12 Solar Water Heater Geyser
12 Solar Water Heater Geyser
Spring 2020-21
Team Members
Project Advisors:
Acknowledgments
First, we would like to thank our PMU faculty members specially our advisor Dr. Waqar
Khan for their continuous help and support we recieved during our work on this project.
Further more, we would like to express our gratatude for their efforts in teaching us the
knowledge and skills needed to accomplish this project.
List of Figures:
Figure 1 Components of the Solar Heater............................................................................................................... 6
Figure 2 Schematics of the Geyser Pump Flow ...................................................................................................... 7
Figure 3 3D Model of Solar Water Heater.............................................................................................................. 8
Figure 4 Solar Collector ......................................................................................................................................... 9
Figure 5 Solar Water Heating Geyser………………………………………………………………………........14
Figure 6 Flat Plate Collector………………………………………………………………………………….….15
Figure 7 Evacuated Tube Collector………………………………………………………………………………15
Figure 8: pump…………………………………………………………………………………………………...15
Figure 9: Water Tank…………………………………………………………………………………………….15
Figure 10: Evacuated Tubes……………………………………………………………………………………...15
Figure 11: Manifold………………………………………………………………………………………………16
Figure:12 Temperature Sensor…………………………………………………………………………………...16
Figure 13: Schematic diagram of the solar water heating geyser………………………………………………...16
Figure 14: Economic Evaluation…………………………………………………………………………………17
Figure 15: Sensor Location………………………………………………………………………………………18
Figure 16: Test Results…………………………………………………………………………………………..19
2
1 Table of Contents
Abstract............................................................................................................................................................... 2
Acknowledgments .................................................................................................................................................. 2
List of Figures: ....................................................................................................................................................... 2
Chapter 1: Introduction ........................................................................................................................................... 4
1.1 Project Definition .................................................................................................................................. 4
1.2 Project Objectives ................................................................................................................................. 4
1.3 Project Specifications ............................................................................................................................ 4
1.4 Applications .......................................................................................................................................... 4
Chapter 2: Literature Review.................................................................................................................................. 5
2.1 Project background................................................................................................................................ 5
2.2 Previous Work....................................................................................................................................... 7
2.3 Comparative Study ................................................................................................................................ 9
Chapter 3: System Design ...................................................................................................................................... 9
3.1 Design Constraints and Design Methodology: ...................................................................................... 9
3.2 Engineering Design standards……………………………………………………………………………11
3.3 Theory and Theoretical Calculations .................................................................................................. 12
3.4 Product Subsystems and selection of Components ............................................................................. 16
3.5 Manufacturing and assembly (Implementation)………………………………………………………..18
3.6 Economic Evaluation ……………………………..……………………………………………………17
Chapter 4: System Testing and Analysis .............................................................................................................. 19
4.1 Experimental Setup, Sensors and data acquisition system .................................................................. 19
4.2 Results, Analysis and Discussion ........................................................................................................ 19
Chapter 5: Project Management ........................................................................................................................... 20
5.1 Project Plan ......................................................................................................................................... 20
5.2 Contribution of members: (out of 100%)…………………………………………………………………21
5.3 Project Execution Monitoring ............................................................................................................. 23
5.4 Challenges and Decision Making ........................................................................................................ 23
5.5 Project Bill of Materials and Budget ................................................................................................... 23
Chapter 6: Project analisys ................................................................................................................................... 23
6.1 Life-long Learning .................................................................................................................................. 24
6.2 Impact of Engineering Solutions ........................................................................................................... 24
6.3 Contemporary Issues Addressed…. ....................................................................................................... 24
Chapter 7: Conclusions and Future Recommendations…………………………………………………………23
7.1 Conclusions ......................................................................................................................................... 24
7.2 Future Recommendations .................................................................................................................... 25
8. References .................................................................................................................................................... 25
Appendix A: Progress Report .............................................................................................................................. 25
Appendix B: Engineering Strandards ................................................................................................................... 30
Appendix C: CAD drawings and Bill of Materials ............................................................................................... 30
Appendix D: Datasheets ....................................................................................................................................... 32
Appendix E: Operation Manual ............................................................................................................................ 33
3
Chapter 1: Introduction
1.4 Applications
The applications of the solar water heater geyser are given below:
4
The solar water heater geyser is installed and utilized for domestic usages such as
apartments, houses, flats, and Bungalows.
