Well Foundation Methodology - R0

This document summarizes the methods for constructing well foundations for a project to build a four-lane expressway from Delhi to Amritsar and Katra in Punjab, India. It includes the scope, specifications, construction methodology, quality control plans, and health and safety plans for building well foundations along the 16.9 km long expressway, including a 1.3 km long cable stay bridge. The project involves constructing 17 box culverts, 11 bridges, and other structures along the route.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
130 views

Well Foundation Methodology - R0

This document summarizes the methods for constructing well foundations for a project to build a four-lane expressway from Delhi to Amritsar and Katra in Punjab, India. It includes the scope, specifications, construction methodology, quality control plans, and health and safety plans for building well foundations along the 16.9 km long expressway, including a 1.3 km long cable stay bridge. The project involves constructing 17 box culverts, 11 bridges, and other structures along the route.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection of Amritsar

with Delhi-Amritsar-Katra expressway from Junction with Kapurthala- Sultanpur Lodhi Road
(NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction at Ch. 40+900 Dhunda Village on
EPC mode under Bharatmala Pariyojana in the state of Punjab (Pkg-Spur-I)

GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION


OF WELL FOUNDATION
Contractor

SP SINGLA CONSTRUCTIONS PVT. LTD.


1006-1007, 10TH Floor, Pearls Best Height-1
Netaji Subhash Place
Pitampura, New Delhi-110034

Authority’s Engineer

M/S Rodic consultant Private Limited


In JV with
G-Eng. Advisory Services Private Limited
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

Document control sheet

PROJECT- Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection of


Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala- Sultanpur Lodhi
Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction at Ch. 40+900 Dhunda Village
on EPC mode under Bharatmala Pariyojana in the state of Punjab (Pkg-Spur-I)

DOCUMENT- GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL FOUNDATION

DOCUMENT NO- SPS-P344-MS-001-R0

Rev Date Description Prepared Reviewed By Approved By


No. By
Lalit Kishore Pankaj Kumar Sunil Yadav
Tomar Roy
Planning Project Team Leader Project Director
R0 26-02-2023 Initial
Manager Manager
Issue
SPSCPL RODIC NHAI

(This document is a property of SP SINGLA CONSTRUCTIONS PRIVATE


LIMITED. This is not transferable and shall not be used for any purpose
other than for which it is intended.)

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 2 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

INDEX

1. INTRODUCTION…………………………………………………………………….…………04

2. SCOPE & OBJECTIVE……………………………………………………………………….06

3. TECHNICAL SPECIFICATIONA………………………….…………………………....07

4. OPERATIONAL STRATEGY.…………………………………………………….……….08

5. CONSTRUCTION METHODOLOGY…………………………………………….…….12

6. QC & QA……………………………………………………………………………………………16

7. HSE PLAN………………………………………………………………....................18

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 3 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

INTRODUCTION

This document called General Method and Arrangement for Construction of Well Foundation
(hereinafter also referred as Well Foundation Methodology) briefly describe the criteria,
responsibilities and operational methods will be adapted by SP SINGLA CONSTRUCTIONS PRIVATE
LIMITED in order to meet contract requirement of the Project relating to Construction of four-lane
Greenfield Delhi-Amritsar-Connectivity for Connection of Amritsar with Delhi-Amritsar-Katra
expressway from Junction with Kapurthala- Sultanpur Lodhi Road (NH-703A) near Isharwal Village
Ch. 24+000 to MDR Junction at Ch. 16+9000 Dhunda Village on EPC mode under Bharatmala
Pariyojana in the state of Punjab (Pkg-Spur-I).

