Software Project Management Unit-4 - 3 PDF
Software Project Management Unit-4 - 3 PDF
UNIT-4 (Lecture-3)
VISUALIZING PROGRESS
Once data has been collected about project progress, a manager needs some way of presenting
that data to greatest effect. Some of these methods such as Gantt charts provide a static picture, a
single snapshot, whereas others such as time line charts try to show how the project has
progressed and changed over time.
The simplest kind of Gantt chart can be created using a software tool such as Microsoft Excel.
For that matter, any spreadsheet tool can be used to design a Gantt chart template.
Advantage
The ability to grasp the overall status of a project and its tasks at once is the key advantage in
using a Gantt chart tool. Therefore, upper management or the sponsors of the project can make
informed decisions just by looking at the Gantt chart tool.
The software-based Gantt charts are able to show the task dependencies in a project schedule.
This helps to identify and maintain the critical path of a project schedule.
Disadvantage
For large projects, the Gantt chart tool should be supported by other means of documentation.
For large projects, the information displayed in Gantt charts may not be sufficient for decision
making.
Ball Charts
A more prominent way of showing whether or not targets have been met is to use a ball chart.
The same is illustrated in Figure. In this version of the ball chart, the circles indicate start and
completion points for activities. The circles initially contain the original scheduled dates.
Whenever revisions are produced, these are added as second dates in the appropriate circle until
an activity is actually started or completed.
Circles will contain only two dates, the original and most recent target dates, or the original and
actual dates. Where the actual start or finish date for an activity is later than the target date, the
circle is colored red (dark grey in Figure) - where an actual date is on time or earlier than the
target then the circle is colored green (light grey in Figure).
The advantage of ball charts over Gantt and slip charts is that they are relatively easy to keep up
to date. Only the dates and possibly colors need to be changed, whereas the others need to be
redrawn each time target dates are revised.
Timeline Chart
One major disadvantage of Gantt chart, Slip chart and Ball chart is that they do not show clearly
the slippage of the project completion date through the life of the project.
Knowing the current state of a project helps in revising plans to bring it back on target, but
analyzing and understanding trends helps to avoid slippage in future projects. The timeline chart
is a method of recording and displaying the way in which targets have changed throughout the
duration of the project.