The solar water heater geyser is installed and utilized for commercial usages such as
hospitals, hostel, restaurants, hotels, and hospitals
The solar water heater geyser is installed and utilized for industrial usage too such as
Process Industries and Preheating boiler feed water.
Hot water for bathing, washing garments, and utensils, etc. is used in the domestic field.
However, the criteria may differ according to the season of the year and the family
number.
On average, 30 to 35 liters of water is observed in our experience at 50 to 55C. It's a
human eaten. 125 LPD Solar Water Heating System is therefore very adequate for a
family of 4 members.
Solar Water Heating Systems is designed to satisfy the above requirements in
commercial & industrial sectors, where large quantities of water are needed at
reasonably high temperatures. The system can be either a modular or a high-capacity
single tank system based on the delivery pattern of hot water.
5
technique was used. As used in solar water heaters, these techniques demonstrated a major
increase in overall thermal efficiency. The solar water heater is presented in Figure 1.
Solar thermal water heating systems (STWH) are cost-efficient as well as energy effective. The
STWH systems are ideally suited for hot weather and direct sunshine but are still very well
suited in cooler weather in the United States. The challenges, such as freezing, are solved by
different principles of the STWH structures. Most systems of STWH have a solar collector on
the roof of the residence facing south. Flat plate solar panels contain four parts: translucent
covers for reduced convection and heat loss radiation; dark-color, flat plate panels for optimum
heat absorption; heat transfer fluid conducting pipes extracting heat from the sensor; and heat-
isolated backpacks to avoid conductive conduction.
Loss of sun. There is a network of black tubes that flow water or some other fluid within this
collector. The fluid in the tube is rarely cold in the panel and heated by the panel while the
black outside of the tubes receives heat from the light. The heat transfer fluid and the chosen
materials for the tubes are critical criteria for the device to resist drastic frosting and
overheating temperatures. When the substance is water, it joins a hot water holding tank
straight away. The heat is then moved from the working fluid to the water in the hot water tank
using another working fluid by heat exchange in the tank.
6
Figure 2 Schematics of the Geyser Pump Flow
7
selective coatings. However, because of issues such as cost and compatibilities in winter,
development was slow. Significant technical and product breakthroughs made in the 1990s in
vacuum pipe production allowed China to build a self-designed vacuum pipes production line
and to mass-produce a solar water heater with a vacuum piping system. Such accomplishments
in technology and research have led to the continuous development of solar collector and heater
efficiency with the vacuum tube and heat pipe all-glass and reduced expense. It brings
considerable impetus to the Chinese solar thermal industry's industrialization.
A CAD model of a Solar Water heater is illustrated in Figure 3. It shows the collector and
frame of the solar water heater. The tubes are designed inside the collector which contains the
hot water which goes to the tank and from there, the cold water comes to the tubes to get the
heater through the solar energy. Since the mid-1920s impressive advances have been recorded
in modeling and simulation technologies. The mechanical differential analyzer was also used
to solve only a small number of ordinary differential equations. In the 1950s, as electronics
replaced cumbersome equipment, significant technical change was recorded. The simulation
was eventually encouraged by broad-based growth and industrialization.
8
Figure 4 Solar Collector
In the 1960s, electronic development is the year in which digital computers had been replaced
by analog computers. The development was also witnessed by the modeling and simulation.
The simulation was user-friendly since computer graphics were commercially released on the
market in the 1990s.
First of all, draw a 3d model of Water Solar Heater Geyser, then make a practical model and
define its Design Constraints and Design Methodology. Its Design Constraints are following:
Geometric Constrains:
Geometric Constrains are dimensional conditions imposed on Design Methodology.