Fig.-1 Site on Map

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 4 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

A brief summary of Kapurthala Cable stay bridge project is broadly covered:

 Total Length of Project :16.900 KM


 Total length of Cable stay Bridge : 1.300 KM
 Length of Main Span (India’s Longest) : 0.700 KM
 Length of Side Span (both side) : 0.600 KM
 South Approach Span : 0.810 KM
 Total Length of Road Section (4 Lane) : 13.280 KM
 Pylons : 2 Nos
 Height of Each Pylon : 170 m
 Box Culvert (2*2) : 17 Nos
 Box Culvert (4*3) : 11 Nos
 Box Culvert (6*4) : 3 Nos
 SVUP : 4 Nos
 LVUP : 6 Nos
 VUP : 4 Nos
 Minor Bridge : 3 Nos

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 5 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

SCOPE & OBJECTIVES

This Construction procedure is applicable for the construction of well foundation as per the
approved GFC drawings for the project - Construction of four-lane Greenfield Delhi-Amritsar-
Connectivity for Connection of Amritsar with Delhi-Amritsar-Katra expressway from Junction with
Kapurthala- Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction at Ch.
40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the state of Punjab (Pkg-Spur-
I).

This work procedure includes following:

 Survey – Setting out


 Cutting Edge Fabrication
 Placement and Assembling of Cutting Edge
 Well Curb Construction
 Grounding of Well Curb
 Construction of Well Foundation – Steining
 Well Sinking
 Seating of Foundation Well
 Construction of Well Foundation Bottom Plug
 Sand filling (If required)
 Construction of well cap

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 6 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

TECHNICAL SPECIFICATIONS

Codes & Specifications

1) MORTH Specifications.
2) IS 456-2000- Indian Standard specification for Plain & reinforced Concrete.
3) IS 383:1970- Indian Standard specification for coarse and fine aggregate.
4) IS 2502 – Code of Practice for Bending and fixing of Bars for concrete Reinforcement.
5) IS 1786: 2008 Indian Standard specification for High strength deformed steel bars and
wires for concrete Reinforcement.
6) IS 1904-1986 Indian Standard specification for Design and construction of foundation in
soil.

GFC Drawings

1) SPS/P344/MJB/SD-02

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 7 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

OPERATIONAL STRATEGY
Organization Chart

The roles & responsibilities for Construction of well foundation elaborated in the organization
chart below:
1) Project Manager
2) Planning Manager
3) Manager Construction
4) Formwork foreman
5) P&M In charge
6) P&M Engineer
7) Manager Quality
8) Quality Engineer
9) HSE Officer
10) Surveyor

Roles & Responsibilities:-

1) Project Manager:
Organize & manage all resources field activities to achieve an effective completion of
the contract, within the agreed time & cost, whilst paying due regard to safety &
meeting quality requirements.

2) Planning Manager:
a. Receive the drawings from client and issuing to site team.
b. Plan the resources, with inputs from site team.
c. Contract review and preparation of MSP schedules.
d. Coordinate with vendors for arranging resources.
e. Monitor the progress, financial performance and resource usage.
f. Update the resources schedule and look ahead progress.
g. Responsible for collecting and maintaining the documents like RFI/All checklists
formats etc. after client signature.

3) Manager Construction:
a. Responsible for all construction works such as reinforcement, shuttering, etc as per
GFC drawings issued to him from planning.
b. Preparation and indent of materials and consumables to execute the job.
c. Maintenance of site working formats and checklists.
d. Responsible for proper usage of concrete and other major consumables materials
such as TMT bars, without any wastage.
e. Responsible for implementation of safe work environment at work place.

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 8 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

f. Responsible for execution and maintain the good quality of work.

4) Formwork Foremen:
a. Responsible for formwork assembly and erection as per scheme drawing with
consulting site engineer.
b. Responsible for checking line, level and dimension trueness of formwork.
c. Responsible for reinspection of Formwork alignment after completion of concrete
pour.
d. Responsible to take care of Deshuttering of formwork without injuring the concrete.

5) P & M In charge:
a. Responsible for equipment fitness inspection, monitoring and maintain records.
b. Responsible for all mechanical and electrical equipment ensuring continues availability
and proper functioning of P&M at site.
c. Ensure periodic preventive maintenance & timely breakdown repairs of all machinery
& electrical equipment as per their inspection manual.
d. Ensure operation of P&M as per company norms.

