Universidad Nacional de Derecho de Rajiv Gandhi
Universidad Nacional de Derecho de Rajiv Gandhi
VIS INTERNATIONAL
COMMERCIAL ARBITRATION MOOT
ON BEHALF OF:
- CLAIMANT -
AGAINST
- RESPONDENT -
TABLE OF CONTENTS
I. BOOKS .................................................................................................................. X
iii. Subsequent conduct confirms the conclusion of the Arbitration Agreement ........ 6
iv. The Arbitration Agreement meets all the Formal Validity requirements ................ 7
b. Frustration of the Arbitration Agreement would violate the general principle ...... 9
c. Even VCLT does not allow RESPONDENT to invoke its national law ................... 10
[2] The Arbitration Agreement stands valid due to the doctrine of separability ............ 12
[1] Proceeding with the arbitration will save time and money .......................................... 15
[2] RESPONDENT has failed to show any of the accepted criteria for a stay ................... 16
[3] The parties intended to arbitrate disputes about contractual validity ......................... 17
[1] The applicable legal principles and existing arbitral practice would not lead to such a
decision ........................................................................................................................................... 18
[1] Charges brought up against Mr. Field do not relate to the present contract ............ 22
[2] The alterations in the scope of the contract have been explained by CLAIMANT .... 22
[3] The Public Prosecution Office and Ms. Fonseca cannot be relied upon to conduct an
objective investigation................................................................................................................... 23
A. The drones were not intended or destined for air transport ................................ 24
[1] The intended function of objects and purpose of transactions is paramount .......... 24
[2] Kestrel Eye 2010 drones were meant to function as surveillance devices ................. 24
ii. RESPONDENT purchased Kestrel Eye 2010 to conduct surveillance alone ............... 25
A. RESPONDENT cannot rely on Art. 3.2.5 as it is not applicable in the instant factual
situation ....................................................................................................................... 27
i. Identified factual subject matter would at most raise issues of non-conformity ...... 27
ii. There exist no extraneous/ collateral factual circumstances beyond mere non-
conformity to establish misrepresentation ............................................................................. 28
[4] Allowing RESPONDENT’s misrepresentation claim would dilute the purpose and
authority of the CISG ................................................................................................................... 30
i. There was no fraudulent representation by CLAIMANT about the quality of the drones
............................................................................................................................................... 31
INDEX OF ABBREVIATIONS
Art./Arts. Article/Articles
cl. Clause
ed/eds. Editor/Editors
Id. Idem
No. Number
op. Opinion
p./pp. Page/Pages
RE RESPONDENT’s Exhibit
§/§§ Section/Sections
v. Versus
Vol. Volume
Algerian Code Algerian Code of Civil Procedure, adopted February 25, 2008
INDEX OF AUTHORITIES
I. BOOKS
Kröll/ Mistelis/ Stefan Kröll, Loukas Mistelis, Pilar Perales ¶¶ 106, 108,
Viscasillas Viscasillas (eds.) 110
UN Convention on Contracts for the International Sale of
Goods (CISG): A Commentary
2nd Edition
C.H. Beck – Hart – Nomos, 2018
Lew/ Mistelis/ Julian Lew, Loukas Mistelis and Stefan Kröll, ¶¶ 40, 41, 50,
Kröll Comparative International Commercial Arbitration 129
Kluwer Law, 2003
Paterson JM Paterson ¶ 30
Duty of Good Faith: Does it Have a Place in Contract Law?
74 Law Institute Journal 47, 48 (2000)
Woods/ Ros/ Guillet/ Louise Woods, Ciara Ros, Elena Guillet and Edward ¶¶ 63, 69
Wilson Wilson (Vinson & Elkins LLP)
“Procedural Issues”
Global Arbitration Review, June 9, 2021
III. MISCELLANEOUS
Op. 13, CISG AC Opinion no. 13, CISG Advisory Council ¶ 130
AD HOC ARBITRATION
Revere Copper and Brass Revere Copper and Brass v. Overseas Private ¶ 30
Investment Corporation,
American Arbitration Association award
17 International Legal Materials 1321 (1978),
summarised in V Y.B. COM. ARB. 202 (1980)
AUSTRALIA
Balaji Coke Industry Traxys Europe S.A. v. Balaji Coke Industry Pvt ¶ 41
Ltd.
Federal Court, Australia
March 23, 2012
[2012] FCA 276
CHINA
CISG/2000/06
Available at:
https://iicl.law.pace.edu/cisg/case/china-january-
7-2000-translation-available
COLOMBIA
FRANCE
GERMANY
HONG KONG
Fung Sang Fung Sang Trading Ltd v. Kai Sun Sea Prods. & ¶ 65
Food Co. Ltd.,
CLOUT case no. 20
High Court—Court of First Instance, Hong Kong
October 29, 1991
[1991] HKCFI 190 (H.K. Ct. First Inst.)
ICSID
Available at:
https://www.italaw.com/sites/default/files/case-
documents/ita0340.pdf
Glencore A.G. Glencore International A.G. and C.I. Prodeco S.A. ¶¶ 55, 79
v. Republic of Colombia
ICSID Case No. ARB/16/6
Award dated August 27, 2019
Available at:
https://www.italaw.com/sites/default/files/case-
documents/italaw10767_0.pdf
Micula v. Romania (II) Ioan Micula, Viorel Micula and others v. Romania
[II]
ICSID Case No. ARB/14/29
Award dated March 5, 2020
Available at:
https://www.italaw.com/sites/default/files/case-
documents/italaw11284.pdf
INDIA
ICC
Dallah Real Estate First Partial Award in Dallah Real Estate and ¶ 31
Tourism Holding Company v. The Ministry of
Religious Affairs, Government of Pakistan
ITALY
PARAGUAY
PCA
Philip Morris Asia Ltd. Philip Morris Asia Limited v. The Commonwealth ¶ 61
of Australia
UNCITRAL, PCA Case No. 2012-12
Procedural Order No. 4, dated October 26, 2012
Available at:
https://www.italaw.com/sites/default/files/case-
documents/italaw1215.pdf
SWITZERLAND
UNCITRAL
UNITED KINGDOM
20-1143_m6hn.pdf
Geneva Pharms. Geneva Pharms. Tech. Corp. v. Barr Labs., Inc. ¶ 120
District Court for the Southern District of New
York
May 10, 2002
201 F. Supp. 2d, 236, 285 (S.D.N.Y. 2002)
Prima Paint Prima Paint Corp. v. Flood & Conklin Mfg. Co. ¶ 36
Supreme Court of the United States
June 12, 1967
388 U.S. 395 (1967)
STATEMENT OF FACTS
The Parties entered into a Purchase and Supply Agreement (PSA) for supply of CLAIMANT’s latest
Kestrel Eye 2010 UAS.
MARCH 20, 2020 RESPONDENT opened a tender process in connection with the NP
Development Program. CLAIMANT was selected as one of the two bidders
with which RESPONDENT entered further negotiation.
NOV. 4, 2020 Mr. J.C. Bluntschli, COO, Drone Eye plc and Mr. David Field, COO,
Equatoriana Geoscience, held a meeting to negotiate the contract. In the
meeting, CLAIMANT made an entirely new offer for 6 UAS including their
service and maintenance which Mr. Field intended to accept.
NOV. 27, 2020 The Arbitration Agreement (Article 20 of PSA) was up for discussion and
approval in the Parliament but was called-off on short notice.
NOV. 29, 2020 Mr. Bluntschli had been arrested for tax evasion and Mr. William Cremer,
CEO, Drone Eye plc, had to replace him in the negotiations. Mr. Cremer
insisted on the inclusion of a merger clause.
DEC. 1, 2020 PSA signed at a formal ceremony by Mr. Cremer, Ms. Wilhelmina Queen,
CEO, Equatoriana Geoscience, and Mr. Rodrigo Barbosa, Equatoriana’s
Minister of Natural Resources and Development.
PSA provided for the delivery of 6 Kestrel Eyes 2010 UAS. The first 3 drones
were supposed to be delivered by January 15, 2022 and the other 3 drones
were to be delivered at later dates. The overall price for the 6 UAS was fixed
at 44 million EUR, with 10 million to be paid by RESPONDENT in advance.
FEB. 2021 CLAIMANT unveiled its newest UAS, the Hawk Eye 2020, at the air show in
Mediterraneo. RESPONDENT alleged that CLAIMANT had misrepresented the
quality of the drones and that the Kestrel Eye drone were neither state-of-the-
art nor the latest.
CLAIMANT also applied for the patents relating to the technology used in
Hawk Eye 2020 after the air show.
MAY 27, 2021 The Parties held meeting to resolve the issue of misrepresentation on the part
of CLAIMANT. The discussion about the alleged misrepresentation ended until
it suddenly resurfaced in May 2022. In this meeting, RESPONDENT also asked
for amendments to the arbitration clause.
JULY 3, 2021 The Citizen started to publish a series of articles about a massive corruption
scheme surrounding the NP Development Program and led to a public outcry,
which led to the Prime Minister’s resignation and a new government formed
by a coalition of several parties, including the Liberal Party.
DEC. 27, 2021 The new government immediately issued a moratorium for all contracts
concluded under the NP Development Program and appointed Ms. Lyndsey
Fonseca as special public prosecutor to investigate the corruption allegations
surrounding the NP Development Program.
MAY 21, 2022 Announcement by Ms. Fonseca bringing up charges concerned with the
payments made to Mr. Field’s offshore accounts in connection with two other
contracts. She promised that she would also investigate all other contracts
concluded by Mr. Field for signs of corruption.
MAY 30, 2022 Ms. Wilhelmina Queen terminated PSA through legal notice.
JULY 2022 CLAIMANT was granted the patents relating to the technology used in the
Hawk Eye 2020.
SUMMARY OF ARGUMENTS
Issue 1: The Parties have validly agreed on Tribunal’s jurisdiction. There exists a valid concluded
Arbitration Agreement between the Parties. Parties’ intention to arbitrate and their post
contractual conduct speaks to the Arbitration Agreement’s validity. RESPONDENT cannot rely on
its internal law to revoke its consent to arbitrate. Utilisation of internal law goes against the general
principles of International Commercial Arbitration. Also, any attempt to use national law would
be contrary to the good faith doctrine. Further, the allegations on PSA being obtained by
misrepresentation and corruption do the affect the validity of the arbitration. Such challenges on
the main contract cannot make the Arbitration Agreement invalid due to doctrine of separability.
Moreover, any award rendered by the tribunal will be enforceable.
Issue 2: RESPONDENT’s request to stay or bifurcate the arbitration pending the outcome of the
investigation to be conducted by the Public Prosecutor’s office of Equatoriana has to be denied
because RESPONDENT has failed to demonstrate why a stay would be in the interest of efficiency
and in line with existing arbitral practice, and a stay would not address RESPONDENT’s concerns
either, the proceedings should not be bifurcated as per existing arbitral practice and would make
any further proceeding futile, RESPONDENT’s concerns regarding the Arbitral Tribunal’s
investigative powers have been blown out of proportion as the domestic investigation is not
controlling case law, and third party evidence can be collected by the Arbitral Tribunal via Art. 27
and there is no credible allegation of corruption with regard to the present contract.
