Method Statement For Testing & Commissioning of AHU
Method Statement For Testing & Commissioning of AHU
FAHU
Prior to testing & commissioning ensure that all the sections of the Air Handling Units are
thoroughly cleaned. In case units are supplied with per alumna panels, polythene protective
film must be peeled off and must be ensured that no traces of film is left loose within the
unit. Only qualified & experienced personnel shall perform testing &
commissioning.
Ensure all panels, if removed during installation, are in position. Ensure all electrical wiring
carried out and all components are provided with safety protecting and isolating devices.
Remove all filters including panel filters: install low efficiency filters such as gauze bags or a
set of throw away type filters.
Ensure all dampers are opened. Check water/ steam/ refrigerant coil connection for any
leaks. Ensure that all the air in the system and coil is vented out. Check coil face free from
free from debris. Add water in condensate drain pan to prime the trap and ensure free flow
of water into the drain. Ensure that minimum water levels are maintained in electrical pan
humidifier/ air washers.