6) P & M ENGINEER:-
a. Responsible for operational inspection and maintenance of P & M equipment’s on
regular basis.
b. Reporting of required data related to operation and maintenance of records.
c. Responsible for arranging power supply at workplace on day-to-day basis by co-
ordination with site engineer.
d. Ensure continues availability and proper functioning of P&M at site.
e. Ensure periodic preventive maintenance and timely breakdown repairs of all machinery
& electrical equipment as per their inspection manual.

7) Manager Quality:-
a. Check the quality of cement, fine aggregates and coarse aggregates etc.
b. Responsible for the compressive strength of the concrete batched for site at RMC.
c. Identify material sources, and conduct material tests and ensure conformity with
specification & standards.
d. Conduct routine tests on materials as per ITP for conformance and maintenance
records.
e. Identify, calibrate and maintain master list of testing and measuring equipment.
f. Responsible for submission of all reports related to quality matters.

8) Quality Engineers:-
a. Responsible for casting of concrete cubes for every batch produced from the plant.
b. Responsible for check and maintenance of required workability of concrete at pour
location.

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 9 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

9) HSE Officer:-
a. Responsible for implementation of company norms at site.
b. Responsible for all safety related works and proper functioning of safety at site.
c. Identify potentially unsafe acts, areas, implement practice measures, and educate
staff & workers.
d. Investigate unsafe occurrence and initiate corrective steps.
e. Organize training programs for safety awareness.
f. Helps to provide necessary safety materials as per work requirement.

10) Surveyor:-
a. Setting out of control points and those approved from Consultant.
b. Alignment and leveling of formwork as per approved drawing.

Resources

1. MANPOWER

Si No Manpower No’ per day No’s per night Remarks


shift shift
1 Pump/Boom Placer operators 1 1
2 Crane Operator 1 1
3 Unskilled 4 4
4 Shuttering Foremen 1 1
5 Reinforced Fitter 8 8
6 Rigger/khallasi 1 1
7 Helpers for concrete, 8 8
Reinforcement, formwork and
mechanical work.
8 Housekeeping supervisor’s 01 01
Total Manpower 25 25

2. MATERIAL
a. Ready mix Concrete (RMC) M35.
b. Reinforcement FE 500D.
c. GI Binding wire 18 gauge.
d. Formwork.

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 10 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

3. MACHINERY

Si No Machinery No’s per day Remarks


1 Batching Plant As per site For Concrete production (calibrated
requirement once in a month)
2 Chilling plant As per site
requirement
3 Crane 1 No
4 Grab 1 No
5 Concrete Pump / 1 No For Concrete Pouring
Boom Placer
6 Transit mixer 2 No For Transporting the concrete from
batching plant
7 Needle vibrators 3 No For proper Compaction of fresh
concrete
8 DG 62 KVA 1 No For Shuttering work & Lighting work
9 Water pump (5hp) 1 No For curing of concrete
10 Bar bending Machine 2 No Bending the reinforcement as per
schedule
11 Bar Cutting Machine 2 No Cutting the reinforcement as per
schedule
12 Welding Machine 2 No For shuttering
13 Hydra 14 MT 1 No For shifting of reinforcement
14 Total station 1 No For survey work
15 Excavator 1 No For removing mud and other works

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 11 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

CONSTRUCTION METHODOLOGY
A. Construction of Well Foundation: Survey – Setting out

Setting Out is the establishment of the points and lines to define the actual location and
level of the structural elements for the construction work so that construction of well
foundation works may proceed with reference to them. The purpose of Surveying is to ascertain
the positions of existing features by measurement for well foundation procedure.
 With the help of the total station accurate layout of the bridge centerline and pier
location to be marked.
 Reference survey points shall be established away from the zone of blowups or possible
settlements area resulting from well sinking.
 Such reference points shall be connected to permanent stations with the baselines at
the bank.
 Accurate tapes and precision Distomat shall check the distance.

B. Construction of Well Foundation: Cutting Edge Fabrication

 Cutting edge shall be fabricated in the yard as per approved design and drawing.
 Cutting edge shall be fabricated in some segments depending upon circumference and
ease of handling and transporting.
 It has to be cold-bent after joining the two angles back to back, heating not permitted.
 It should be properly anchored with the well curb concrete.
 In case blasting is anticipated, part of the inner face of well curb is armored with steel
plate.