Issue 3: The Purchase and Supply Agreement is governed by the CISG since Kestrel Eye 2010
drones do not qualify as aircrafts under Art. 2(e) CISG. They were not destined to carry out the
function of air transport. CLAIMANT engineered them to function as surveillance devices, and
accordingly bestowed them with low payload carrying capacities and superior flight stability
features at a higher cost than the drones manufactured to excel at air transport. The parties were
cognizant of this fact and understood that the purpose of the transaction was to facilitate
surveillance in Northern Equatoriana. They agreed that the drones would be deployed principally
for surveillance. Moreover, fifty percent of the drones completely lacked the capability to transport
cargo owing to the absence of free space in their payload bays. The drones did not even require
registration under Equatoriana’s domestic law and were thus not subject to any special registration
requirements outside the scope of the CISG. Therefore, Kestrel Eye 2010 is not an aircraft and
the sales transaction falls within the sphere of application of the CISG.
Issue 4: In case PSA is governed by CISG, RESPONDENT cannot rely on Art. 3.2.5 ICCA to avoid
the contract. First, the provision is not applicable in the instant factual situation. Art. 35 CISG
provides remedy for breach of contract by a party on account of non-conformity of goods.
RESPONDENT’s claim that the Kestrel Eye 2010 drones do not meet the qualities agreed upon by
the parties does not involve an interest arising independently of contractual claims to establish a
case of misrepresentation beyond mere non-conformity. The claim is also not based on a
fraudulent intention on behalf of CLAIMANT, and Art. 3.2.5 ICCA provides the same remedy, i.e.,
avoidance of the contract, as is also allowed under Art. 49 CISG for supplying non-conforming
goods. Therefore, allowing RESPONDENT’s fraud claim to pre-empt a possible non-conformity
claim under the CISG would result in dilution of the latter’s purpose and authority. Second, in the
alternative, even if Art. 3.2.5 ICCA is applicable in the instant case, RESPONDENT cannot rely on
it as there was no misrepresentation. There was no fraudulent representation or non-disclosure by
CLAIMANT. Further, CLAIMANT had no intent to lead RESPONDENT into error and gained no
advantage to RESPONDENT’s detriment.
ARGUMENTS ON PROCEDURE
1. On December 1, 2020 CLAIMANT and RESPONDENT concluded PSA for 6 of CLAIMANT’s Kestrel
Eye 2010 Drones [Cl. Ex. C2, p.10]. The PCA Rules [Letter by PCA, p.24], in conjunction with the
UNCITRAL Model Law [PO1, p.43, ¶ 3] and the New York Convention [Id.], govern the arbitral
procedure.
3. CLAIMANT requests the Tribunal to rule that Parties have validly agreed on the jurisdiction of the
Arbitral Tribunal. The challenge to the validity of Arbitration Agreement is based on the claims of
lack of authorization, corruption and misrepresentation [Response, pp.30-31, ¶¶ 20-23]. In deciding
whether the Parties have agreed on the jurisdiction, the tribunal must determine; the existence of
an enforceable Arbitration Agreement [A]; whether the Arbitration Agreement can be avoided for
the claims of misrepresentation and corruption [B]; the award rendered by the Tribunal would be
enforceable [C].
4. An arbitral tribunal bases its jurisdiction only on an enforceable and validly concluded arbitration
agreement [Craig/Park/Paulsson, ¶ 5.01; Kaufmann-Kohler, ¶ 189a; Redfern/Hunter III, ¶¶ 5.85-5.87;
Redfern/Hunter II ¶ 1-13]. Contrary to RESPONDENT’s allegations, both Parties validly concluded
an Arbitration Agreement [1]. The Arbitration Agreement is not invalid for lack of authorization
from the Parliament [2].
5. The foundation of an arbitration proceeding is a valid arbitration agreement [Van Den Berg, pp.144-
145; ICC 7929]. The valid conclusion of the Arbitration Agreement is shown through: the Parties’
intent to arbitrate [i]; their consent to arbitration [ii]; their subsequent conduct [iii]. The
6. The validity of the arbitration agreement depends primarily on the parties’ common intent [Dalico
Case; SOERNI]. Many courts have given paramount importance to the intent of parties to arbitrate
[Lucky-Goldstar; Fiona]. So much so that, even the minimal indication of intent to arbitrate must be
given full effect by the Arbitral Tribunal [Standard Fruit; Bauhinia Corp.]. Both RESPONDENT and
CLAIMANT showed clear intentions to submit their disputes to arbitration. CLAIMANT gave
RESPONDENT no indication that they would be amenable to any other form of dispute resolution.
The only possible form of dispute resolution mechanism ever discussed between the parties was
Arbitration.
7. The intent of the parties must be examined “by taking into account what the parties reasonably
and legitimately envisaged” [Fouchard, ¶ 477]. In the present case, it was reasonable to expect that
contracting parties would go for arbitration given the tendency of the courts of Equatoriana to
favour the State [PO2, p.46, ¶ 18]. Due to this, even the second bidder who was based in
Equatoriana had an arbitration clause in its offer [PO2, p.47, ¶ 28]. The State-Owned Entities of
Equatoriana regularly submit disputes to PCA Arbitration [Response, p.30, ¶ 21]. CLAIMANT also
regularly goes for arbitration when contracting with state parties [Cl. Ex. C7, p.19 ¶ 14]. Hence, it
was legitimate to anticipate arbitration in case of a dispute.
9. It is settled law that a party’s assent to an instrument presumptively includes assent to all the
instrument’s terms [Born, p.851]. A party’s signature on the underlying contract constitutes consent
to the arbitration clause contained within that contract [Id.]. PSA was signed by both Ms.
Wilhelmina Queen and Mr. William Cremer, RESPONDENT’s and CLAIMANT’s CEOs respectively
[Cl. Ex. C2, p.12; Cl. Ex. C7, p.18, ¶ 8]. Thus, Art. 20 PSA was assented to by both the parties.
10. RESPONDENT’s post contractual conduct indicates that it considered itself to be bound by the
Arbitration Agreement. A party may be bound by an arbitration clause if its subsequent conduct
indicates that it is assuming the obligation to arbitrate [Thomson-CSF; Shaw Group; Gvozdenovic]. In
May 2021, RESPONDENT requested for an amendment to allow for submission to arbitration under
UNCITRAL Expedited Arbitration Rules, 2021 for a claim of less than 1 million Euros and the
inclusion of UNCITRAL Transparency Rules [Cl. Ex. C7, pp.18-19, ¶¶ 10, 14].
11. The issue of state entities submitting their disputes to arbitration was put up before the Parliament
the following month [Cl. Ex. C7, p.19, ¶ 15]. To defend the practice of submitting disputes to
arbitration, the government argued in favour of arbitration agreements containing transparency
clauses and referred to the Arbitration Agreement in PSA as an example [Cl. Ex. C7, p.19, ¶ 15].
Thereby, it publicly acknowledged the valid conclusion of the Arbitration Agreement. The request
for amendment in the existing Arbitration Agreement and the reference and justification of the
Arbitration Agreement in the parliamentary debate demonstrates that RESPONDENT had assumed
its obligation to arbitrate.
12. Moreover, performance of contractual obligations is regarded as assent to the contract, and in
some cases the arbitration clause contained therein [Born, p.858; Craddock; Albertson; First Citizens
Mun. Corp]. The handing over of advance payment in accordance with Art. 4 PSA was an act in
furtherance of PSA [PO2, p.47, ¶ 30]. This was a clear indication to CLAIMANT that RESPONDENT
considered itself to be bound by the obligations under PSA, thus confirming the conclusion of the
Arbitration Agreement.
13. The Arbitration Agreement meets all the form requirements under DAL, which is a verbatim
adoption of Model Law [PO1, p.47, ¶ 3]. The Model Law places form requirements on the
Arbitration Agreements [Born, p.185]. Danubia has adopted Option 1 of Art. 7 under which it is
necessary for an arbitration agreement to be in writing [Binder, p.140].
14. Under DAL, a written form requirement is complied when there is a written record of the
agreement to arbitrate (without regard to the manner in which that agreement to arbitrate may
have been concluded) [Binder, p.140; Rajoo/Klötzel, p.729; Born, p.187; UNCITRAL Exp. Note ¶ 19].
The written form requirement is satisfied here because of the existence of a formally signed
contract between both the parties [Cl. Ex. C2, p.12]. The Arbitration Agreement is recorded in
Art. 20 and is signed by both the parties [Id.]. In conclusion, Parties have validly concluded an
Arbitration Agreement.
15. The NYC's international neutrality and non-discrimination standards should apply to any
limitations that national legislatures have placed on the ability of parties to enter into arbitration
agreements [Born, p.671; Young Pecan Cie; SOERNI]. Contracting States have made a commitment
to the NYC to recognize and enforce international arbitration agreements, save where they are null
and void. This commitment overrides national law rules that single out international arbitration
agreements for special burdens [Born, p.671; NYC, Arts. II, V].
16. Firstly, RESPONDENT cannot rely on its own national laws as its actions go against general
principles of ICA [i]: the principle of prohibiting the use of national restrictions is a general
principle of ICA [a]; frustration of the Arbitration Agreement would be in violation of these
principles [b]; and even the VCLT does not allow RESPONDENT to invoke its national law [c].
Secondly, invoking national law would also go against the principle of good faith [ii].
a. The principle of prohibiting the use of internal restrictions is a general principle of ICA
17. Refusal to accept national law as a jurisdictional bar to international arbitration involving a state
may be seen as a necessary complement to the modern rule of restrictive sovereign immunity
[Paulsson, p.12]. The principle that the state or state entity may not rely on its internal formalities to
deny the validity of an arbitration agreement concluded by it is a general principle of international
arbitration [Fouchard, p.322; Pitkowitz]. This is due to multiple reasons.
❖ Firstly, it is enshrined in international conventions. Art. II(1) ECICA talks about “Rights of Legal
Persons of Public Law to resort to Arbitration” [ECICA, Art. II(1)]. According to Art. II(1), any
legal person of public law has a right to conclude a valid arbitration agreement. Arts. 27 and 46
VCLT contain a similar principle which may be applied between a state and a private party
[VCLT, Arts. 27, 46; Paulsson II].
❖ Secondly, international arbitral case laws and scholarly opinions have recognized this principle.
In Benteler v. Belgium, it was held that the principle of Art. II(1) is a general principle of
international arbitration [Benteler]. There is an abundance of cases and opinions where arbitrators
have arrived at a similar conclusion [ICC 1526; ICC 3327; ICC 5103; Italian Co; Elf Aquitaine Iran;
Framatome; Hascher; Razumov].
❖ Lastly, many jurisdictions have incorporated this principle in their national law. Countries like
Switzerland, Algeria, Tunisia etc [Swiss Law, Art. 177(2); Tunisian Code, Art. 7; Algerian Code Art.
442]. have adopted this principle as a substantive rule. On the other hand, the national courts of
countries like France, England, Greece, Italy, among others, have upheld the validity of
arbitration agreements using this principle [Anghelos; Gatoil International Inc, Corte di Cassazione].
