances may this value have to be exceeded?
What would be your main consideration in exceeding this value? (2 marks)
Develop a checklist of your expectations for your site personnel to follow in the event of:
a) An earth fault on a 10km overhead power line energised at 11kV to a remote dam
site. (4 marks)
b) What differences would you have in your procedure in the event that the previous
situation in ‘a)’ was an instantaneous overcurrent fault?(2 marks)
c) Who would you allow to conduct any fault finding/switching on site and why?(2 marks)
d) Would you consider a competent 4th year electrical apprentice to undertake this work
if they are the only resource available at the time? (1 mark)
e) Explain how an insulation test would or would not be beneficial in fault finding the
aerial system? (1 mark)
CEE2 Legislation and standards applicable to underground coal mines August 2013
He has asked you as the Manager of Electrical Engineering on site to prepare a report of
all areas on the surface of your mine site where there is a risk of arc-flash or electric shock
incidents involving non-electrical and electrical personnel.
b) Further to above in ‘a)’, what specific controls could be put in place to eliminate or
minimize the hazards of arc flash and electric shock? (2 marks)
d) Further to (c) what are your recommendations to protect these personnel from the
hazards identified? (2 marks)
e) What are your recommendations to protect electrical persons from the hazards
identified? (2 marks)
The Safe Work Australia Code of Practice, Managing Electrical Risks in the Workplace,
provides guidance and information on how the provisions of the Regulation can be met.
a) The Code outlines the requirements for a safe system of work to deal with potentially
unsafe electrical equipment. What are the key elements of this system? (2 marks)
b) According to the Code, what are the competency requirements for personnel
undertaking testing under AS3760? (2 marks)
d) For the purposes of this Code, is automotive electrical work undertaken on earth-
moving plant considered “electrical work”? (2 marks)
e) The WH&S Regulation 2011 details the circumstances under which work on
“energized electrical equipment” is permitted. What are these? (2 marks)
CEE2 Legislation and standards applicable to underground coal mines August 2013
a) List three (3) items of plant or equipment that you would want specifically addressed
in your induction training? (2 marks)
b) What are your individual site requirements for the items listed above? (4 marks)
c) What would be your inspection regime for portable electrical tools and appliances in
the surface workshop at your operation? (1 mark)
d) Explain how your inspection and test frequency may differ from the requirements of
AS3760 – In service safety inspection and testing of electrical equipment (2 marks)
b) List at least four (4) concepts used in the design of Exe equipment (2 marks)
c) Give examples of typical Increased Safety equipment currently used in the industry
(1 mark)
d) When an inspection of an Exe lighting box enclosure on a Longwall face was carried
out, it was identified that the external cable glands entering the enclosure were
standard off the shelf PVC glands. Are these allowed for this type of enclosure?
Justify your answer. (3 marks)
b) How would you confirm the requirements detailed in the information and training you
provide, are understood? (3 marks)
c) What processes could you utilise to measure the effectiveness of your training
system? (2 marks)
d) What systems could you utilise to ensure support information was available to
personnel as required? (2 marks)
a) You have an ongoing issue with spurious CH4 trips on your Longwall face. The
supplier of the methanometer considers that voltage drop is the issue and has
recommended a replacement cable with larger conductor cross sectional area. In
terms of the integrity of the IS protection, what would be your main concern? (1 mark)
c) According to AS60079.11, what are the minimum clearance distances between the
bare conducting parts of separate IS circuits? (1 mark)
e) Draw a sample block diagram for the following simple IS system (6 marks):
Pressure Transducer located in a hazardous area connected to a PLC analogue input
in a safe area via a IS transmitter. Include all key parameters utilising typical expected
values. In your diagram, the relationship between all input and output parameters (eg
Um; Uo; Ii; Io; Co; Ci; Lo; Lr) should demonstrate that the circuit is compliant
END OF QUESTIONS
END OF PAPER
(CEE3)
INSTRUCTIONS TO CANDIDATES:
It is expected that candidates will present their answers in an engineering manner making
full use of diagrams, tables, and relevant circuits where applicable and showing full
working in calculations. Neatness in diagrams is essential and will be considered in the
allocation of marks. Questions are to be answered as a prospective Qualified electrical
engineer at a NSW mine.
a) With the use of the area below draw a typical cross sectional diagram of a “type
409 Trailing Cable” and identify the critical design features of the cables internal
cores, insulation and screening. (4 marks)
b) Describe the primary engineering reasons for this particular design and layout of
the cable construction. (2 marks)
c) List a minimum of five of the eight pre-repair tests which need to be carried out on
every mining cable when sent to a licenced repair workshop. (4 marks)
d) After construction of your Main Substation, the Supply Authority contacts you to
advise that due to alterations to their network configuration the incoming fault level
at your substation has risen by 30MVA. What are the potential issues associated
with this, and what would be your first action? (2 marks)
e) The primary fundamental principle that should be applied to the design, selection
and installation of electrical protection and earthing systems at your mine is that the
first fault to be detected and cleared is always what type of fault? (1 mark)
Page 2 of 8
CEE3 Legislation and standards applicable to surface coal mines August 2013
Your mine has a project to install a new 10000 tonne ROM bin. Approval Conditions
stipulate the ROM conveyor from the loading point to the top of the bin (800m long) and
the top of the bin itself must be fully enclosed to minimise dust. Due to operational
sequencing the bin will typically run at about 75% of capacity. The ROM coal is typically
dry; the in-situ gas content of the mined coal is very high (5m3/tonne) with a low
desorption rate, and has a high propensity for spontaneous combustion.
a) Given the information above, outline what should be done at the design stage to
establish requirements for the electrical installation at the top of the bin (3 marks)
For each of the following clauses describe how you would incorporate the requirements
of each into the Technical Specifications and Electrical Engineering Management Plan
for your Mine. (2 marks each)
d) Clause 1.5.4.1 - Protection shall be provided against dangers that may arise from
contact with parts of the electrical installation that are live in normal service.
e) Clause 1.5.5.1 - Protection shall be provided against dangers that may arise from
contact with exposed conductive parts that may become live under fault conditions.
f) Clause 1.8 – All electrical installations and any alterations additions and repairs to
electrical installations shall, prior to being placed into service or use, be inspected
as far as practicable and tested to verify that the installation meets the requirements
of this standard as applicable.