C. Construction of Well Foundation: Placement and Assembling of Cutting Edge:

 Well foundation procedure involves Checking of the center point of the foundation well
as per design coordinates before placing with the help of total station.
 Provide four permanent reference pillars along and across the bridge centerline.
 The area will be levelled and compacted before placing of cutting edge.
 The cutting edge will be placed over the wooden sleeper, maintaining the spacing of
2.00m c/c.
 The segments will be joined by splicing plate as per the approved drawing.
 In case of massive cutting edges, it is preferable to place it on rollers.
 Final checking for construction of well foundation includes alignment, level, splicing
joints, etc.

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 12 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

D. Construction of Well Foundation: Well Curb Construction:

It is the wedge-shaped reinforced concrete ring beam shaped structural element located at the
lower part of Steining. Well curb is provided to facilitate sinking of well effectively.

1. Inner Formwork:
 First, internal formwork shall be erected and joined to form the proper shape as per
drawing.
 Providing and fixing of horizontal and diagonal supports.
 Shuttering should be cleaned, and standard form releasing agent (shuttering oil)
applied.
 Seal the shutter joints using foam sheets to make leak-proof.

2. Reinforcement Fixing:
 Rebars are cut and bend at the reinforcement yard.
 Check rebars for corrosion, pitting etc.
 Provide an adequate number of circular cover blocks (75mm).
 Vertical reinforcement bars are to be properly anchored with cutting edge with the help
of welding or nut-bolts as per approved design and drawing.

3. Outer Formwork:
 The entire floor area should be properly cleaned before fixing outer formwork.
 Formwork shall be fixed as per approved drawing.
 Shuttering shall be cleaned, and standard form releasing agent applied.
 Seal the shutter joints using foam sheets to make leak-proof.
 Fix coil anchors at appropriate locations for the erection of shutter for next lift.
 Outer formwork is supported by encompassing the circumference by wire rope tightened
with the turnbuckle.
 Lateral bracing should connect the inner and outer shutter.

4. Well Curb Concreting:


Concrete shall be placed in a single and continuous pour by crane bucket or pump as per
availability, ensuring proper compaction.

5. Deshuttering and Gauge Marking:


 Inner formwork can be remove after 72 hrs.
 Outer formwork may be remove after setting of concrete.
 Gauge marking shall be done along both axis at the four outer face location of the
foundation well with paint by using a template.

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 13 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

E. Construction of Well Foundation: Grounding of Well Curb:

 Grounding of well curb is the process for transferring the load from wooden sleeper to
the ground truly concentrically and vertically without tilt or shift. Successfully grounding
is crucial for further activities of construction of well foundation.
 Grounding may start after removal of inner formwork.
 Gunny bags filled with sand shall be placed in between wooden sleepers along the
periphery at the bottom of cutting edge.
 Diagonally opposite sleepers shall be removed by scooping earth from beneath.
 The load of curb transferred from wooden sleepers to sand-filled gunny bags and finally
to the ground by cutting the diagonally opposite gunny bags by knife
 The initial sinking of curb is significant and shall be done manually as far as possible,
keeping curb top approximately one meter above the ground level.

F. Construction of Well Foundation: Steining

 After grounding of well curb and its initial sinking, the well is built up by constructing
Steining in stages/lifts and subsequent sinking of the same.
 The height of Steining is 2.0m for 1st lift and thereafter 2.0 to 2.5m, and number of lifts
should be minimum to avoid construction joint.
 The chances of tilting increase if the well is made top-heavy by raising the Steining too
high in the first stance.
 The Steining shall be built in one straight line from bottom to top such that if the well
is titled, the next lift of Steining will be aligned in the direction of the tilt.
 Straightness check shall be with the aid of an approved length of straight edges.
 Plumb bob or spirit level shall never be used for alignment.
 Before the erection of shutter for next lift damaged portions if any, of Steining top of
the previous lift shall be properly repaired.
 Shear keys, as shown, shall be provided in the construction joint of well Steining.