18. The rule prohibiting the use of internal restrictions is a general principle of international arbitration
and is regularly applied by arbitral tribunals irrespective of the applicable law and the seat of
arbitration [Fouchard, p.318; Kroll, p.12]. Hence, it must be applied in the instant case.
19. The invalidation of the Arbitration Agreement on account of lack of consent from the Parliament
would be in violation of the general principle prohibiting the use of internal restrictions. It is an
unsatisfactory situation when a state agency relies on its own law to defeat a contract that it has
freely entered into, by contesting the validity of its agreement to arbitrate on grounds of its own
legislation [Pitkowitz, p.107]. To avoid such a situation, the principle prohibiting the use of internal
restrictions must apply.
20. For the principle to apply, the party relying on internal restriction must be a state-controlled entity
[Beisteiner, pp.56-66; Hascher, p.516; Pitkowitz, p.108]. The sole shareholder of Equatoriana
Geoscience is the State [Notice, p.4, ¶ 2; PO2, p.44, ¶ 5]. Different ministers appoint the supervisory
board which is chaired by the Minister of Natural Resources and Development [id.]. Although it
operates like a commercial company in essence, RESPONDENT is in fact a legal person of public
law.
21. To avoid arbitration, RESPONDENT is trying to rely on its national law that addresses the issue of
contracts for public works [PO2, p.47, ¶ 31; Response, ¶ 21]. The provision relating to administrative
works set out in Art. 75 states that Parliamentary consent in cases of administrative contracts when
the other party is a foreign entity or the arbitration is seated in a different state. Countries such as
Iran and Tunisia have had a similar provision in their national law which allowed the state entities
to back out of an arbitration agreement after consenting to it [Iran CONST., Art. 139; Tunisian Code,
Art. 7]. However, national courts and arbitral tribunals have estopped these States or their entities
from relying on such provisions to retract their consent from international arbitration agreements
[Razumov, pp.260-267; Framatome; Elf Aquitine Iran; Etat tunisien; ICC 5103].
22. A party cannot rely on a failure to comply with its own provisions concerning the extent and the
powers of the governmental entities [Beisteiner, pp.58-66; Audit]. To challenge a tribunal’s
jurisdiction, a party cannot use the irregularities attributable to itself, more so when the arbitration
agreement was entered into with full knowledge and approval of the highest authorities
[Framatome]. In light of the amendment request, it is clear that RESPONDENT had full knowledge
of the arbitration agreement [Cl. Ex. C9, p.22]. The arbitration agreement was knowingly signed
by Mr. Rodrigo Barbosa, Minister of Natural Resources and Development, which he could only
do after proper consent from the Parliament [Cl. Ex. C7, p.18, ¶ 8; Response, p.28, ¶ 12].
RESPONDENT alleges that the Mr. Barbosa was acting ultra vires as there was no consent by the
Parliament [Response, p.28, ¶ 12]. However, the onus was on RESPONDENT to get the required
approval from the Parliament and it cannot be allowed to take advantage of this irregularity that
occurred at their own end.
23. The purpose of this principle would be defeated if a foreign party is expected to perform extensive
due diligence into the required domestic formalities of the State it is contracting with [Beisteiner,
pp.56-66]. A reasonable due diligence is enough, the standard of which should not be set too high
[Id.]. In the present case, CLAIMANT performed a reasonable amount of due diligence. Ms. Horacia
Porter examined all the registration/operation/special requirements and possible immunities from
state [Cl. Ex. C7, p.18, ¶ 4]. Although CLAIMANT was aware that approval by the Parliament is
required for arbitration agreement [Cl. Ex. C7, p.18, ¶ 6], it was assured by Mr. Barbosa that the
Parliamentary approval was just a formality and would be forthcoming [Cl. Ex. C7, p.18, ¶ 9].
Given the conduct of RESPONDENT it would not be reasonable to expect CLAIMANT to constantly
keep inquiring about it.
24. Requiring the private investor to question a minister's affirmed authority is hardly conducive to
the aims of either the Government or the private party [Paulsson, pp.90, 91; Kröll, p.12]. It is normal
to presume the capacity of the minister in charge [Aminoil; Govt. of Turkey et al; Case No. 262, p.434;
Hemming]. CLAIMANT had no reason to doubt the words of the minister as RESPONDENT was
already performing its contractual obligations [PO2, p.47, ¶ 30].
25. Prior to the evolution of the principle, private users of arbitration faced a lot of problems with the
uncertainties that exist in the national law of the contracting State party [Beisteiner, pp.56-66]. The
contrary views on requirement of parliamentary consent for amendment in arbitration clause create
an uncertainty in the national law of Equatoriana [PO2, p.48, ¶ 36]. Some believe that Parliamentary
approval is needed for amendment while others do not [Id.]. Through the amendment request
CLAIMANT was led to believe that the Arbitration Agreement was validly concluded [Cl. Ex. C7,
p.18, ¶ 10]. Moreover, after the amendment the State referred to our Arbitration Agreement in the
Parliamentary debate [Cl. Ex. C7, p.19, ¶ 15]. Thus, the uncertainty in the Equatoranian law cannot
go against CLAIMANT.
26. Therefore, the Tribunal must not allow RESPONDENT to frustrate the Arbitration Agreement
through Art. 75, as it would violate the general principle of ICA which prohibits the use of internal
restrictions to avoid arbitration.
c. Even VCLT does not allow RESPONDENT to invoke its national law
27. VCLT confirms the position established by the general principle of ICA which prohibits the use
of national law. All three States are parties to the VCLT. Art. 27 forbids states from invoking
internal law as a justification for their failure to perform a treaty [Art. 27, VCLT]. The general
principle expressed therein must apply all the more in the dealings of the State or State-Owned
entity with a private counterparty, as the current issue is similar to the treaties concluded in
contradiction to the provisions of national law [Beisteiner, pp.56-66; Paulsson II, p.91].
28. This principle is bolstered by Art. 46, which provides that a State's right to invoke the violation of
a provision of its internal law regarding competence to conclude treaties is limited to situations
where the violation was “manifest” to the other party [VCLT, Art. 46; Blusun]. A “manifest
violation” is defined as one that would be “objectively evident” to the other party conducting itself
in the matter in accordance with normal practice and in good faith [id.; Kiran Nasir Gore, p.; Slovak
Republic].
29. Although RESPONDENT is attempting to rely on the violation of Equatoriana’s domestic law to
invalidate its consent to arbitrate, its endeavour fails. The alleged violation was not manifest to
CLAIMANT, who was initially under the impression that the Parliament had approved the
submission to arbitration [Cl. Ex. C7 ¶8, 10]. RESPONDENT also reassured CLAIMANT about the
approval by the Parliament, claiming that it was only a matter of time, being a mere formality [Cl.
Ex. C7 ¶9]. CLAIMANT expected subsequent approval to be granted [PO2, ¶ 30]. RESPONDENT
further reinforced the validity of the Arbitration Agreement by seeking an amendment to the same
[Cl. Ex. C7 ¶10]. In light of the same, and acting in good faith, CLAIMANT did not confirm the
explicit approval from Parliament and was thus unaware of the alleged violation. Considering that
the violation of domestic law cannot be said to be objectively evident to CLAIMANT, RESPONDENT
cannot be allowed to rely on the violation of domestic law to thwart arbitration
30. The principle of good faith means that one should not frustrate legitimate and reasonable
expectations [Paterson, p.74; Yee; Burton]. It presumes a co-operative obligation, an honest and
reasonable conduct, and to have regard to the reasonable expectations and legitimate interests of
the other party [Miller/Perry, p.98]. This principle of good faith has been applied by international
arbitrators as an imperative norm perceived without reference to any specific national law [Paulsson
II, p.91; Craig/Park/Paulson, §§ 5.02 and 5.07; Revere Copper and Brass; ICC 1939; ICC 1803].
CLAIMANT was reasonable and legitimate in expecting RESPONDENT to perform its obligations.
Every indication given by RESPONDENT showed that it effectively wanted to perform its obligation
under PSA.
31. The principle of good faith is used to avoid a situation where a State uses its legislative power to
its advantage and frustrates the arbitral proceedings [ASA Bull; ICC 4381; Dallah Real Estate;
Fouchard, ¶ 553; Kröll, p.13]. CLAIMANT entered into PSA in good faith, and thus deserves
protection of international law. Any ground taken by RESPONDENT to render the Arbitration
Agreement ineffective would be in bad faith. Hence, the Tribunal must not allow RESPONDENT
to use their internal restrictions.
32. In conclusion, the Arbitral Tribunal has jurisdiction as parties have validly concluded an
Arbitration Agreement which meets all the formal validity requirements. Moreover, RESPONDENT
cannot rely on its national law to revoke its consent from Arbitration.
33. RESPONDENT contends that the Tribunal lacks jurisdiction as there is no valid arbitration
agreement as it is most “likely” that the conclusion of PSA was tainted by corruption resulting in
its invalidity [Cl. Ex. C8, p.20]. They argue that PSA and thus also the arbitration clause contained
therein would not have been concluded but for the bribes paid and the misrepresentation by
CLAIMANT [Response, p.30, ¶ 20]. CLAIMANT will demonstrate that: the allegations of corruption are
arbitrable [1]; and the Arbitration Agreement stands valid due to the doctrine of separability [2].
34. RESPONDENT might contend that the Tribunal does not have the jurisdiction to address the
allegations of illegality and corruption. Earlier Tribunals used to show reluctance to resolve matters
relating to corruption or bribery [ICC 1110; Hwang/Lim, pp.43-44]. However, recently, tribunals
have frequently considered disputes where a party claims that the underlying contract was tainted
by, or invalid due to corruption [Westinghouse; Westacre; Fiona; ICC 6474; ICC 6286; ICC 4145; NAI
4687; Taller RC] and held such questions to be capable of resolution by arbitration. As the English
Court of Appeal in the case of London Steamship Owners pointed out, it is necessary to distinguish
between a finding of criminal conduct and a conviction which provides the basis for penal
sanction. The arbitrator ordinarily has the jurisdiction to find facts which constitute a criminal
offence [London Steamship Owners]. Therefore, the allegations of bribery or corruption with regard
to PSA can be heard by and decided upon by the tribunal.
[2] The Arbitration Agreement stands valid due to the doctrine of separability
35. It is well settled that for an arbitration agreement to be considered invalid due to corruption or
misrepresentation, there must be a specific averment that the arbitration agreement was obtained
by corruption/misrepresentation [Harbour Assurance; Fiona].
36. This is a usual complaint that if the party had prior knowledge of the fraud, or misrepresentation,
or illegality, or bribery, then they would not have entered the contract as a whole and that logically
and necessarily includes the arbitration clause [Pengelley, pp.450-451]. This argument, however
logical it may seem, is precisely what the tribunals and the courts around the world have rejected
on the grounds of the separability doctrine [Id; Feehily, p.367; Hwang/Lim, p.43; Prima Paint; Harbour
Assurance; Fiona; Buckeye; Ferris v. Plaister].
