Prosedur Kerja Tie-In Pipa 10 Dan Demolish Pipa 8

This document provides work procedures for tie-in of a new 10-inch pipeline and demolition of an existing 8-inch pipeline. It outlines the necessary equipment, preparation steps, and work processes. For the tie-in, the existing pipe is cut and a temporary spool is installed. The new pipe is pulled into position and connected to the existing pipe via flanges, bolts, and nuts. Testing is then done to check for leaks. For demolition, permits are prepared and cutting equipment is used to remove the existing 8-inch pipe, which is then transported away using a vehicle. The new pipe is slid into the permanent position.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
572 views7 pages

Prosedur Kerja Tie-In Pipa 10 Dan Demolish Pipa 8

This document provides work procedures for tie-in of a new 10-inch pipeline and demolition of an existing 8-inch pipeline. It outlines the necessary equipment, preparation steps, and work processes. For the tie-in, the existing pipe is cut and a temporary spool is installed. The new pipe is pulled into position and connected to the existing pipe via flanges, bolts, and nuts. Testing is then done to check for leaks. For demolition, permits are prepared and cutting equipment is used to remove the existing 8-inch pipe, which is then transported away using a vehicle. The new pipe is slid into the permanent position.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

PROSEDUR KERJA TIE-IN PIPA 10” DAN DEMOLISH PIPA

EXISTING 8”
ENGINEERING, PROCUREMENT AND CONSTRUCTION FOR REPLACEMENT AND
UPGRADING OF SEJORONG FRESH WATER PIPELINE SYSTEM

DOKUMEN NO: W-TJC-C2102-AMNT-II-CONS-010

CONTRACT NO: BH2245900co

ORIGINATED BY REVIEWED BY APPROVED BY DISTRIBUTION

- SDCC : Asli
- Originator : Copy
- All Div : Copy

KUSNADI RIO C. MANTIRI ARI BUDI DHARMA - All Dept : Copy


Pipeline Engineer Site Coordinator Branch Manager

EFFECTIVE
REV. NO ISSUED DATE BRIEF REVISION
DATE
0 May 15, 2023 May 15, 2023

PAGE
PT. TRUBA JAGA CITA 1 OF 7
No. Document :
W-TJC-C2102-AMNT-II-CONS-010
PROSEDUR KERJA TIE-IN PIPA 10” DAN Issued Date:
DEMOLISH PIPA EXISTING 8” May 15, 2023
UNIT ISSUING : APPROVED BY Page Rev.
CONSTRUCTION BRANCH MANAGER 2 dari 7 0

TABLE OF CONTENT

No. Description Page

1. Lingkup Pekerjaan 3 dari 7

2. Fungsi 3 dari 7

3. Equipment & Peralatan 3 dari 7

3.1 Equipment 3 dari 7

3.2 Peralatan 3 dari 7

4. Prosedur Kerja Tie-In Pipa 10” 4 dari 7

4.1 Persiapan 4 dari 7

4.2 Langkar Kerja Tie-In 4 dari 7

5. Prosedur Kerja Demolish Pipa Existing 8” 6 dari 7

6 Lampiran 7 dari 7

1.0. LINGKUP PEKERJAAN


No Document :
W-TJC-C2102-AMNT-II-CONS-010
PROSEDUR KERJA TIE-IN PIPA 10” DAN Issued Date:
DEMOLISH PIPA EXISTING 8” May 15, 2023
UNIT ISSUING : APPROVED BY Page Rev.
CONSTRUCTION BRANCH MANAGER 3 of 7 0

Prosedur ini menjelaskan tentang tata cara melakukan pekerjaan Tie-In “EPC
of Replace and Upgrade Sejorong Fresh Water” untuk area Sejorong hingga
Town Site. Sehubungan dengan itu, apabila ada perubahan terhadap
Instruksi ini, maka perubahan tersebut harus dilakukan setelah ditinjau oleh
pihak yang bersangkutan.

2.0. FUNGSI
Petunjuk kepada supervisor lapangan atau engineer terkait untuk melakukan
pekerjaan Tie-In “EPC of Replace and Upgrade Sejorong Fresh Water” pada
area Sejorong hingga Town Site.