G. Construction of Well Foundation: Well Sinking

 The sinking of well is done by two methods open sinking of wells (Most commonly used
method in India) and Pneumatic sinking (Used rarely when open sinking does not help
due to hard strata)
 The sinking operation involves lowering of well by dredging in the dredge hole.
 Plate grab is used in soft strata like sandy silt, soft clay, sandy clay, dense sand etc.
 In hard/stiff clay strata heavy-duty chisel used, followed by dredging by tyne grab.
 Levels and alignment (tilt and shift) of well shall be checked regularly at every 0.5m of
sinking.
 Sinking operation shall preferably be non-stop under skilled supervision.
 Dredged materials shall not be heaved on one side of well to avoid tilt and shift.

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 14 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

The above cycle of well Steining and sinking shall be repeated up to the last lift of the well
until well reaches to the founding level.

H. Construction of Well Foundation: Seating of Foundation Well:

 The well shall be uniformly seated on the founding strata.


 It shall be ensured that the soil strata encountered at the founding level and up to a
depth of one and a half times the foundation well diameter is uniform and identical to
that adopted in the design.
 In case the well is in hard steeply slopes rocky strata, pneumatic methods of sinking may
be adopted to seat the well evenly.
 Suitable sump (preferably D/6) shall be provided.
 In sandy strata, light blasting may be done for consolidating the soil, and loose materials
shall be dredged out thereafter.
 The final level of Cutting edge and sump shall be jointly recorded.

I. Construction of Well Foundation: Bottom Plug

 Bottom plug concreting will be done by “Tremie Method” or Skip box method.
 The top-level of bottom plug shall be kept minimum 300 mm above the top of the well
curb.
 Concrete shall be poured without interruption up to the required level as per drawing.
 The concrete mix used in the bottom plug shall have a minimum cement content of 330
kg per cum with a slump of about 150 mm or specified in the design.
 The soundness of the bottom plug should be checked by dewatering the well after seven
days to a level 5.0m below the surrounding water level and checking the rise of water,
which should not be greater than 10 cm per hr.

J. Construction of Well Foundation Sand filling:

 Sand filling may be started after completion of the soundness check.


Backfilling material should be clean and free from earth, clay clods, roots, boulders, shingles,
etc.

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 15 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

QUALITY CONTROL & ASSURANCE

Inspection Plan

Inspection Plan for reinforcement, Formwork, Surveying and concreting works of Well
Foundation:

Check Check By
Si Description of Sub Activity by Authority Documentation Remarks
No SPSCPL Engineer
1 Fixing of temporary bench W R RFI
marks
2 Alignment and leveling W W RFI
3 Receipt of reinforcement steel W R Invoices and MTC
4 Sampling and testing of W R Third party report
reinforcement steel
5 Bar bending schedule as per W W BBS
GFC
6 Tying of reinforcement steel W R -
7 Trueness of formwork or W W RFI and Checklist
dimensional check and level
checking as per level sheet
8 Mix design of Concrete and its W W RFI and Mix design
approval. approval
9 Placing of concrete W W RFI
10 Sampling for workability, W W Pour card and slump test
casting of cubes record

*MTC- Manufacture Test Certificate


*W- Witness
*R- Review
*RFI- Request for Inspection
*BBS- Bar Bending Schedule

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 16 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

Test Plan

This section deals with the materials, methods and equipment used in the manufacturing,
transporting, placing and compaction and curing of concrete.
1) Cement
2) Coarse and fine aggregate
3) Water
4) Admixture
5) Fly Ash

1. Cement
 The cement shall be Ordinary Portland cement of 53 Grade conforming to IS 269
Codes respectively and shall meet all physical and chemical requirements as
specified.
 The cement for the works will be procured in bulk forms, MTC shall be obtained for
all batches / consignment received at site. Routine test like setting time and
compressive strength test shall also be conducted at site laboratory for each batch
as per ITP.

2. Coarse aggregate / fine aggregate


 Aggregate for concrete works shall be used from approved source. Routine test like
gradation, flakiness and elongation index, Impact value and silt content for fine
aggregate and moisture content test shall be carried out at site laboratory as per
ITP.