37. As per Article 16(1) of the DAL, the arbitration clause which forms a part of a contract shall be
treated as an agreement independent of the other terms of the contract. A decision by the Tribunal
that the main contract is null and void would not lead to the invalidity of the arbitration clause
[DAL, Art. 16(1); PCA Rules, Art. 23(1)]. It is well settled that the claims that the underlying
contract is illegal or obtained illegally, do not ordinarily affect the validity of the arbitration clause
[Westinghouse; Westacre; Rosell/Prager, p.330; Concepcion, p.13]. Similarly, claim that the underlying
contract was voidable for misrepresentation or fraud does not affect the validity of the arbitration
clause [Capital Trust; Comandate Marine Corp.; Ferris v. Plaister]. The Arbitration Agreement can
survive even when the main contract is repudiated, breached, terminated or found to be invalid
[Jones, p. 57; Parish, pp.661-679; Robert Lawrence Co; N.N. Global].
38. In the present case, RESPONDENTs have merely alleged that the main contract has been obtained
through corruption and misrepresentation [Response, p.30, ¶ 20]. There is no specific challenge
posed against the arbitration agreement. RESPONDENT have failed to show that the arbitration
agreement specifically was obtained by bribery or misrepresentation. Merely alleging bribery or
misrepresentation in the main contract would not affect the arbitration agreement. Therefore,
RESPONDENTs objection to the jurisdiction of the tribunal on this ground must be declined.
39. The sole remaining impediment to jurisdiction is potential non-enforceability of the Tribunal’s
award in Equatoriana. The grounds on which the recognition and enforcement of an award may
be refused are narrow. These grounds are codified in Art. V NYC and Arts. 34 and 36 Model Law
[NYC, Art. V; UNCITRAL, Arts. 34, 36]. RESPONDENT may contend that the award rendered by
the Arbitral Tribunal is against the public policy of Equatoriana, making it unenforceable.
However, the award is not contrary to the public policy of Equatoriana.
40. Under Art. V NYC, the term public policy refers to a narrow international standard otherwise
classed as ordre public [Lew/Mistelis/Kröll, ¶ 9-31]. While the ‘international’ element is not explicitly
referred to in the Model Law or NYC, it is extensively recognised in French jurisprudence and is
supported by both case law and commentary [Mitsubishi; Ganz; Thieffry, p.35; Caprasse/Hanotiau,
41. For an award to be rendered unenforceable, it must not be contrary to the public international
notions of morality [Lew/Mistelis/Kröll, ¶ 9-31]. Also, a mere violation of domestic law is unlikely
to make a ground to refuse recognition or enforcement on the basis of public policy [Travaux
préparatoires, NYC Art. V; Balaji Coke Industry; Petrotesting Colombia]. An award rendered by the
Arbitral Tribunal would not violate public international notions. On the contrary, it fosters
international public policy in form of upholding general principles of ICA. Even if the award
rendered is contrary to the domestic law of Equatoriana, it will not be unenforceable.
42. While an arbitral tribunal is empowered to ‘stay’ an arbitration proceeding in case of pending
paralle criminal, court, or arbitration proceedings, it is not obliged to do so under any law or
practice in any jurisdiction [Swiss Federal SC, 2010]. On the contrary, there is a legal presumption
to the effect that arbitration proceedings will move on unless exceptional reasons or circumstances
require a stay [Luka Groselj, p.576].
43. Additionally, Art. 17(1) PCA Rules imposes a responsibility on the Arbitral Tribunal to avoid
unnecessary delay and conduct fair and efficient arbitral proceedings [PCA Rules, Art. 17(1)]. The
language of Art. 17(1) appears to accord considerations of efficiency identical status with
mandatory requirements of equal treatment and due process: the references to “unnecessary delay
and expense” and an “efficient process” are phrased in mandatory terms (“shall”) and are referred
to together with considerations of fairness (“fair and efficient process”) [Born, pp.2314-15].
Additionally, to avoid postponing the Tribunal’s own inquiry, the Tribunal must have evidence
that the objection is so serious that it wishes to avoid the risk of wasting its and the parties’ efforts
[Paulsson, p.115].
44. As of now, the Public Prosecutor appointed to investigate corruption in the NP Development
Program, Ms. Lyndsey Fonseca, has only announced charges in 2 unrelated contracts by Mr. Field,
and that the present contract is merely one of those under investigation [Re. Ex. 2, p.33]. Per
RESPONDENT, the investigation by Ms. Fonseca will not be finalised until the end of 2023 at the
latest [Response, p.31, ¶ 22], and a conviction would not occur before July 2024 at the latest [Response,
p.31, ¶ 23]. Additionally, the decision of the special court can be appealed, which would cause an
additional amount of delay [PO2, p.49, ¶ 47].
45. The uncertain duration of the investigation has to operate in conjunction with the fact that CEO
of the other bidder, Aerial Systems plc., is Ms. Fonseca’s brother-in-law and her son’s fiancé is the
former personal assistant of Mr. Field, Leonida Bourgeois [Re. Ex. 2, p.33]. Upon Mr. Field’s arrest,
Ms. Bourgeois was promoted to become the head of internal investigation at Equatoriana
Geoscience, from which she moved to the office of the new public prosecutor, her mother-in-law
[Id.]. Thus, the investigation is clearly tainted, and its outcomes would be unreliable.
46. In Swiss Timing Ltd. v. Commonwealth Games, in a case involving a criminal proceeding running
parallel to an arbitration, it was held that shutting out arbitration at the initial stage would destroy
the arbitral intent of the parties [Swiss Timing]. If the matter were not referred to arbitration, and
the criminal proceedings were to result in an acquittal it would have the wholly undesirable result
of delaying the arbitration [Id.]. Thus, in case the investigation fails, or the Court acquits Mr. Field,
then this Tribunal will need to proceed with the arbitration. It is much more efficient for to do
this now. Returning to the Tribunal twelve months later would result in both an unjustified delay
and additional expense, which is contrary to Art. 17 and the general ethos of arbitration.
47. The Tribunal is just as competent as any court to rule on whatever objections RESPONDENT may
raise, and can avoid excessive costs by maintaining jurisdiction. RESPONDENT’s dilatory tactics
should not be rewarded by the Equatorianian courts, which already have a bad reputation [PO2,
p.47, ¶ 28]. RESPONDENT’S request to stay or bifurcate the arbitration pending the outcome of the
investigation to be conducted by the Public Prosecutor’s office of Equatoriana should be denied
for four reasons; stay cannot be granted in the present case [A]; the proceedings should not be
bifurcated [B]; RESPONDENT’s concerns regarding the Arbitral Tribunal’s investigative powers
have been exaggerated [C]; and there is no credible allegation of corruption with regard to the
present contract [D].
48. The CLAIMANT submits that: proceeding with the arbitration will save time and money [1];
RESPONDENT has failed to show any of the accepted criteria for a stay [2]; and the parties intended
to arbitrate disputes about contractual validity [3].
[1] Proceeding with the arbitration will save time and money
49. RESPONDENT’s request that the Tribunal stay its proceedings in order to allow the conclusion of
their domestic investigation is untenable, since it presumes that the investigation by Ms. Lyndsey
Fonseca, will lead to a finding of corruption with regards to PSA. A stay would delay the case and
increase its costs, regardless of the outcome of the proceeding and the court. No decision from
Equatoriana’s special court on the question of Mr. Field’s guilt can be expected prior to the July
50. The Tribunal has already taken steps to mitigate RESPONDENT’s concerns by ordering an initial
argument only on the concerns of jurisdiction, stay or bifurcation, and the more abstract questions
raised by 1c and 1d [PO2, p.50, ¶ 52]. By the time the Tribunal hears the oral arguments in this
matter, both parties will have fully presented their arguments on all of the issues. Arbitral
proceedings, “since their outcome is final and binding, typically take less time than a full review”
by the courts [Lew/Mistelis/ Kröll, p.8]. The primacy of efficiency has already been addressed in
preceding submissions. Thus, it is more prudent for the Tribunal to continue the proceedings
without a stay.
[2] RESPONDENT has failed to show any of the accepted criteria for a stay
51. The provision that grants the authority to the Tribunal to stay proceedings in the present case
would be Art. 17 PCA Rules [PCA Rules, Art. 17]. Art. 15(1) UNCITRAL Arbitration Rules, which
is verbatim as Art. 17 PCA Rules, has been referred to as the “heart” of the UNCITRAL
Arbitration Rules [Caron/Caplan/Pellonpää, p.26]. As noted in Methanex Corp., this provision “grants
the Tribunal a broad discretion as to the conduct of this arbitration”, and “is intended to provide
the broadest procedural flexibility within fundamental safeguards, to be applied by the arbitration
tribunal to fit the particular needs of the particular arbitration [Methanex Corp].” The tribunal must
ensure the avoidance of unnecessary delay, as expressly contained in text of Art. 17 PCA Rules
[PCA Rules, Art. 17].
52. It is in the context of this view of Art. 17 PCA Rules that this tribunal must examine the decision
in Cairn Energy, where the Tribunal, in a proceeding under the PCA Rules, provided the factors
that must be considered for a stay to be granted [Cairn Energy].
i. Whether the stay creates an imbalance between the parties, or causes material prejudice
to one of the parties, thus violating their right to equal treatment;
ii. Whether the stay amounts to depriving a party from the right to present its case;
iii. Whether the stay delays the proceedings unreasonably; and
iv. Where the stay is based on the finalization of other pending proceedings, whether the
outcome of the other pending proceedings is material to the outcome of the arbitration
53. There is material prejudice against CLAIMANT. With regards to the first ground, in the present case,
a stay would cause the proceedings to be delayed to the end of 2023 at the earliest [Response, p. 31,
¶23]. CLAIMANT has ordered surveillance equipment specific to RESPONDENT’s needs, and was
fitting the 3 existing drones, to begin delivering the drones on January 15, 2022, until the
moratorium notified was on December 27, 2021 [Cl. Ex. C6, p.17, ¶; Cl. Ex. C2 p.10; Notice, p.5, ¶
8]. Thus, a stay would cause the drones and other equipment to go to waste. The sudden
moratorium, with only 19 days till the delivery date, has clearly caused material prejudice to the
CLAIMANT as they are left with 3 drones specifically designed for use by RESPONDENT [Notice, p.5,
¶ 8]. The said drones also cannot be sold elsewhere without difficulties and significant price
considerations [PO2, p.46, ¶ 24].
54. A stay, if granted, would unreasonable and onerously delay the proceedings by almost 2 years. As
of now, Ms. Lyndsey Fonseca, has only announced charges in 2 unrelated contracts by Mr. Field,
and that the present contract is merely one of those under investigation [Re. Ex. 2, p.33]. The
conviction would not occur before July 2024 at the latest [Response, p.31, ¶ 23]. Additionally, the
decision of the special court can be appealed, which would cause an additional amount of delay
[PO2, p.49, ¶ 47]. RESPONDENT is requesting a stay when the criminal investigation has only just
been initiated. Thus, a stay here would cause unreasonable delay to the arbitral proceedings.