3.0. EQUIPMENT & PERALATAN


1. EQUIPMENT
 TMC 12 Ton
 Welding Machine 400A
 Excavator

2. PERALATAN
 Electric Grinding Machine 7” & 4”
 Cutting Torch
 Hydraulic Jack 20 Ton
 Webbing Sling 4 Ton, Shackle, and Wire Sling
 Webbing Sling 5 Ton, Shackle, and Wire Sling
 Chain Block 5 Ton & 3 Ton
 Lever Block 3 Ton & 1,5 Ton
 Hammer Ring Spanner
 Hydraulic Torque
 Combination Wrench

4.0. PROSEDUR KERJA TIE-IN PIPA 10”


No. Document :
W-TJC-C2102-AMNT-II-CONS-010
PROSEDUR KERJA TIE-IN PIPA 10” DAN Issued Date:
DEMOLISH PIPA EXISTING 8” May 15, 2023
UNIT ISSUING : APPROVED BY Page Rev.
CONSTRUCTION BRANCH MANAGER 4 dari 7 0

1. PERSIAPAN
 Siapkan scaffolding atau tangga sebagai akses (jika diperlukan).
 Siapkan spool temporary untuk koneksi menuju pipa Existing 8” (Lihat
gambar)

 Marking batas pemotongan pipa existing untuk keperluan Tie-In.


Marking pipa existing untuk dipotong minimal sepanjang 20 meter dari
titik Tie-In point.

 Siapkan material-material lainnya, seperti bolt and Nut, gasket dan lain
sebagainya pada saat flange connection.

2. LANGKAH KERJA TIE-IN


 Persiapkan semua dokumen dan ATW Permit
 Siapkan peralatan yang dibutuhkan, seperti mesin gerinda, mesin las
dan sebagainya beserta consumablenya.
 Siapkan peralatan lifting dan Tarik untuk keperluan fit-up pipa saat
melakukan Tie-In.
 Pastikan pipa existing sudah dalam keadaan Non Service.
 Potong pipa pada posisi yang sudah di marking sebelumnya dalam
tahap persiapan.
No Document :
W-TJC-C2102-AMNT-II-CONS-010
PROSEDUR KERJA TIE-IN PIPA 10” DAN Issued Date:
DEMOLISH PIPA EXISTING 8” May 15, 2023
UNIT ISSUING : APPROVED BY Page Rev.
CONSTRUCTION BRANCH MANAGER 5 of 7 0

 Install temporary spool pada pipa existing 8” yang telah difabrikasi


sebelumnya.

 Tarik pipa yang baru (New Pipe 10”) kepada posisi pipa existing 8”
hingga lurus dan align. Penarikan pipa baru menuju pipa existing
memanfaatkan natural bending.

 Install Gasket, baut dan nut sesuai dengan Rating flange yang
terinstall, lalu kencangkan menurut kaidah pengencangan Flange.
 Pastikan semua komponen sudah terpasang dengan baik. Lakukan test
saat pipa Kembali On Service.
 Periksa koneksi flange dari kemungkinan kebocoran. Jika terdapat
kebocoran, segera diperbaiki.
 Metode ini akan berlaku hingga Tie-In Point seterusnya hingga Town
Site.

4.0.
4.0.
No. Document :
W-TJC-C2102-AMNT-II-CONS-010
PROSEDUR KERJA TIE-IN PIPA 10” DAN Issued Date:
DEMOLISH PIPA EXISTING 8” May 15, 2023
UNIT ISSUING : APPROVED BY Page Rev.
CONSTRUCTION BRANCH MANAGER 6 dari 7 0

4.0.
5.0. PROSEDUR KERJA DEMOLISH PIPA EXISTING 8”
 Persiapkan Dokumen dan ATW Permit yang diperlukan.
 Siapkan peralatan yang dibutuhkan untuk melakukan pemotongan dan
pembongkaran pipa existing 8” seperti Cutting Torch dan lain sebagainya.
 Mobilisasi dan pengangkatan pipa existing yang telah dibongkar akan
menggunakan TMC 12 Ton yang telah disediakan.
 Siapkan alas berupa teplon pada bagian bawah pipa baru sebelum
dilakukan penggeseran menuju posisi permanentnya.
 Setelah semua pipa existing 8” terbongkar, maka geser pipa baru menuju
posisi permanent yaitu pada posisi bekas pipa existing 8”.
 Pastikan semua area pada jalur pipa yang telah di Tie-In sudah pada
posisinya.
 Pastikan Kembali jika ada bagian pipa yang mengalami kebocoran setelah
dilakukan penggeseran.
 Metode ini akan berlaku untuk point demolish seterusnya hingga ke Town
site.
No Document :
W-TJC-C2102-AMNT-II-CONS-010
PROSEDUR KERJA TIE-IN PIPA 10” DAN Issued Date:
DEMOLISH PIPA EXISTING 8” May 15, 2023
UNIT ISSUING : APPROVED BY Page Rev.
CONSTRUCTION BRANCH MANAGER 7 of 7 0

6.0. ATTACHMENT
1. Layout Drawing terlampir terpisah