9
Length of the Tubes 1800mm.
Sustainability Constraints:
This project is basically the related to energy sustainability, so sustainability constraints are
taken into account.
We are using Solar Energy.
Use of renewable energy.
Economic Constraints:
Purpose of economic constrain is to make the product market compatible.
Economical material is being used for this model.
Material used in this project is easily available in market.
Environmental Constraints:
The purpose of Environment Constraints is to limits the production which may cause pollution
in environment.
This project is environment friendly, and it does not have any negative impact on the
environment.
No noise pollution, no air or land pollution.
This product will help to keep the environment clean because it makes use of the
renewable energy instead of the fuel for heating which causes some air pollution.
10
This project makes use of the renewable energy instead of fuel for the heat generators,
causing the environment safe and healthy.
Manufacturability Constraints:
Concern of the Manufacturability constraint is to assure the design methodology which is easy
to manufacture in bulk quantity.
Solar heater is manufacture in the possible easiest way for bulk production,
Material used in the product is easily available in the market.
Social Constraints:
Purpose of social constraint is to design the product which is according to the requirements of
human and it should address some social issues.
This project has addressed the issues of Sustainable energy and Air pollution.
Ethical Constraints:
Ethical constraint is applied to limit the product which may hurt the feelings of people. Its
purpose is to provide the user with expected results without the breach on any ethical
boundaries.
Risk Analysis:
When assessing the risk on a solar water geyser we look for aspects where the product can
harm properties and human life. The risk we avoid pressurizing the system to avoid burst
in the system. Furthermore, we choose metals that would avoid corrosion and metal
toxicity.
11
3.3 Theory and Theoretical Calculations
A flat plate collector consists of multiple vertical copper tubes which are arranged in parallel
configuration, these tubes are connected from the top and the bottom with copper tubes
usually larger in diameter. The larger diameter tubes are perpendicular to the smaller tubes,
this gives the plate a rectangular shape. The tubes are enclosed inside a well-insulated box
with a cover made out of tempered glass.
The Flat collector plate is usually connected to risers, the heat is gained by collecting the
solar energy from the sun which gets absorbed by the copper to heat the circulating water. (p.
1)
Evacuated tubes are made of vacuum tubes. They are tubes with an inner and an outer layer
of glass, the tube then is vacuumed. These tubes are fitted with a copper heat pipe filled with
a non-toxic liquid.
The Evacuated tube is a poor heat conductor, but the vacuum between the layers ensures that
the solar radiation is almost fully absorbed and intraped inside it. The energy gets absorbed
12
by the copper heat pipe inside the tube, which in return heats the circulating water manifold.
In Direct configuration, the water circulates form the tank to the solar collector directly. The
water gets passed through the collector where it gets heated.
In Indirect configuration the fluid which flows to the solar collector is not the actual geyser
water itself rather it is a glycol mixture, which is contained in a closed loop, running from the
geyser to the collector and back again.
Passive and Active explains how the system water circulates from tank to the heat collector.
Active configuration is also known as Pumped Configuration. In this configuration the geyser
is located below the solar collector. This system make use of the circulation pump, to pump
to move the water in the system from the tank to the collector and vice versa. (p. 2)
Calculations:
13
For evaluation of performance of solar water heater, we need to calculate its efficiency.
Collector efficiency is the ratio between the rates of useful heat (QU) transferred by solar
radiation on the cover plate. Efficiency can be shown in the equation as follows:
Q out is the heat energy absorbed by the water from to the collector.
Q out = m * cp * ΔT (2)
m = mass flow rate (kg/s)
m=ρ*A*V
Conductive heat loss through the wall of a cylinder or pipe can be expressed as
π = pi = 3.14...