55. The outcome of domestic proceedings is not entirely material. The stay is incumbent on the
ongoing criminal investigation against Mr. Field. However, the materiality of the outcome of the
proceedings is subjective, as the tribunal will conduct their own proceedings and inquiry into
corruption [TSA Spectrum; Fraport AG]. From a procedural perspective, a review of arbitral
decisions suggests that domestic corruption findings or convictions are not binding on arbitral
tribunals [Karkey A.S.; Croatia v. MOL PLC; Glencore A.G.].
56. Thus, considering all the factors provided above, the Tribunal must rule that a stay cannot be
granted in the present case, since it would violate the spirit of preventing “unnecessary delay” as
codified in Art. 17 PCA Rules.
57. RESPONDENT’s request that the Tribunal stay its proceedings contravenes the clear intent of the
parties, as has already been discussed in detail in ¶¶ 5 through 14, Issue I(A) 1.
58. The Tribunal should thus decline complicity with RESPONDENT’s duplicitous request for grant of
stay and rule against granting a stay, since it is more efficient to proceed with the arbitration, a stay
cannot be granted per the Cairn test, and it is the duty and obligation of the tribunal to rule on the
validity of the contract.
59. Bifurcation is a procedural tool with a basic impact on the merits of the dispute. Thus, it is essential
to address whether the Arbitral Tribunal should first address reason and challenge for bifurcation
of the proceedings, or whether the arbitral tribunal has to deal with all possible claims at the same
60. RESPONDENT requests for bifurcating the proceeding only to the extent of invalidity of PSA due
to corruption [PO2, pp.49-50, ¶ 52]. CLAIMANT posits that in the present case, the proceedings
should not be bifurcated as such because: the applicable legal principles and existing arbitral
practice would not lead to such a decision [1]; a bifurcation of the issue of corruption would not
be feasible [2]; bifurcation would go against the tenets of arbitration [3]; and a grant of bifurcation
would be unfair to the CLAIMANT [4].
[1] The applicable legal principles and existing arbitral practice would not lead to
such a decision
61. The power to order a bifurcated schedule is conferred by the general power found in Art. 17
UNCITRAL Rules and is at the Tribunal’s discretion, with fairness and efficiency as guiding factors
[Philip Morris Asia Ltd.]. With respect to issues that contain elements of both substance and
procedure, arbitrators could look to norms synthesized from various cases and awards, even if the
Arbitral Tribunal is not bound by previous decisions [Vojtěch Trapl].
62. Recently, tribunals in hearings administered by the PCA Rules have more frequently deferred the
decision whether to bifurcate until receipt of substantive submissions by the parties [Daly, p.85, ¶
5.64]. In one instance, a tribunal denied RESPONDENT’s request to bifurcate the proceedings
because it would have had to investigate the full set of facts to decide on the issue of jurisdiction,
which meant that bifurcation would not “appear . . . to be the most efficient and time-saving way
to structure the proceedings [Id., ¶ 5.63].” In the present case, a determination of bifurcation has
anyway necessitated an inquiry on the part of the Tribunal into the merits of whether there was
any corruption, as is also addressed by the CLAIMANT in Issue II (D). Thus, since in any case the
Tribunal would have to hear the merits of the corruption claim, it would only be practicable to not
bifurcate the proceedings.
63. Bifurcation entails splitting the arguments in a case into two phases, which are typically either (1)
jurisdiction and liability, or (2) liability and damages [Woods/Ros/Guillet/Wilson]. In the present
case, RESPONDENT has proposed a bifurcation request which would only extend to the question
of the invalidity of the contract due to corruption [PO2, p.50, ¶ 52]. Considering the pervasiveness
of corruption concerns throughout the dispute, its bearings on the jurisdiction and on the validity
of PSA, RESPONDENT’s request for bifurcation thus cannot be given effect.
64. The tribunal’s decision will usually depend on whether the objection is a self-contained knowledge
of the underlying facts (in which case, bifurcation may well be ordered), or a question that is linked
to the merits and facts of the case [Gran Colombia]. Per the RESPONDENT, the arbitration agreement
stands invalid due to the contract being obtained by corruption [Response, p.30, ¶ 20]. An inquiry
into the jurisdiction of the Tribunal would also entail an inquiry into the question whether the
contract was obtained by corruption or not. This is an issue related to the merits of the case. Thus,
the Tribunal will have to deal with the merits to establish jurisdiction as there is closely interlink in
the merits and jurisdictional issues of the case.
65. It is established that if an arbitral tribunal does not have jurisdiction over an issue, then it cannot
proceed to issue an award on the merits of that issue [Santacroce, p.539; McErlaine/Allsop;
Calamita/Sardinha, p.44; McDermott Int’l; PacifiCare; Fung Sang]. As corruption also pertains to the
jurisdiction, any request of bifurcation would lead the Tribunal to establish complete jurisdiction
only after hearing certain aspects of merits. Any ruling on merits rendered in the first phase goes
against logic and general practice. If the Tribunal later finds out that it does not have jurisdiction
due to corruption, all the prior proceedings of jurisdiction and substance will be rendered futile.
66. When issues are entwined to the extent that they cannot be unraveled from each other, a
bifurcation would only result in the facts being pleaded twice [Greenwood, p110; Redfern/Hunter II,
p.363]. The issues in the present case cannot be argued in vacuum of each other. The same set of
facts apply to all the issues. The Parties will have to make full submissions to the Tribunal on the
facts of the dispute which will likely be repeated in the bifurcated phases of Arbitral Proceedings.
67. For all these reasons, Bifurcation of the issue of invalidity of PSA due to corruption would not be
feasible.
68. By requesting bifurcation, RESPONDENT seeks for the Tribunal to rely on the outcome of the
domestic judicial proceedings dealing with corruption charges, the decision on which cannot be
expected before July 2024 [Response ¶24]. Pertinently, the verdict so delivered would not be
conclusive since it would be from a first instance court. One of the parties will most likely resort
to challenging it by way of appeal before higher courts of law. Any other decision, let alone a
decision at the first instance, cannot guide the Tribunal in determining issues pertaining to
corruption in any definitive manner. The Tribunal will have to investigate independently in any
event unless it agrees to bifurcate the proceedings until the parties exhaust all appeals and are left
with a final decision on matters of corruption.
69. Thus, the Tribunal would be better served by rejecting bifurcation at the outset to conduct its own
investigation in the matters of corruption that affect PSA [Woods/Ros/Guillet/Wilson; Hart-
70. After bifurcation, a tribunal will render a partial award in relation to the first phase. If this award
is challenged at the court of the seat, it will be truly unfair as a successful party will see itself fighting
on two fronts [Kinnear/ Bjorklund/ Hannaford, p.1135; Greenwood, p.111; S.D. Myers]. Moreover, the
second phase of the proceedings may be jeopardized due to a challenge on the partial award given
after first phase [Greenwood, p.111]. If partial award rendered in the present case, is challenged by
RESPONDENT, it will be expensive and distracting for CLAIMANT. CLAIMANT will have to defend
itself not only in the arbitral proceedings but also in court.
71. Further problems will be caused when the witnesses may need to be called twice [Greenwood, p.110;
Monichino]. As any adverse credit findings in the first phase will compromise the latter phase of the
proceedings [Id.]. The characters associated with the issues of misrepresentation and corruption
are the same. Bifurcation would lead to a situation where all the witnesses will have to be called
twice. Any prejudice created against the witnesses in the first phase will compromise the second
phase of the proceedings. Therefore, the Tribunal must not bifurcate the proceedings as it would
be injustice to CLAIMANT.
72. RESPONDENT’s primary concern with regards to the continuation of proceedings is that “Unlike
the Arbitral Tribunal, the public prosecutor has broad investigative powers which extend also to
third parties [Response, p.30, ¶ 23].” However, the same is not normally viewed as a bar to the fair
determination of claims in arbitration [Baizeau/Hayes].
73. Additionally, there is little reason why a tribunal would not be able to unearth the truth relating to
bribery allegations any less ably than it does with other allegations that parties vigorously contest
[Gary Born]. Thus, RESPONDENT’s concerns in this regard are essentially building a mountain out
of a molehill.
74. These concerns, which are limited to the third-party investigative powers of an Arbitral Tribunal,
can be addressed by Art. 27 DAL [PO1, p.43, ¶ 3], which provides that the arbitral tribunal may
request assistance in taking evidence from a competent court of the State by themselves or on the
request of one or more of the parties [UNCITRAL, Art. 27; Vibroflotation; Satinder Singh].
75. It is well established that the arbitral tribunal frequently lacks the power to enforce decisions for
production of evidence and rely on local courts to issue orders in this regard [Binder, p.388]. The
basic proposition of RESPONDENT’s argument thus falls, since they can request, with the approval
of the Tribunal, that evidence be collected from the necessary third parties.
76. In the present case, in case an order is issued by the courts of Danubia requiring taking of evidence
from Equatorianian individuals under Art. 27 DAL, such as Mr. Field, Equatoriana is bound by a
duty to assist the courts in that endeavour, per Art. 37(5) UNCAC. The provision creates a duty
on the part of one State to encourage persons within their State who can provide substantial
assistance towards the investigation of an offence under the convention by another State.
[UNCAC, Art. 37(5)]. Such persons are usually encouraged through mitigation of punishment or
providing of immunity from prosecution [UNCAC, Art. 37(2)-37(3)]. This provision is especially
critical with respect to complex wrongs such as transnational bribery or laundering of proceeds of
bribery, particularly when several actors are involved [Landwehr, p.378].
77. Equatoriana is a signatory of the UNCAC [PO2, p.43, ¶ 3], and as such, would at least be motivated
to assist the investigation as needed. Thus, the concerns with regards to the investigative powers
of the Arbitral Tribunal have been exaggerated.
PRESENT CONTRACT
78. Under both the PCA Rules and the Model Law, each party shall have the burden of supporting its
claim or defense [PCA Rules, Art. 27; UNCITRAL Art 24.1]. As RESPONDENT alleges that
CLAIMANT’s cover agreement with a third party was tainted by bribery, RESPONDENT has the
burden of proving CLAIMANT has committed the alleged corruption [Vladislav Kim; EDF].
79. Additionally, RESPONDENT must satisfy a high evidentiary standard [Micula v. Romania (II); South
American Silver], as most legal systems impose a strict standard of proof for cases involving
allegations of bribery such as Clear & Convincing Evidence [Westinghouse], Irrefutable Evidence as
followed by ICSID tribunals, or the slightly lower standard of Balance of Probabilities or
circumstantial evidence [Glencore A.G.]. CLAIMANT submits that in the present case, RESPONDENT
has failed to even provide a credible allegation of corruption let alone prove it.
80. CLAIMANT submits that in any case, there is no credible allegation of corruption regarding the
present contract because charges brought up against Mr. Field do not relate to the present contract
[i]; the alterations in the scope of the contract have been explained by CLAIMANT [ii]; and the
Public Prosecutor Office and Ms. Fonseca cannot be relied upon to conduct an objective
investigation [iii].
[1] Charges brought up against Mr. Field do not relate to the present contract
81. CLAIMANT submits that so far, there is not even a credible allegation that PSA is obtained by
corruption. RESPONDENT’s CEO, Ms. Wilhelmina Queen, in her letter of termination cites that
there is a “considerable likelihood that the Contract had been obtained by corruption [Cl. Ex. C8,
p.20].” Ms. Queen herself states that there is no proof yet as to the payment of any bribes in relation
to this contract. She merely suspects that such proof will emerge in the course of ongoing
investigations [Cl. Ex. C8, p.20].
