MN601 Network Project Management
MN601 Laboratory: Week 10
Instruction
All MN601 laboratory reports should be submitted weekly at the end of each laboratory
section as individual submissions via Moodle.
Organise and arrange your Moodle folder submission needly. You need to name your files
using the weekly laboratory number, your names, and student ID, such as LabWeek10
YourName MITID.
The laboratory activities have two sections, Section A is about Microsoft Project and Section
B has a few questions related to project management areas. Thus, it will provide you with a
better understanding of the topics.
Do not retype or reuse laboratory questions to avoid high similarities, always aim for 0%
similarities for all laboratory reports. For Microsoft Project Section A, when you submit
screenshots, please take the whole screenshots of your screen. Ensure your report is
different from that of other students and not plagiarised.
Late submissions will result in a loss of 10% marks for each day the report is late.
Prepared by: Dr Nalin Sharda Page
Section A: Microsoft Project - Budgeting Project
Learning Outcomes
1. Budgeting (Bottom-up) Project Using MS Project 2021
Enter cost to the project resources
Activity costs and project total costs
2. Save MyFirstProject file
1 Budgeting Project
a. Enter cost to project resources (i.e., activity/task, equipment, etc.)
Open MyFirstProject.mpp
On the View tab Split View group, click Details
In the upper pane, select an activity (e.g., 5), and in the lower pane click on a
resource (such as John) under Resource Name, select Resource Form from the
View tab Split View group.
In the Std rate field, enter $50 under resource (say John).
Similarly, enter costs for other resources.
b. Activity costs and project total costs
Assign both Chris and Terri to work one day on activity 7, i.e., “Site Selection”
and enter hourly rate $50 and $45 respectively.
On the Task tab View group, click Task Usage
On the View tab Split View group, click Details
On the View tab Split View group, select Task Form (if not already displayed)
Right click in the form in the lower page and enter Work
`In the upper pane, select Start column and right click on Start column header
to add “Cost” column, which shows the total project costs.
2 Save MyFirstProject.mpp file
Prepared by: Dr Nalin Sharda Page
Section B: Project Management Questions – Project Team and Project Progress
1. Explain at least three characteristics of successful project teams?
2. Explain conflict resolution processes to manage project conflicts.
3. What is the main purpose of monitoring and controlling a project?
4. How can you use the Schedule Performance Index and Cost Performance Index to
determine financial issues of a project.
Prepared by: Dr Nalin Sharda Page