3. Water
 The water for the concrete will be potable water and it will be pumped into chilling
plant and stored in storage tank near batching plant. Water to be used for concrete
will be tested and got approved.

4. Admixture
 Approved and compatible admixture conforming to IS 9103 shall be used to improve
concrete handling and placing capabilities.
 Admixture shall be stored away from sunlight and shall be stirred well before usage
for uniformity.
 Mixing of two different admixture batches or manufactures shall not allowed unless
it is controlled.

5. Fly ash
 The fly ash should possess the properties as mentioned in IS 3812:2008.

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 17 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

HEALTH SAFETY & ENVIRONMENT PLAN


SPSCPL Management will provide demonstrable management leadership and commitment
through active participation in safety functions. Management is committed to manage all the
high-risk activities to ‘As Low as Reasonably Practicable’ (ALARP) level.

The management seeks to create and sustain a Safety culture in which employees share a
commitment to Health, Safety and Environment.

 First agenda- Put HSE as the “First agenda” of all project review meetings / Management
review meetings.
 Empowerment to Stop Work - Employees are empowered to stop work when the situation
warrants immediate action in view of imminent danger to life / property / environment.
 Awards- Project Director / Dy. Project Director will appreciate and reward those
employees whose prompt action helps avoid any potential incident at project site.

SPSCPL Vision

To move towards a ZERO HARM vision, requires a management game changing shift. The top
management at SPSCPL has embarked on a zero harm vision that focuses on:

 Zero Fatalities
 Zero disabling injuries
 Zero injuries to members of the public
 Zero long-term harm to health
 Zero Environmental incident

Environment

 Vehicle / Machinery and equipment operation, maintenance and refueling shall be carried
out in such a fashion that spillage of fuels and lubricants does not contaminate the ground.
 General refuse shall be stored in enclosed bins or units and it should to be separated from
construction and chemical waste.

Health

 HSE officer shall ensure all workers are screened before engaging them for duties. In
charge shall ensure availability of First aider with first aid kit.
 Shed shelter shall be provided for workers for weather protection along with drinking
water.

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 18 of 19
FOUNDATION
GENERAL METHODS AND Construction of four-lane Greenfield Delhi-Amritsar-Connectivity for Connection
ARRANGEMENTS FOR of Amritsar with Delhi-Amritsar-Katra expressway from Junction with Kapurthala-
CONSTRUCTION OF WELL Sultanpur Lodhi Road (NH-703A) near Isharwal Village Ch. 24+000 to MDR Junction
FOUNDATION at Ch. 40+900 Dhunda Village on EPC mode under Bharatmala Pariyojana in the
state of Punjab (Pkg-Spur-I)

Safety

 All transit mixers shall be provided with reverse horns.


 Warning signboards like “Men at work” shall be displayed at work area.
 If night work is to be carried out, the area shall be sufficiently provided with lightening.
 It should be ensure that safety belts were worn tied and anchored properly while working
at heights.
 All working platforms shall be tied at both ends firmly.
 All goliath crane/gantries should be fitted with limit switches and siren (to blow before
starting movement).
 The working condition of reinforcement cutting and bar bending machines limit switches
shall be ensured before starting the day’s work.
 Hand gloves shall be used for cutting, bending and shifting of reinforcement rods.
 Qualified/experienced P&M personnel through ELCB shall give the electrical connections
for vibrators, lightening only.
 Ensure that all moving parts of vibrator compressor if any shall be provided with Guards.
 Sign Boards & warning signs shall be displayed at prominent location nears to work place.
 Ensure lifting tackles such as D Shackle, wire rope slings are of requisite capacity and are
in good condition.
 All lifting personnel will be supplied with standard PPE, which consists of, Hard Hat,
Safety Boots, Overalls, Gloves, Hi-Vis (and Safety Goggles if required).

DOCUMENT NO- SPS-P344-MS-001-R0 GENERAL METHODS AND ARRANGEMENTS FOR CONSTRUCTION OF WELL Page 19 of 19
FOUNDATION