82. It is pertinent to note here that CLAIMANT has also reviewed all the payments made from their
accounts to RESPONDENT’s from the date of the invitation to tender until two months after the
contract conclusion and found no suspicious payments [Cl. Ex. C3, p.14, ¶ 11].
[2] The alterations in the scope of the contract have been explained by CLAIMANT
83. The primary reason cited by RESPONDENT to bring up the question of illegality of the present
contract is that the scope of the contract was drastically altered during the final stages of
negotiation. The reasons for these changes have been well-explained by CLAIMANT. Due to the
insolvency of another customer which led to the cancellation of a partly paid order, CLAIMANT
was able to deliver the first 3 drones at very favourable conditions [Notice, p.5, ¶ 5; PO2, p.46, ¶ 25].
Additionally, the three other drones had optional front payload bay which would provide
RESPONDENT with the flexibility to employ additional surveillance equipment. This will be useful
for RESPONDENT as 40% of RESPONDENT’s missions were expected to require drones with an
optional payload bay to employ additional surveillance equipment [PO2, p.44, ¶ 8].
84. The increase in the maintenance period was also explained as being based on the negotiations
considering the expected life of the drones and the favourable conditions provided by CLAIMANT
[Cl. Ex. C6, p.17, PO2, p.47, ¶ 26].
85. Based on CLAIMANT’s internal calculations, a gain of 1.5 million EUR is added to the price of each
drone. But in the present case, even after the increase in the scope of the contract, the entire
additional gain to CLAIMANT under the present arrangement was a mere 1.8 million EUR [PO2,
p.47, ¶ 27]. Given the contract with a value of over 44 million EUR, the meagre profits derived do
[3] The Public Prosecution Office and Ms. Fonseca cannot be relied upon to
conduct an objective investigation
86. It is noteworthy that the newly appointed head of the public prosecution office himself has been
a leading figure in the Liberal Party until his appointment, and has strongly criticized the NP
Development Program since its inception. [Letter by Langweiler to Arbitral Tribunal, p.40]
87. Furthermore, the objectivity of Ms. Fonseca, the specially-appointed prosecutor, and her staff is
also to be questioned. As reported by The Citizen, Ms. Fonseca’s brother-in-law is the CEO of
the other successful bidder, Aerial Systems plc. [Re. Ex. 2, p.33] Therefore, the Tribunal must
exercise its powers to determine its own facts and not rely upon the findings of the Special Public
Prosecutor. Additionally, the statements of Ms. Bourgeois cannot be relied upon given her
relationship with Ms. Fonseca [PO2, p.49, ¶ 43]. Therefore, her statements add no credibility to
the allegations of corruption.
88. It is thus submitted that RESPONDENT’s request to stay or bifurcate the arbitration pending the
outcome of the domestic investigation must to be denied.
ARGUMENTS ON SUBSTANCE
89. The CISG applies to contracts of sale of goods between parties whose places of business are in
different contracting states [CISG, Art. 1(1)(a)]. CLAIMANT’S place of business is in Mediterraneo
[Notice, p.4, ¶ 1] and RESPONDENT is based in Equatoriana [Response, p.27, ¶ 3]. Both states are
contracting states of the CISG [PO1, p.43, ¶ 3]. Further, the parties have agreed that the applicable
law of the contract is the law of Equatoriana [Cl. Ex. C2, p.10]. Equatoriana has not declared any
reservations under Art. 92 CISG [PO2, p.49, ¶ 48]. Thus, PSA falls within the sphere of application
of the CISG.
90. RESPONDENT claims that PSA is not governed by the CISG upon the application of Art. 2(e)
CISG [Response, p.31, ¶ 26]. It may also claim that the drones are classified as aircrafts under
Equatoriana’s domestic law [Re. Ex. 5, p.36]. However, CLAIMANT submits that PSA is indeed
governed by the CISG, under which, only objects which are primarily intended to serve the
function of air transport are to be regarded as aircrafts [Schlechtriem/Schwenzer, p.247]. Contrary to
RESPONDENT’S suggestions, the Kestrel Eye 2010 drones are not aircrafts and the sales transaction
falls within the sphere of application of the CISG. The drones were not intended or destined to
transport cargo or humans [A]. Moreover, there was no need to register them as aircrafts under
Equatoriana’s domestic laws [B].
91. RESPONDENT may claim that the drones could potentially be used as aircrafts. However, the
intended use of objects as well as the purpose of transactions is an important consideration to
determine whether they are excluded under Art. 2(e) CISG [1]. The drones do not qualify as
aircrafts since they were manufactured to be used principally for surveillance and exploration
purposes and the parties understood the same [2].
92. All objects capable of flight cannot be indiscriminately excluded from the CISG’s sphere of
application. The envisaged function of objects is the criterion to determine their nature under Art.
2(e) CISG [Ferrari, ¶ 42]. Moreover, the purpose of the transaction is pertinent for interpretation
under Art. 2(e) [Djakhongir] since objects may be sold for purposes other than those for which they
were manufactured. Thus, objects must be destined for air transport to be regarded as aircrafts
[Schlechtriem/Schwenzer, p.254].
[2] Kestrel Eye 2010 drones were meant to function as surveillance devices
93. The Kestrel Eye 2010 drones cannot be regarded as aircrafts because they were not meant to carry
out the function of transport. They were manufactured with a view to conduct surveillance [i];
and the Parties intended to employ them for the same [ii].
94. The drones were neither capable of carrying humans nor intended to deliver cargo [PO2, p.44, ¶
9]. Their primary purpose was to facilitate surveillance. This can be demonstrated as follows.
95. First, the drones have been engineered at higher costs to provide greater flight stability that serves
surveillance purposes [PO2, p.44, ¶ 9]. The drones which are manufactured simply to move cargo
have much larger payload bays than Kestrel Eye 2010 and are 30% cheaper since they do not
ensure such great flight stability [Id.]. The use of Kestrel Eye 2010 drones to transport cargo is not
commercially sensible given their small payload carrying capacity and costlier flight stability
features which are not required for standard delivery of cargo [Id.; Re. Ex. 5, p.36]. Moreover,
surveillance equipment occupies the entire weight and volume capacity of the central payload bay
and would need to be removed to make room for cargo [Id.]. The impracticality of employing the
drones for transportation indicates that it is built for surveillance.
96. Second, Kestrel Eye 2010 has primarily been used to carry surveillance equipment instead of cargo.
It was used to carry cargo only in rare instances of emergency, when no other means of delivering
small crucial equipment bits or medicine to remote locations was at hand on short notice [PO2,
p.44, ¶ 9]. The deployment of Kestrel Eye 2010 to transport cargo instead of employing
surveillance equipment was always a last resort in urgent cases when cheaper alternatives that are
usually available for such tasks were absent [PO2, pp.44, 46, ¶ 9, 22]. This further demonstrates
that their principal purpose since inception, has always been surveillance.
97. Crucially, at least 3 Kestrel Eye 2010 drones were not even capable of transporting cargo, let alone
intended for the same. The first 3 drones which CLAIMANT had initially planned to sell to another
customer were agreed to be sold to RESPONDENT equipped with geological surveillance equipment
[Cl. Ex. C2, p.10; Notice, p.5, ¶ 8]. However, these 3 drones did not have the optional front payload
bay [PO2, p.44, ¶ 8]. This meant that they had hardly any capacity left to carry cargo [PO2, p.45, ¶
10] since the surveillance equipment takes up the entire capacity of the central payload bay, which
is the only other available bay [PO2, p.44, ¶ 9]. Therefore, at the very least, the first 3 drones are
not aircrafts within the meaning of Art. 2(e) CISG because of their utter inability to serve the
function of air transport.
98. Even the versions equipped with the optional front bay are suited only to surveillance because of
low load carrying capacity and higher costs, and RESPONDENT also intended to employ them for
that very purpose. PSA and the Call for Tender indicates that the primary intention behind
acquiring drones is to collect data by way of geological surveillance equipment [Cl. Ex. C2, p.10].
The versions with the optional front payload bay were intended to be used only in 40% of the
missions to employ additional surveillance equipment [PO2, p.44, ¶ 8; Cl. Ex. C1, p.9]. Therefore,
Kestrel Eye 2010 drones were not intended to transport cargo on any mission.
99. RESPONDENT agreed to increase the volume of the transaction in light of the highly favorable price
and a potential additional use of Kestrel Eye 2010 [Cl. Ex. C2, p.10]. It may claim that the additional
use was to use the drones to transport cargo which would otherwise be transported through
cheaper alternatives in cases of emergency. However, RESPONDENT was aware that such cases
would be truly exceptional and involve greater financial costs, to be resorted to only in urgent
situations when cheaper means of transport are unavailable [PO2, p.44, ¶ 9; PO2, p.44, ¶ 22]. This
demonstrates that RESPONDENT did not purchase the drones to transport cargo. The possibility
of such use does not alter the principal intention behind manufacturing and buying the drones, or
their primary function. Urgent cases of emergency where all other means of transport are absent
are not likely to occur, and mere possibility of such situations arising and the drones being used to
transport cargo in such cases cannot affect the nature of the drones.
100. Kestrel Eye 2010 drones were manufactured to serve as surveillance devices and were
consequently bestowed with greater flight stability features, smaller payload capacity, and higher
prices than drones meant for air transport. The Parties understood this and agreed that these
drones would be deployed principally for surveillance [PO2, p.46, ¶ 22]. They cannot be classified
as aircrafts merely because it was possible to use them to transport cargo with great inconvenience
when such possibility runs counter to their intended purpose.
101. Like with most other objects, drones can potentially be used for purposes other than for which
they are engineered and purchased. However, in light of their primary function as envisaged by
the manufacturer [PO2, p.44, ¶ 9] and the intention of RESPONDENT to use them primarily for
surveillance [Cl. Ex. C2, p.10], it is apparent that Kestrel Eye 2010 was not destined for air
transport. Thus, the drones cannot be excluded from the sphere of application of the CISG.
102. Aircrafts are excluded from the scope of the CISG under Art. 2(e) because they are potentially
subject to special registration rules under domestic legal systems [Schwenzer/Fountoulakis, p.40].
There are varying standards across jurisdictions when it comes to requirements for registration of
aircrafts [CISG Draft Commentary, Art. 2]. This was a contributing factor in aircrafts being excluded
from the CISG’s scope of application for two reasons: to eliminate uncertainties regarding which
objects would be subject to the CISG in light of differing domestic rules of registration, and the
fact that the relevant place of registration and the law governing it might not be known at the time
of the sale [Id.].
103. However, the Parties knew the relevant place of registration, and therefore the law governing the
registration. Per Art. 10 of Equatoriana’s Aviation Safety Act, the drones are not subject to
registration with the aircraft registry because they were purchased and operated by a state-owned
entity [Re. Ex. 5, p.36]. Consequently, the transfer of ownership of Kestrel Eye 2010 was perfected
even without the drones being registered as aircrafts. RESPONDENT merely requested visible
product numbers to be marked on the drones’ tails to identify them if they interfered with other
forms of aerial traffic [Re. Ex. 1, p.32]. The same did not amount to registration [PO2, p.44, ¶ 8].
