Our ref : PE/2206/MW/SCB/23
Date : 5 May 2023
A) Technical Proposal
1. General information
1.1 In order to generate steam for the laundry process, an existing wood boiler is being
utilized, however, during its operation, the flue gas emitted from the wood boiler is
observed to have a dark soot appearance which indicates the presence of pollutants.
Therefore, there is a requirement for a pollution control technology to be
implemented to treat the flue gas and reduce its harmful emissions.
1.2 For budget purposes, we are proposing ONE UNIT of WET SCRUBBER for
client’s consideration.
Wet Scrubber
Model PE Scrubber NTU 2
Material Steel HTU 0.5m
Waste Gas Flue Gas From Boiler Packing Type Structured-Pack
Liquid No Packing Material PVC
Recirculate
Waste Gas ~17,500 m³/hour Pack Size - Surface 35mm - 109m²/m³
feeding Area
Operating 160oC Water Consumption 2.67 m³/hour
Temperature
Retention 3 Other Components PE-Screen &
Time Storage Tank
Operating 14 Other Accessory Valve, Level sensor
hours & controller
1.3 The screening process is employed to extract any linen present in the effluent.
Furthermore, a water-cooled condenser is employed to maintain the temperature of
the effluent within the optimal range for it to function as a suitable scrubbing
solution.
1.4 The flue gas is from the boiler will directed into the wet scrubber containing a
double packing media system. The purpose of the packing media is to augment the
contact surface area between the exhaust gas and the scrubbing solution, thereby
improving the absorption of pollutants. Following the scrubbing process, the
demister unit is responsible for removing any residual liquid droplets present in the
exhaust gas.
1.5 Upon completion of the scrubbing process, the purified flue gas is released, while
the scrubbing solution, which contains the captured pollutants, is directed to a
mixing tank. The mixing tank is responsible for adjusting the pH value of the
solution to meet the required standards prior to discharge.
Private & Confidential Page 2|6
Our ref : PE/2206/MW/SCB/23
Date : 5 May 2023
1.6 Process flow chart
Boiler Flue Gas
- 160 ℃
- 17500m³/hour
- 342 mg/m³ Total PM
Emission Flue Gas
Boiler
- 80℃
Condenser - 14 m/s
- 34.2 mg/m³ Total PM
ID Fan
Wet
Screening & Storage Scrubber
Effluent Source End Suction Chemical Mixing Tank Effluent Discharge
- 65 ℃ Pump Tank - 50 ℃
- 2.67 m³/hour
- 2.67 m³/hour
- pH 7 ~ 8
- pH 7 ~ 8
1.8 Wet Scrubber Layout
5
1
Legend
1) Boiler
2) Wet Scrubber 6
3) ID Fan
4) Chimney
7m
5) Screening and Storage Tank
6) Condenser
7) Chemical Tank
7 3
8) Mixing Tank
8 2
4
7m
Private & Confidential Page 3|6
Our ref : PE/2206/MW/SCB/23
Date : 5 May 2023
2. Scope Of Supply/Work
2.1 The scope of supply/works included in our proposal for the treatment systems are: -
a) To design and fabricate
b) Supply and install
c) Testing and commissioning
d) Training to operator
2.2 The scope of supply/works excluded in our proposal are: -
a) All civil and structural including external, drainage works, wall hacking and
make good of building and any M&E
b) All plumbing and piping works for incoming water to system
c) All electrical and wiring works from source to control panel
d) Raw materials or wastes for testing & commissioning
e) Any drums and containers required for the project
f) Any other authorities approval except DOE
3. Installation Procedures
3.1 The installation of the system can only commenced after the structures and
foundations are ready.
3.2 Installation of the heavy components along with other parts will be done
immediately and hand tools are required.
3.5 Testing and commissioning will commence when electricity are available.
4. Project Schedules
Please be informed that we can only provide the estimated time as below and we will not
be responsible for any delays:
4.1 The proposed system is scheduled to complete within 3 months upon receiving
Letter of Award and advanced payment.
4.2 The typical installation time of major heavy components and M&E components
along with electrical wiring for the system can be completed within 20 days.
4.3 The testing commissioning and training of the system will be within 1-2 days.
Private & Confidential Page 4|6
Our ref : PE/2206/MW/SCB/23
Date : 5 May 2023
5. Warranty
5.1 The warranty period for manufacturing defect is valid for 12 months from the date
of delivery.
5.2 The warranty is not liable for any theft and/or damages caused by negligence,
abuse*/misconduct, modification, act of war and/or force majeure.
5.3 Any impromptu calls for checking, service and maintenance during and after the
warranty will be charged as accordingly. All traveling and accommodation
expenses will be borne by the client.
6. After Sales Service
6.1 After sales service is available upon request.
6.2 Any traveling for service and maintenance will be charged as accordingly.
Private & Confidential Page 5|6