SRE302 - T1 - 2023 - Class 7 - Estimating Part 2
SRE302 - T1 - 2023 - Class 7 - Estimating Part 2
Delivered by:
Dr Argaw Gurmu
Level 4 - John Hay Building, Deakin University, Geelong
Tel: +613 522 78663
E-mail: [email protected]
CLASS AND SEMINARS
Library - https://www.deakin.edu.au/library
Student Committee
Mark
Deliverable Format Submission Date
(%)
Assessment 1 – Quiz 1 10 Individual 24 March 2023 8pm to 31 March 2023 8pm
Assessment 1 – Quiz 2 10 Individual 28 April 2023 8pm to 5 May 2023 8pm
Assessment 2 – Interim Report 25 Group Thursday, 6 April 2023 by 8pm
Assessment 2 – Final Report 25 Group Friday, 12 May 2023 by 8pm
Reference correctly
- Class Activity
- Class Activity
1. Building up rates for reinforcement
Reinforcement
• ASMM: “prices are to include for: Cleaning, cutting, bending,
fabricating, placing, temporary fixings and supports”.
• Subcontractors will perform this work either on a labour only, or
labour and material basis.
• Reinforcement
1- Re-bars
2- Mesh
1. Building up rates for reinforcement
Can be bought either in straight lengths (and any cutting, bending, etc. carried out by
steel fixer), or cut to size, bent, bundled and labelled by the supplier.
From extrusion plant, bars are produced with diameters larger than their normal
size. This is known as ROLLING MARGIN.
The weight of bars measured in the BQ will be based on the nominal diameter
Actual weight purchased for will be for the slightly larger bars produced by the
effect of the rolling margin. An addition of 3% is usually made to the BQ
quantities to allow for the actual weight to be purchased due to the rolling
margin.
Add a reasonable percentage for offcuts and excess lapping as well
1. Building up rates for reinforcement
Various weights patterns and sizes of mesh are available. The standard
sheet is 6m x 2.4m; and roll is 60m x 2.4m.
1. Building up rates for reinforcement
Class activity 1:
Build up the rate for 20mm deformed rebar in ground slab per tonne. The required
data are as below:
• Reinforcing bars are delivered cut to size and bent at
$1,500/𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 (cutting and bending is done by supplier)
• Assume wastage as 1%.
• Labour rate is $50/hr
2. Building up rates for formwork
Materials cost
Plant/equipment cost
Labour cost
2. Building up rates for formwork
2. Building up rates for formwork
Formwork Materials
Formwork lining
2. Building up rates for formwork
Formwork Materials
Re-usable (timber and H frames)
Lost (permanent) - Bondek
Bondek
2. Building up rates for formwork
Formwork - Plant
Crane
2. Building up rates for formwork
Formwork Labour
Labour for:
Making
Fixing
Striking or stripping
Transportation
Cleaning and oiling
Repairing
Supervision
2. Building up rates for formwork
Class activity 3:
Plywood
Clamp
Questions?