Therefore, the drones cannot be qualified as aircrafts since they are not required to be registered
as such, and thus fall within the scope of the CISG.
104. In case PSA is governed by the CISG, RESPONDENT cannot rely on Art. 3.2.5 ICCA of
Equatoriana to avoid the contract as the same is not applicable in the instant case [A]. Even if the
Tribunal finds that Art. 3.2.5 ICCA is applicable, RESPONDENT cannot rely on the same as there
was no misrepresentation thereunder [B].
105. Art. 35 CISG provides remedy for breach of contract by a party where there is non-conformity of
goods. While Art. 3.2.5 ICCA provides the domestic law remedy for fraud, it is pre-empted by the
CISG in the present case. The domestic law of Equatoriana cannot be relied upon by
RESPONDENT to claim a remedy for fraud as RESPONDENT’s claim of the drones not meeting the
technical qualifications as agreed upon by the parties [Response, p.29, ¶ 17] does not involve an
interest arising independently of contractual claims [1], is not based on a fraudulent intention on
behalf of CLAIMANT [2], and provides the same remedy as is allowed for breach of contract under
CISG [3]. Therefore, allowing such a claim would result in dilution of the purpose and authority
of the CISG [4].
106. Where the parties are contracting states of the CISG, the latter exclusively governs factual
situations involving issues regarding conformity of the goods with the characteristics or qualities
agreed upon by the parties [Art. 35, CISG; Kröll/Mistelis/Viscasillas, p.537]. The drones not meeting
the qualities and characteristics agreed upon by the parties would at most, raise contractual issues
of non-conformity under the CISG [i]. Further, where RESPONDENT does not rely on any facts
beyond lack of conformity, fraud cannot be claimed [ii].
107. The CISG has adopted a unitary notion of defective performance. Any difference between what
the parties have contracted for and what the seller provides falls within the concept of lack of
conformity within the Convention [De Luca, p.175]. In the present case, RESPONDENT released a
Call for Tender for four state-of-the-art drones for the collection of geological and geophysical
data [Cl. Ex. C1, p.9]. CLAIMANT responded to the same with a bid that was accepted by
RESPONDENT, and the parties entered into a contract wherein they clearly expressed the agreed-
upon specifications of the goods [Cl. Ex. C2, pp.10, 11]. After the negotiations, the resultant
contract specified the obligations of the Seller under Art. 2 [Cl. Ex. C2, p.10]. By virtue of this
provision, PSA obliges the seller to supply 6 of its newest model of Kestrel Eye 2010 drones and
such drones must be equipped with state-of-the-art geological surveillance equipment features [Id.].
If there is any failure on part of CLAIMANT in supplying such drones, it would imply that there is
a difference between what the parties contracted for and what the seller provides and thus, the
factual situation would constitute lack of conformity.
108. Thus, this factual situation would at best raise issues of non-conformity which are regulated
exclusively by Art. 35 CISG. Art. 35 obliges the seller to deliver those goods which are conforming
to the characteristics explicitly established in the contract [CISG, Art. 35(1); Schlechtriem/Schwnezer,
Art. 35 ¶ 6]. The term ‘Quality’ as used in Art. 35 covers physical conditions of the goods which
are agreed upon or justifiably expected [Kröll/Mistelis/Viscasillas, p.492]. Thus, questions relating to
conformity of the drones with characteristics such as “latest” or “equipped with state-of-the-art
technology” as agreed upon in the Contract must be exclusively governed by Art. 35.
109. Hence, in light of the facts stated, RESPONDENT can, at best, rely on Art. 35 CISG to raise
questions as to the conformity of the drones with the specifications agreed upon by the parties
and stipulated in the Contract.
110. Where it is accepted that remedies under domestic law for the seller’s fraud or deceit are not
excluded, it is essential that parties’ claims are based on special circumstances above and beyond
the mere lack of conformity of the goods [Schlechtriem/Schwenzer, Art. 35, ¶ 51;
Kröll/Mistelis/Viscasillas, p.537].
111. Fraud is “extraneous” to the contract where it concerns matters which do not relate to the quality
or characteristics of the goods for which the parties contracted or the performance under the
Contract [Kaloti Enters]. Thus, when the only fraud alleged is that the party was not sincere when
it promised to perform under the contract, the fraud-based cause of action is duplicative of a
breach of contract claim [Mañas; Gorman v. Fowkes; Did-it.com]. While RESPONDENT claims that
CLAIMANT misrepresented the quality of drones as they were neither “state of the art” nor their
“newest model” [Response, p.29, ¶ 17], these matters relate to the quality or characteristics of the
drones which the parties agreed upon in PSA [Cl. Ex. C2, p.10]. The factual situation concerns
performance under the contract and is not extraneous to the quality of the goods the parties
112. Since RESPONDENT’s claims for fraud are not based on special circumstances above and beyond
the mere lack of conformity of the goods, these claims cannot be raised.
113. Domestic law remedies for innocent and negligent misrepresentation relating to matters governed
by the CISG, such as the features of the goods, are pre-empted by the CISG [Schroeter, pp.578, 582-
583]. It can thus be inferred that it is only the element of fraudulent intention that the CISG does
not seek to govern. The present case, however, involves no fraudulent intention on the part of
CLAIMANT, thus preventing the domestic law remedy from pre-empting the remedy as provided
under the CISG.
114. At the time of conclusion of the contract, Kestrel Eye 2010 was Drone Eye plc’s top model
available in the market [Notice, p.5, Para 9]. While CLAIMANT was developing and testing Hawk Eye
2020 at the time, there was no certainty as to when it would have been available for sale. The
Contract was concluded on December 1, 2020 [Cl. Ex. C2, p.12] and even as late as February 2021,
at the time of the airshow, CLAIMANT had not received the patent for its new product, only
receiving it in July 2022 [PO2, p.45, ¶ 15]. As such, till 2022, CLAIMANT could not have been certain
about when it could have sold Hawk Eye 2020. Therefore, it was not commercially viable for
CLAIMANT to release Hawk Eye 2020 as its newest model or the current state-of-the-art drones
available for RESPONDENT’s purpose at the time.
115. Moreover, during the stage of testing and development, the technology behind Hawk Eye 2020
constituted CLAIMANT’s trade secret. It was a commercially valuable secret, the details of which
were known to only a limited group of people within the company [Trade Secrets, WIPO], which
gave Drone Eye plc an opportunity to use the technology that it developed, to obtain an economic
advantage over its competitors whenever it was released [Carla Walter, p.274]. CLAIMANT was thus
under no obligation to disclose it to RESPONDENT during their negotiations.
116. Hence, there was no fraudulent intention involved on the part of CLAIMANT to warrant holding a
domestic law claim of fraud as maintainable.
117. Given the facts of a case, if the CISG provides solutions that are exhaustive and functionally
equivalent to the otherwise applicable domestic remedies, the CISG pre-empts recourse to those
domestic remedies. Thus, if an issue is one of "validity" as autonomously defined under the CISG,
and therefore (potentially) excluded from its scope of application on the grounds of Art. 4, the
applicable domestic law remedy available to the parties must be identified [Franco Ferrari, p.67]. If
the CISG provides solutions that are functionally equivalent to those available to the parties under
the applicable domestic law, it will pre-empt the corresponding domestic remedies and defences
[Id]. In the present case, PSA is governed by the Law of Equatoriana [Cl. Ex. C2, p.12]. Art. 3.2.5
ICCA provides the relevant domestic law remedy for fraud, allowing a party to avoid the contract
if it was induced to enter into it by fraud [UPICC, Art. 3.2.5].
118. Any failure of the goods to conform to the agreed-upon description will constitute a breach of the
seller’s obligations and result in breach of contract [Delchi], which may allow avoidance [CISG,
Arts. 46-52]. To avoid the contract altogether, RESPONDENT would need to establish that the
alleged non-conformity constitutes fundamental breach of contract under Art. 49 CISG. Hence,
the CISG provides the same remedy as Art. 3.2.5 ICCA. The same is thus pre-empted by the CISG
and RESPONDENT cannot rely on the non-harmonised law of Equatoriana to seek the same remedy
for the same factual situation.
119. Given that the CISG provides solutions that are exhaustive and functionally equivalent to the
remedies under the applicable domestic law, the CISG pre-empts recourse to these remedies.
Therefore, the Tribunal should not allow RESPONDENT to claim remedies under the same.
120. The expressly stated goal behind the CISG is to develop and enforce a uniform international
contract law in order to remove legal barriers in international trade [Preamble, CISG; Art. 7(1),
CISG]. This clearly indicates the intent of the Contracting States to have the treaty pre-empt state
law causes of action. [Schroeter, pp.554-555; Warren Khoo, pp.46-47]. Any recourse to local, non-
unified law involves the risk of upsetting the balance of rights and obligations of international
buyers and sellers that has been laid down in the CISG [Schroeter, p.553], and would subject parties
to the very same ambiguities that the CISG was designed to avoid [Geneva Pharms.].
121. RESPONDENT’s misrepresentation claim only asserts a breach of duties created by the contract
itself, as it relates to the specifications of the drones as agreed between the parties, and raises the
question of the drones not conforming to those specifications. A claim for misrepresentation of
such facts as already addressed by the non-conformity provisions of the CISG must therefore be
subsumed and trumped by the CISG [Schlechtriem, p.33]. Allowing a claim of such nature would
enable a party to avoid the treaty altogether by disguising CISG disputes as local claims.
122. Furthermore, under the CISG, the requirement of proving “fundamental breach” in order to avoid
a contract is intended to make the burdensome unwinding of contracts an ultima ratio (remedy of
last resort) [Schroeter, pp.553-554]. Thus, if a misrepresentation claim under state law, allowing
avoidance of contract without having to prove fundamental breach, is held maintainable, it would
result in the violation of the doctrine of fundamental breach of contract. Thus, RESPONDENT’s
misrepresentation claim under Art. 3.2.5 ICCA must not be allowed so as to preserve the purpose
and authority of the CISG.
123. Hence, RESPONDENT cannot rely on Art. 3.2.5 ICCA to avoid the contract as it is not applicable
in the instant factual situation.
124. Even if the Tribunal finds that Art. 3.2.5 ICCA is applicable in the present factual situation,
RESPONDENT cannot rely on it to avoid the contract. The ingredients of fraud under Art. 3.2.5 are
not fulfilled since: there was no fraudulent representation [1], or fraudulent non-disclosure by
CLAIMANT [2]. CLAIMANT had no intent to defraud RESPONDENT into error [3]; and gained no
advantage to RESPONDENT’s detriment [4].
125. It is submitted that there was no fraudulent representation by CLAIMANT about the quality of the
drones [i] and in any case, CLAIMANT’s interpretation of the term ‘state-of-the-art’ should be
adopted by virtue of the rule of contra proferentem [ii].