Page 3 of 8
CEE3 Legislation and standards applicable to surface coal mines August 2013
b) What is the power factor achieved with the power factor unit you selected, at the
nominated maximum demand? (2 marks)
c) What is the kVAr of each phase if the capacitor bank is delta connected? (2 marks)
d) Calculate the resultant power factor if the capacitor bank you selected remained
connected when the demand dropped to 10MVA at 0.65 lag power factor. (2 marks)
e) List the relative merits of high voltage verse low voltage connected power factor
correction units (2 marks)
b) According to the Standard, what is the maximum permissible operating time for an
Earth Continuity Protection Device? Why is this maximum time important? (2 marks)
d) For Earth Fault Protection Devices installed on IT systems, what is the minimum
recommended trip ratio between the earth fault limitation device and earth fault trip
value? (1 mark)
e) For an Earth Fault Lockout device, what is the minimum permissible insulation
resistance between a phase conductor and earth? (1 mark)
Page 4 of 8
CEE3 Legislation and standards applicable to surface coal mines August 2013
You have taken on the role of Mine Electrical Engineer at a green-field site.
During your first day on the job you take particular note of the following:
• The mine Administration Area is located separately and also comprises a large
number of demountable buildings with 2 large rural sheds being used as
“temporary” workshop facilities.
a) What key Standards and other documentation would you refer to or consider when
assessing the installation? (2 marks)
c) You observe that power cables are installed via a combination of being buried
directly; on cable trays; and suspended via catenary wires. Outline the earthing
requirements for the installation. (3 marks)
d) What would you require to see provided in the testing documentation? (2 marks)
Page 5 of 8
CEE3 Legislation and standards applicable to surface coal mines August 2013
b) What is your advice on the category to be used on this project and designate the
control measures for the category you have chosen? (2 marks)
c) Name the tests that need to be carried out on the electrically supplied welding
machine and the frequency required. (3 marks)
e) What are the added requirements if you are welding in a confined space? Some of
these are specified but are there any other safety improvements you would
recommend to the Project manager? (2 marks)
a) Provide three examples of types of electrical work where the Code of Practice
does not apply. (2 marks)
b) AS3760 sets out indicative inspection and testing frequencies for electrical
equipment. The Code of Practice for ’Managing Electrical Risks in the Workplace’
(Safe Work Australia) provides guidance on when testing should be undertaken in
addition to the testing frequencies recommended in the Standard. When should
such additional testing on electrical equipment be undertaken? (2 marks)
c) In relation to construction work, according to the WH&S Regulation 2011, when
should RCD’s be used? (2 marks)
d) You are performing in inspection at your mine, and find a fitter removing a coupling-
half from the shaft of a 110kW pump motor. You note the motor is still connected to
the cable (with the terminal box cover in place) however he has isolated the pump in
accordance with site isolation procedures.
Under the WH&S Regulation 2011 is this considered “electrical work”? Support your
answer. (2 marks)
e) The WH&S Regulation 2011 details the circumstances under which work on
“energized electrical equipment” is permitted. What are these? (2 marks)
Page 6 of 8
CEE3 Legislation and standards applicable to surface coal mines August 2013
a) List any specific standards / guidelines that you would reference in your
specification. (1 mark)
b) What would be some of your specific requirements in point form for your
specification? (4 marks)
c) What would you consider to be safety critical that you would not compromise on in
your specification? (1 mark)
d) Where would you install any emergency stops and what specific requirements
would you ask for from the supplier? (2 marks)
e) What documentation would you insist on being provided prior to accepting the
machine? (2 marks)
You are the Qualified Electrical Engineer (QEE) for a large Open Cut facility which has
been on “care and maintenance” mode for a period of time, and has just been given a
new life with operations about to start up again.
With the commencement of operations a series of new machinery will be coming to site:
a) What are some of the issues which may be encountered when bringing new
equipment to site? (2 marks)
c) Draw a basic flow diagram of the process, and how you can ensure that the
equipment is suitable for service at your site? (4 marks)
Page 7 of 8
CEE3 Legislation and standards applicable to surface coal mines August 2013
As Qualified Electrical Engineering at a coal operation you need to provide a system that
ensure all your electrical contractors are aware of your standards of Engineering Practice
Describe a system you would put in place to manage the risk of electricity that will:
a) Provide training to your contractors prior to commencing work on your site. This
would include non-electrical people (3 marks)
c) Describe how you will measure the effectiveness of your standard. (2 marks)
d) Describe how you will ensure that supporting information is available (2 marks)
b) What is meant by the term “Corona” with regards to electrical engineering? (1 mark)
j) What gases are produced during an arcing fault within an oil filled transformer? (1 mark)
END OF QUESTIONS
END OF PAPER
Page 8 of 8