Lecture 9 - CIE 531 - EGM 501 - 2021
Lecture 9 - CIE 531 - EGM 501 - 2021
Contract Administration
Lecture 9
1
Construction Documents
Bidding requirements
Notice to Bidders
Instruction to Bidders
Proposal Form
Contract Documents
Contract Forms
Conditions of the Contract
Specifications
Drawings
Addenda
Change Orders
Agreement.
2
Construction Documents
Construction Documents are defined as the written and graphic documents prepared or
assembled by the Engineer for communicating the design of the project and administering
the contract for its construction.
2 major groups
1.Bidding Requirements
2.Contract Documents
3
Construction Documents
4
Bidding Requirements
Bidding Requirements
Bidding Requirements are used to attract bidders and explain the procedures to be
followed in preparing and submitting bids .
Bidding requirements help bidders follow established procedures and submit bids that
will not be disqualified because of technicalities. They do not become part of the contract
documents
Bidding documents
All of the construction documents issued to bidders before the signing of an owner-
contractor agreement.
5
Bid Package
Documents available to the contractor and on which he must make
a decision to bid or not
A set of plans and technical specifications, Proposal form, general conditions, special conditions,
6
Instruction to bidders
It describe the scope of the bid, source of fund (if it is financed from other
agency), fraudulent and fraud practices, eligible bidders, Eligible Materials,
Equipment and Services, Clarification of Bidding Document, Site Visit, Pre-
Bid Meeting, Amendment of Bidding Document
7
Bid Data Sheet (BDS)
Definitions, Engineer’s Authority to Issue Variations, Performance Security, Inspection of Site, Program to Be
Submitted, Cash Flow Estimate
Bid Security, Minimum Amount of Third Party Insurance
Time for Issue of the Notice to Commence, Time for Completion
Amount of Liquidated Damages, Limit of Liquidated Damages
Amount of Bonus for Early Completion, Limit of Bonus
Defects Liability Period, Amount of Interim Payment Certificates
Percentage of Retention, Limit of Retention Money, Amount of Advance Payment
Start Repayment of Advance Payment, Monthly Recovery of Advance Payment
Number of Copies of Statement of Completion and Final Statement
Procedure for Settlement of Disputes
Notice to Employer and Engineer
Origin of Materials and Plant
8
Evaluation and qualification
This section contains all the criteria that the Employer shall use to
evaluate bids and qualify Bidders if the bidding was not preceded
by a prequalification exercise and post qualification is applied.
In accordance with items specified in ITB, no other methods,
criteria and factors shall be used. The Bidder shall provide all the
information requested in the forms included in (Bidding Forms)
section..
9
Evaluation and qualification
1- evaluation : describe the Adequacy of Technical Proposal, in case of Multiple Contracts,
the conditions governs, Completion Time,
10
Bidding forms
11
Construction Documents
12
Construction Documents
Contract documents (graphic and written) describe the proposed construction (the ‘Work’) that
results from performing services, furnishing labor, and supplying and incorporating materials
and equipment into the construction
A. Contract Forms
B. Conditions of the Contract
C. Specifications & BOQ
D. Drawings
E. Addenda
F. Change Orders
13
A. Contract Forms
Contract Forms
Agreement
Performance Bond
Payment Bond
Certificates
14
B. Conditions of Contract
Conditions of Contract
Define basic rights, responsibilities, and relationships of the parties involved in the construction project.
General conditions
Contain basic expressions of rights, duties, and limitations of the entities involved.
Usually in the form of published standard documents that include principles common to most construction Contracts.
Supplementary Conditions
Modify or supplement general conditions as need to provide for requirements specific to a project. They are not standardized
documents and are prepared for specific project needs.
15
Agreement
The written document signed by the owner and the contractor that is the
legal instrument binding the parties to the contract.
Defines the relationship and obligations between owner and contractor.
16
Agreement
The agreement should contain:
The names of contracting parties
A brief description of the work
A list of contract documents, including agreement, general conditions, drawings, and
specifications.
The contract sum, or amount (lump-sum contract)
The procedures for payment
The contract time, or dates for start and completion
The signatures of contracting parties and witnesses
International construction documents are also often based on industry-prepared standard
forms.
17
Agreement Form
A number of organizations prepare recommended standard general
conditions and associated forms. Such as:
◦ ENAA (Engineering Advancement Association of Japan)
◦ FIDIC (International Federation of Consulting Engineers)
◦ ICE (Institute of Civil Engineers, United Kingdom)
◦ JCT (Joint Contracts Tribunal)
18
Bonds / Guarantees Forms
1- Performance Bond / security
The Contractor, upon receiving the Letter of Acceptance, shall obtain and provide to the Employer before signing the
Contract, the Performance Guarantee in the value of ten percent of the Contract Sum, as a guarantee of the
proper execution of the Works in accordance with the Contract. This guarantee shall be issued by a licensed
bank or financial institution acceptable to the Employer. The guarantee shall be prepared in the form included in
part B of these conditions. The obtaining of such guarantee shall in all respects be at the expense of the
Contractor.The Performance Security shall be provided to the Employer no later than the date specified in the
Letter of Acceptance and shall be issued in an amount specified in the PCC (particular conditions of contract),
by a bank or surety acceptable to the Employer, and denominated in the types and proportions of the currencies
in which the Contract Price is payable.
19
Bonds / Guarantees Forms
The Performance Security shall be valid until a date 28 days from the date of issue of the Certificate of
Completion in the case of a Bank Guarantee, and until one year from the date of issue of the
Completion Certificate in the case of a Performance Bond.
◦ In general , it is 10% of contract value
◦ Defect liability
CERTIFICATES
Includes certificates of insurance, certificates of compliance with applicable laws and
regulations.
20
Advanced payment bond
Provide a guarantee that subcontractor, material suppliers, and others providing labor,
material goods, and services to the project will be paid.
The Employer shall make advance payment to the Contractor of the amounts stated in
the PCC by the date stated in the PCC, against provision by the Contractor of an
Unconditional Bank Guarantee in a form and by a bank acceptable to the Employer in
amounts and currencies equal to the advance payment.
The Guarantee shall remain effective until the advance payment has been repaid, but
the amount of the Guarantee shall be progressively reduced by the amounts repaid by
the Contractor. Interest shall not be charged on the advance payment.
21
Advanced payment bond
The Contractor is to use the advance payment only to pay for Equipment, Plant, Materials, and
mobilization expenses required specifically for execution of the Contract. The Contractor shall
demonstrate that advance payment has been used in this way by supplying copies of invoices or other
documents to the Project Manager.
The advance payment shall be repaid by deducting proportionate amounts from payments otherwise due to
the Contractor, following the schedule of completed percentages of the Works on a payment basis. No
account shall be taken of the advance payment or its repayment in assessing valuations of work done,
Variations, price adjustments, Compensation Events, Bonuses, or Liquidated Damages.
22
Insurance Certificates
23
General Conditions of contract
24
Contents of GCC
Definitions
Contract documents
Rights and responsibilities of owner
Duties and authorities of engineer
Rights and responsibilities of contractor
Sub-contractor, Separate contractors
Time
Payments and completions
Changes in the work
Protection of persons and property
Insurance and bond
Disputes
Termination of contract
Miscellaneous provisions
25
THANK YOU
26