126. Fraud under Art. 3.2.5 ICCA can be committed by a positive representation of a false fact, either
expressly or by implication [Vogenauer, pp.499-500]. It is argued that CLAIMANT made no false
representation to RESPONDENT with respect to the nature or quality of the drones.
127. As emphasised earlier, Kestrel Eye 2010 constituted CLAIMANT’s top/latest model at the time of
conclusion of the contract [Notice, p.5, ¶ 9]. It was CLAIMANT’s state-of-the-art drone specifically
engineered for surveillance purposes [PO2, p.44, ¶ 9], corresponding to RESPONDENT’s specific
requirement of collecting geological and geophysical data in the Northern part of Equatoriana as
notified in the Call for Tender [Cl. Ex. C1, p.9]. Mr. Bluntschli merely reinforced these facts in his
email to Mr. Field [Re. Ex. 4, p.35]. At the time of contract conclusion, Hawk Eye 2020 was still
in the development and testing phase and, in fact, the patents for the same had not even been
applied for until after the airshow the following year [PO2, p.45, ¶ 14-15]. Thus, Hawk Eye 2020
could not have been presented as CLAIMANT’s top model at the time.
128. It may also be noted that the Call for Tender document stated that only offers submitted in
accordance with the detailed conditions described therein would be considered [Cl. Ex. C1, p.9].
RESPONDENT was satisfied with CLAIMANT’s offer and products, had likely conducted due
diligence, and had assured itself of the compliance of Kestrel Eye 2010 with its requirements. In
particular, RESPONDENT had selected CLAIMANT’s bid after likely comparison of the Kestrel Eye
2010 with other products available in the market, including drones that were similar to the Hawk
Eye 2020 [PO2, p.45, ¶ 14]. Clearly, RESPONDENT considered Kestrel Eye 2010 to be a state-of-
the-art drone for its purpose, making its subsequent claim of misrepresentation unfounded and
merely an attempt to facilitate wrongful avoidance of the contract.
129. The contra proferentem rule is a rule of interpretation which holds that a party which drafted or
otherwise supplied a contractual term may be responsible for its formulation and should bear the
risk of the ambiguity of that particular term [Yalim, pp.79-96]. It has been noted that when
arbitrators use the contract to determine a dispute, in principle, clauses should be interpreted contra
proferentem [Lew/Mistelis/Kröll, ¶ 18-85]. This rule has been applied as a general principle of law [ICC
3779; ICC 7110]. In the instant case, the Tribunal must apply the rule for interpretation of the term
‘state-of-the-art’ as used in Art. 2 PSA, which states that the seller must supply the buyer with
Kestrel Eye 2010 drones, equipped with ‘state-of-the-art geological surveillance features’ and that
the seller must provide maintenance service after delivery of the ‘respective state-of-the-art UAS’
[Cl. Ex. C2, pp.10, 11].
130. The Rule is also found within the provisions of CISG which by virtue of Article 8(2) places the
burden to communicate clearly on the party which prepares a communication or drafts a contract
[Op. 13, CISG AC]. According to this rule of interpretation, where both parties’ interpretation of
a contractual term makes sense to a certain extent but if contract terms supplied by one party are
unclear, an interpretation against that party shall be adopted [Cysteine case; Automobile case]. The term
‘state-of-the-art’ is a subjective term. CLAIMANT interpreted it to mean latest drones it had released
in the market at time of the tender which suited the purpose of surveillance and date collection
[Notice, P.5, ¶ 9]. As opposed to this, RESPONDENT interpreted the term to mean the latest drones
present in the market at time of delivery. Since both the interpretations make sense to a certain
extent, and RESPONDENT drafted PSA [Cl. Ex. C7, p.19, ¶ 18], the rule of contra proferentem should
131. Therefore, there was no fraudulent representation by CLAIMANT to constitute fraud under Art.
3.2.5 ICCA.
132. Fraud may occur by a failure on the part of one party to disclose the true state of affairs to the
other [Vogenauer, p.500]. Art. 3.2.5 ICCA imposes a duty to disclose as per “reasonable commercial
standards of fair dealing”, which means a general duty for a party to act in good faith and fair
dealing in international trade [Off Comm., pp.19, 20].
133. In the present case, it was generally known in the market that CLAIMANT was developing a new
drone using technology acquired through the acquisition of Drone-Aircraft. RESPONDENT,
however, at no point inquired from CLAIMANT as to whether it was developing a new drone during
the time of negotiations, or if such drone might be better suited for its purpose [PO2, p.45, ¶ 15].
In deciding the extent of the duty of disclosure, the degree of difficulty with which the other party
can obtain information is a relevant factor [Vogenauer, p.501]. Here, RESPONDENT could have
discovered the factum of development of a new drone through reasonable due-diligence and
therefore, is not entitled to claim a breach of CLAIMANT’s duty of disclosure.
134. On the other hand, the information that CLAIMANT was specifically developing the Hawk Eye
2020 based on aerodynamic life technology and was in the testing phase of the same, was a
commercially valuable trade secret [Trade Secrets, WIPO] of CLAIMANT at the time of contract
conclusion. The text of the CISG casts no duty on a party to disclose such business secrets to the
other party. Even if the Tribunal finds that CISG does not govern the contract in the instant case,
Art. 3.2.5 ICCA also does not impose such far-reaching disclosure obligations on parties.
135. The judgment of the Equatorianian Supreme Court that is sought to be relied upon by
RESPONDENT to impose such far-reaching disclosure obligations on CLAIMANT was delivered in
an entirely domestic setting, involving a dispute between two domestic parties under the domestic
Contract Act [Response, p.29, ¶ 18]. In Equatoriana, while a special legislation, i.e., the ICCA, exists
to govern international commercial contracts, the relevant contract law for domestic contracts is
the Contract Act. The interpretation of fraudulent non-disclosure given by the Court in its
judgment is not relevant in a case such as ours, involving an international contract and being
governed by a different legislation altogether. It is a principle of statutory interpretation that a
statute must be interpreted in light of its object [Breyer J]. The object of the two legislations is
different in that one seeks to regulate contracts between domestic parties, while the other regulates
contracts with foreign parties in an international setting. The State may not impose the same
obligations on foreign private entities as it does on its domestic parties without sufficient basis in
law. In any case, it is not for the Tribunal to extend the interpretation of one statute to another.
Thus, CLAIMANT was not subject to the far-reaching and unjustified disclosure obligation as may
be suggested by RESPONDENT and as such, there was no fraudulent non-disclosure by CLAIMANT.
136. Conduct is only fraudulent if “it is intended to lead the other party into error [Off Comm., p.107]”.
137. In the instant case, there was no intention on the part of CLAIMANT to make RESPONDENT rely
on its allegedly fraudulent conduct in order to induce the latter to enter into the contract. No other
bidders participating in the tender offered drones with better technology than the Kestrel Eye
2010 [PO2, p.45, ¶ 14]. Thus, any allegedly fraudulent representations on the part of CLAIMANT as
to the quality or features of its Kestrel Eye 2010 would not have had the effect of wrongfully
presenting their offer as a more attractive one than others.
138. More significantly, in light of RESPONDENT’s aim to collect geological and geophysical data [Cl.
Ex. C1, p.9], and the fact that the Hawk Eye 2020 was not available for sale at the time of contract
conclusion, CLAIMANT held the genuine belief that Kestrel Eye 2010 constituted a “state-of-the-
art” drone for RESPONDENT in terms of the Call for Tender. RESPONDENT selected CLAIMANT’s
bid after likely examination of the product and its comparison with other products existing in the
market. RESPONDENT’s conduct clearly indicated that it found Kestrel Eye 2010 to be a state-of-
the-art drone suitable for its purpose. Thus, it cannot be said that RESPONDENT was lead into any
error, and no fraudulent intent can be attributed to CLAIMANT.
139. Under Art. 3.2.5 ICCA, intentional conduct amounts to fraud if it allows the party committing
fraud to gain an advantage to the detriment of the other party [Off Comm., p.107]. CLAIMANT gained
no “advantage to the detriment of the other party” [ICCA, Art. 3.2.5] by leading RESPONDENT
into “error”. An analysis of the available information regarding the cost of the drones, the value at
which the 4 drones were to be sold along with the 2-year maintenance service package, and the
value for the 6 drones and the 4-year maintenance service package that was ultimately agreed
between the parties, reveals that the entire additional gain to CLAIMANT under the present
arrangement was a mere 1.8 million EUR [PO2, p.47, ¶ 27]. The gain does not even amount to 5%
of the total contract value of over 44 million EUR and, thus, cannot be reasonably considered as
a gain sufficient to prove fraudulent conduct.
140. Moreover, no detriment was caused to RESPONDENT by any conduct of CLAIMANT. Kestrel Eye
2010 is specifically engineered for surveillance purposes and possesses various qualities (such as
flight stability, compact size, etc.). This makes it appropriate for RESPONDENT’s requirements of
collecting geological and geophysical data in the difficult terrain of Northern Equatoriana [PO2,
pp.44-45, ¶ 9; Cl. Ex. C4, p.15]. Furthermore, given that the area is not well-developed and lacks
infrastructure [Notice, p.5, ¶¶ 4-5], RESPONDENT would need to incur extra expenditure to operate
Hawk Eye since the landing strips would have been farther away from the area of usage [PO2, p.45,
¶ 16]. However, RESPONDENT aimed to make use of the revenue collected by way of exploration
of northern part of Equatoriana to fund such infrastructural development in the first place. Thus,
the monetary constraints and the fact that the airfield could only be developed at a considerable
distance from the area of usage [PO2, p.45, ¶ 16] makes the Hawk Eye 2020 a more expensive
option for RESPONDENT [Cl. Ex. C3, p.14, ¶ 9]. Hence, usage of Kestrel Eye 2010 would cause no
detriment to RESPONDENT.
141. Also, no other bidders, including Aerial Systems plc, participating in the tender process had offered
to RESPONDENT technology like Hawk Eye 2020 [PO2, p.45, ¶14]. RESPONDENT made a conscious
choice to employ CLAIMANT to provide it with Kestrel Eye 2010, despite the fact that it could have
reasonably known that drones similar to Hawk Eye 2020 already existed in the market. As such, it
can be reasonably assumed that CLAIMANT’s bid constituted one of the two most attractive bids
[Cl. Ex. C1, p.9] received by RESPONDENT and the decision to conclude the contract was an
informed decision following long negotiations between the two parties. Given the facts of the case,
it cannot be said that the contract was to the detriment of RESPONDENT.
142. Therefore, it cannot be said that CLAIMANT gained an advantage to the detriment of RESPONDENT
under the contract, as required by Art. 3.2.5 ICCA.
143. Hence, RESPONDENT cannot rely on Art. 3.2.5 ICCA to avoid the contract as no case of
misrepresentation is made out thereunder.
RELIEF SOUGHT
In light of the arguments presented in this memorandum, CLAIMANT respectfully requests the
tribunal to declare
CLAIMANT reserves the right to amend the relief sought as may be required.
CERTIFICATE OF INDEPENDENCE
It is hereby confirmed that this memorandum was not prepared by anyone other than the people
who have signed their names below:
As submitted respectfully on behalf of CLAIMANT, Drone Eye plc. on December 8, 2022, by the
abovementioned.