Bill of Quantities

1. The document provides a bill of quantities for drainage works including preliminaries, drainages, culverts, concrete works, and signage. 2. Key items include site mobilization, meetings and management, tools and equipment, notice boards, and demobilization. Drainage works include excavation, culverts, backfilling, and concrete pipes. 3. The total cost for the drainage works is K494,160.45 inclusive of preliminaries, contingencies, and VAT.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
73 views

Bill of Quantities

1. The document provides a bill of quantities for drainage works including preliminaries, drainages, culverts, concrete works, and signage. 2. Key items include site mobilization, meetings and management, tools and equipment, notice boards, and demobilization. Drainage works include excavation, culverts, backfilling, and concrete pipes. 3. The total cost for the drainage works is K494,160.45 inclusive of preliminaries, contingencies, and VAT.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 9

ITEM DESCRIPTION UNIT QTY RATE

PRELIMINARIES AND GENERAL ITEMS

NOTE: The value of preliminaries and general items shall not


exceed 5% of the value of the measured works. Item

1.01 Site Mobilization

The contractor shall set up working areas and storage facilities


as may be deemed necessary including all required site
mobilization activities not mentioned below Item 1 12,500.00

1.02 Site Meetings, Works Suupervision and Management

The Contractor shall allow for all expenses associated with


convening and attending site progress meetings with clients
staff and stage inspection of works quality and progress Item 1 5,500.00

1.03 Contractor's site tools, Plants and equipment


The contractor shall provide all the tools required for the due
execution of the whole of the works Item 1 2,500.00

1.04 Purchase of a Measuring Wheel


Purchase and deliver an RS Pro Metric measuring wheel to
Ndola City Council. Item 1 2,300.00

1.05 Notice Board


The contractor is to provide 1No. Notice Board in accordance
with the requirements of the project Manager / Engineer and
erect where directed Item 1 4,000.00

1.06 Contractor's Demobilization and handover


The contractor shall upon completion of the works remove all
equipment, tools and remaing materials and clean the site as
may be approved by the Engineer Item 1 6,000.00
To Summary
AMOUNT

12,500.00

5,500.00

2,500.00

2,300.00

4,000.00

6,000.00
32,800.00
ITEM DESCRIPTION UNIT QTY RATE
DRAINAGES
Excavation and shaping of existing drains
including mitre drains as directed by the m3
2.01 Engineer 600.00 45.00

Excavate, Clean and Desilt existing Culverts,


Inlets and outlets including stream channels m3
to flow in all sizes as directed by the
2.02 Engineer. 40.00 45.00

PREFABRICATED CULVERTS
Excavation of soft material situated within
the following depth ranges below the
2.03 surface level
(a) 0m up to 1.5m m3 36.00 45
i Exceeding 1.5m and up to 3.0m m 3

ii Exceeding 3.0m and up to 4.5m m3


Extra sub item 2.03 (a) for excavating in m3
(b) hard material irrespective of the depth.

2.04 BACKFILLING
(a) Using the excavated material m3 36.00 50.00
(b) Using Imported Material m 3
350.00 80.00
Extra over subitem 2.04(a) and (b) for soil m3
( C) cement backfilling (2) with 5% Cement.

Concrete Pipe culverts: Including widening


exixtiong culverts and provision for skew
2.05 culverts on Class A bedding.
(a) 600mm Dia. Class Y m 12.00 3,500.00
(b) 900mm Dia. Class Y m 12.00 5,600.00
( C) Maintenance of existing culverts m3

2.06 Removal of Existing Concrete


(a) Plain Concrete m3 18.00 420.00
(b) Reinforced Concrete m 3
10.00 860.00
(C ) Stone Pitching m 3

Vertical formwork to provide F2 surface


2.07 finish to:
i) Culvert headwalls and wing walls m2 48.00 750.00

2.08 Reinforcement for:


a) Culvert headwalls and wing walls
b) Bridge/Portal culverts extensions
i) Mild steel bars T
ii) High Yield tress steel bars T 0.30 15,000.00
iii) Welded steel mesh fabric Kg

To Summary
AMOUNT

27,000.00

1,800.00

1,620.00
-
-

1,800.00
28,000.00

42,000.00
67,200.00
-

7,560.00
8,600.00
-

36,000.00
-
4,500.00
-

226,080.00
ITEM DESCRIPTION UNIT QTY RATE
Remove and stacking existing pipes (all sizes)
and deliver them to Ndola City Council
3.01 Workshop m 24.00 132.50

3.02 Cast in-situ concrete


a) Grade 35/19 to bridges/Culvert head walls m3
and wingwalls 18.00 2,156.30
b) Grade 35/19 to Bridge/ Culvert extension m3
slabs, walls and roof. 12.00 2,156.30
c) Grade 35/19 to apron slabs m 3

d) Grouted rock fill to aprons, floor extensions, m3


slabs

PITCHING, STONE WORK AND PROTECTION


3.03 AGAINST EROSION
(a) Riprap
i) Packed riprap (2Kg) m3 20.00 120.00
ii) Synthetic - fibre filter (Kaymat Bidim U44) m 3

3.04 STONE MASONRY WALLS


Construction of masonry lined drainages in
accordance with the drawings or as directed by
the Engineer
a) Stone masonry m2 423.00 220
b) Block Masonry m2 156.00 195

3.05 Cutting an removal of over grown vegetation Lump Sum 1.00 7,500.00
Disposal of excavated materials to a
3.06 designated dump site Lump Sum 1.00 10,500.00

3.07 ROAD SIGNS


Provide and install SATCC standard street
names No. 10.00

To Summary
AMOUNT

3,180.00

38,813.40

25,875.60

2,400.00
-

93,060.00
30,420.00

7,500.00

10,500.00

211,749.00
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

1 Preliminaries and General items 32,800.00

2 Dranaiges 226,080.00

3 Drainages 1 211,749.00

Subtotal 470,629.00

Add 5% Contigency 23,531.45

16% VAT inclusive in all rates

Grand Total 494,160.45