14
k = thermal conductivity of stainless steel (w/m.k)
π = pi = 3.14...
m=ρ*A*V
m = 998(π/4)(0.17)^2(0.146)
m = 3.3 kg/s
Q out = m * cp * ΔT
Q out = (3.3)(1.5616)(71-61)
Q out = 51.33 w
Qin = 2 π (15) (0.6) (353 – 344) / ln(0.08 / 0.085)- 2 π (15) (0.6)(344-334) / [ln(0.085 / 0.08)]
Qin = 63.95 w
Ƞ = (51.53/63.95)*100 = 80.5 %
15
3.4 Product Subsystems and selection of Components
Circulation Pump
Figure 8: pump
Control System
16
Manifold
Sensor
17
Long term durability and reliability
Ease of repair of collectors
Low risk of corrosion
Good performance even in the windy conditions.
Least expensive installation.
Here is the schematic diagram of the solar water heating geyser and this is how we assemble
it.
18
Chapter 4: System Testing and Analysis
The results of the test were depending on the temperatures we were seeing on the temperature
gauge. The goal is to reach the temperature of 50 C˚ up to 70 C˚ on the temperature gauge.
19
As the data showing in figure 16 the results show that in the first three hours during the
testing we reached our goal. The temperature kept on raising each hour until the system
reached its highest temperature of 62 C˚ at 1pm. As shown on the left the change of
temperature in each hour was in the expected region, except for the hours of 10 Am and 4 Pm
were the temperature of the tank never changed or showed a decrease which may be a result
of inaccurate reading due to the gauge being analog or because the weather temperature did
not change.
3D modeling
Purchasing of material
Testing
Task Division
Identification of Material
Majed
Material Purchase
Yahya
Practical Model
20
Testing Yahya
All
Mosab
Concluding Project
Yahya
Mosab
Report Writing
Majed
Hassan
Table 5.1: Time duration table of tasks
Task 3 Material
Identification
Task 5 Practical
Model
Task 6 Testing
21
5.2: Contribution of members: (out of 100%)
22
Practical Model 50%
Hassan
Testing 50%
Testing
23
Chapter 6: Project Analysis
6.1 Life-long Learning
Knowledge in how the fabricating industry work in Saudi Arabia.
We gained more knowledge in the solar energy& renewable energy field.
Our time management skills improved.
Project management skills improved.
Research on different types of materials that are suitable for human use.
Handel work under pressure.
Couple of engineering books from: Thermodynamics, Heat Transfer, Manufacturing
Methods in Design.
Couple of e-Journals using Google Scholar.
In conclusion, the solar geyser showed how efficient it is to be used in Saudi Arabia. The
system reached its goal of 50 C˚ three hours into sunrise and kept rising until it reached its
maximum temperature of 62 C˚ at 1 PM and it stayed relatively constant for the rest of the
night. One of the challenges the team encountered is to finish the project in 8 days and that
required us to almost perfect our time management in order to fit into Ramadan odd working
hours, and that shortage of time happened to be due to shipment delay from the supplier side.
We gained knowledge and huge team work skills. We learned various renewable energy
systems and especially solar energy technologies available around the globe. The knowledge
we acquired is one of the stepping stone to the future of renewable energy. The work has
been divided among team members in such a way where each team member got a task that
suits his strength points.
24
7.2 Future Recommendations
Change the system from an active solar water heater to passive one.
Change the position of the water tank and making it the highest point (above the
manifold).
8. References
Brothers, H. (2019, September). Solar Water Heater. Renewable Energy. Retrieved March,
2021 from https://www.haroonbrothers.com/renewable-energy/solar/solar-water-
heater/
Solar, P. (2020). Solar Geyser | Solar Water Heater. Renewable Energy. Retrieved March,
2021 from http://www.paksolarservices.com/solar-geyser.html
Han, W. S., Lu, M., McPherson, B. J., Keating, E. H., Moore, J., Park, E., ... & Jung, N. H.
(2013). Characteristics of CO 2‐driven cold‐water geyser, C rystal G eyser in U tah:
experimental observation and mechanism analyses. Geofluids, 13(3), 283-297.
Jurgens, P. J. (2011). Feasibility analysis & operational design for local manufacturing of
solar water heating equipment.
Sankar, K., Selvam, K., Ashwin, K. J., & Prasanth, S. S. (2021). Analysis of Corrosion
Resistance in Domestic Water Geysers by Coating Nano-Film Using Thermal Spray
Coating. Trends in Manufacturing and Engineering Management, 123-134.
25
Appendix A: Progress Reports
Includes copies of what you have already submitted.
SDP – MONTHLY MEETING REPORT
Department of Mechanical Engineering
Prince Mohammad bin Fahd University
ACADEMIC
SEMESTER: Spring 2021
YEAR:
PROJECT
Design of Solar Geyser
TITLE
SUPERVISORS Dr. Waqar Khan
Month 2: March
List the task s conducted this month and the team member assigned to
conduct these task s
List the task s planned for the month of April and the team member/ s assigned
to conduct these tasks
Team member/s
# Task description assigned
1 Mosab / Yahya
Fabrication
2 Assembly Nawaf / Majed
3 Calculations Hassan / Yahya
4 Majed / Nawaf / Hassan
Prototype Testing and Analysis
5 All
Report Completion
6 All
Final Presentation
26
# Name Criteria Criteria Criteria Criteria
(MEEN4A) (MEEN5A) (MEEN5B) (MEEN5C)
1 Mosab Al Shammari 4 3 4 4
2 Majed Al Daghreer 4 4 4 4
3 Hassan Qudrah 4 3 4 4
4 Nawaf Al Nuaim 3 4 3 3
Majed Al Daghreer Overall vital team member and well organized in team meetings.
Nawaf Al Nuaim Great team member but need to work more on communicating with group
members.
ACADEMIC
SEMESTER: Spring 2021
YEAR:
PROJECT
Design of Solar Geyser
TITLE
SUPERVISORS Dr. Waqar Khan
Month 3: April
List the task s conducted this month and the team member assigned to
conduct these task s
27
4 All 100%
Design Methodology
List the task s planned for the month of April and the team member/ s assigned
to conduct these tasks
Team member/s
# Task description assigned
1 Mosab / Yahya
Fabrication
2 Assembly Nawaf / Majed
3 Calculations Hassan / Yahya
4 Majed / Nawaf / Hassan
Prototype Testing and Analysis
5 All
Report Completion
6 All
Final Presentation
2 Majed Al Daghreer 4 4 4 4
3 Hassan Qudrah 4 3 3 3
4 Nawaf Al Nuaim 3 4 3 4
Majed Al Daghreer Overall vital team member and well organized in team meetings.
Hassan Qudrah Need to put more effort into time management, also need to work more on
communicating with group members
Nawaf Al Nuaim Great team member but need to work more on communicating with group
members.
ACADEMIC
SEMESTER: Spring 2021
YEAR:
28
PROJECT
Design of Solar Geyser
TITLE
SUPERVISORS Dr. Waqar Khan
Month 4: May
List the task s conducted this month and the team member assigned to
conduct these task s
List the task s planned for the month of April and the team member/ s assigned
to conduct these tasks
Team member/s
# Task description assigned
1 Mosab / Yahya
Fabrication
2 Assembly Nawaf / Majed
3 Calculations Hassan / Yahya
4 Majed / Nawaf / Hassan
Prototype Testing and Analysis
5 All
Report Completion
6 All
Final Presentation
2 Majed Al Daghreer 4 4 4 4
3 Hassan Qudrah 4 3 4 4
4 Nawaf Al Nuaim 3 4 3 4
29
Comments on individual members
Name Comments
Majed Al Daghreer Overall vital team member and well organized in team meetings.
Hassan Qudrah Need to work on time management, also need communicate with group members
Nawaf Al Nuaim Showed more effort in working with the group and communicating.
International
• SAES-W-012 (welding)
• NFPA 70: National Electrical Code®
• ASTM A1049
• ISO 9001-2015(Tank)
Local
SASO 2884 .2017
30
402.5 x (5 tubes) = 2025
31
Manifold and Stand = 3500 SAR
Appendix D: Datasheets
32
Appendix E: Operation Manual
33