Note: V = (3.60m) (3.60m) (0.
100m) (1)
Concrete: Use Class A Mixture V = 1.296m3
Cement Mortar: Use 10x20x40 CHB TOTAL VOLUME OF CONCRETE
Cement Plaster: Use 20mm thickness of
VT = 1.20m3 + 0.66m3 + 1.00m3 + 0.66m3 +
plaster; both side of the wall. 0.90m3 + 1.296m3
Metal Reinforcement: VT = 5.72m3
F1/FTB-1/G1: Use 16db for bend
Column Main reinforcement: Use 12db QUANTITY FOR CONCRETE
for hook length
Ties & Stirrups: Use 6db for hook Using Class A Mixture:
Cement = 5.72m3 x 9.0 = 51.5 say 52 bags
Sand = 5.72m3 x 0.5 = 2.86 say 3.00m3
CONCRETE
Gravel = 5.72m3 x 1.0 = 5.72 say 6.00m3
FOOTINGS
CONCRETE HOLLOW BLOCKS
Footing 1 (F1) (CHB)
V=LxW xHxn
V = (1.00m) (1.00m) (0.30m) (4) AREA OF WALLS
V = 1.20m3
Front Elevation
FOOTING TIE BEAMS A = L x H – Adoor
A = (3.00m – 0.250m) (2.70m) – (2.10m x
Footing Tie Beam 1 (FTB-1) 0.90m)
V=LxW xHxn A = 5.535m2
V = (3.00m – 0.250m) (0.200m) (0.300m) (4)
V = 0.66m3 Right Side Elevation
A = L x H – Awindow
COLUMNS A = (3.00m – 0.250m) (2.70m) – (1.00m x
1.00m)
Column 1 (C1) A = 6.425m2
Height of C1 = 0.30m + 2.70m + 0.30m +
1.00m – 0.30m Left Side Elevation
H = 4.00m A = L x H – Awindow
A = (3.00m – 0.250m) (2.70m) – (1.00m x
V=LxW xHxn 1.00m)
V = (0.250m) (0.250m) (4.00m) (4) A = 6.425m2
V = 1.00m3
Rear Elevation
BEAMS A=LxH
A = (3.00m – 0.250m) (2.70m)
Girder 1 (G1) A = 7.425m2
V=LxBxDxn
V = (3.00m – 0.250m) (0.200m) (0.300m) (4) TOTAL AREA OF WALLS
V = 0.66m3
AT = 5.535m2 + 6.425m2 + 6.425m2 + 7.425m2
SLAB ON FILL AT = 25.81m2
V=LxW xtxn QUANTITY OF CHB
V = (3.00m) (3.00m) (0.100m) (1)
V = 0.90m3 N = AT x 12.5
N = 25.81m2 x 12.5
SLAB N = 322.625 say 323pcs of CHB
V=LxW xtxn
CEMENT MORTAR For 9.0m length steel bar:
9.00
N= = 7.20 ≈ 7pcs
Using 10 x 20 x 40 CHB and Class A Mixture: 1.25
Cement = 25.81m2 x 0.981 waste = 9.00m − 7(1.25m) = 0.25m
= 25.32 say 26 bags
Sand = 25.81m2 x 0.0545 Choose 7.5m length steel bars (no waste).
= 1.41m3 say 2.00m3
Number of 7.5m length steel bars
56
CEMENT PLASTER N= = 9.33 say 10pcs
6
Use Class A Mixture and 20mm thickness of Therefore, use 10pcs – 12mm diameter –
plaster. Assume both side of the wall is to be 7.5m length steel bars for footing
plastered. reinforcement.
A = 25.81m2 x 2
A = 51.62m2 COLUMNS
Cement = 51.62m2 x 0.360 Main Reinforcement:
= 18.58 say 19 bags Hook Length = 12db = 12(16mm) = 192mm say
Sand = 51.62m2 x 0.020 200mm
= 1.03 say 1.50m3
L = 0.45m + (1.00m – 0.075m) + 0.30m +
REINFORCING BARS 2.70m + 0.30m + 0.20m
L = 4.875m
FOOTINGS
Number of vertical bars in one column
Length of one cut bar: N = 4pcs
Development Length/Bend, Ld = 16db
Ld = 16 (12mm) = 192mm say 200mm Total no. of vertical bars
N = 4pcs x 4 columns
L = LT – Cc + Ld N = 16 pcs
L = 1.00m – 2 (0.075m) + 2 (0.200)
L = 1.25m Choose economical bar size
For 6m length steel bar:
Number of cut bars in one footing 6.00
N= = 1.23 ≈ 1pc
1.00 4.875
N= = 6.67 say 7pcs bothways waste = 6.00m − 4.875m = 1.125m
0.150
N = 7pcs x 2 = 14pcs
For 7.5m length steel bar:
7.50
Total no. of cut bars N= = 1.54 ≈ 1pc
N = 14pcs x 4 footings 4.875
waste = 7.50m − 4.875m = 2.625m
N = 56 pcs
For 9.0m length steel bar:
Choose economical bar size 9.00
N= = 1.85 ≈ 1pc
4.875
For 6m length steel bar: waste = 9.00m − 4.875m = 4.125m
6.00
N= = 4.80 ≈ 4pcs
1.25 Choose 6.0m length steel bars (least waste).
waste = 6.00m − 4(1.25m) = 1.00m
Number of 6.0m length steel bars
For 7.5m length steel bar: 16
N= = 16pcs
7.50 1
N= = 6pcs
1.25
waste = 7.50m − 6(1.25m) = 0 Therefore, use 16pcs–16mm diameter–6.0m
length steel bars for column reinforcement.
LATERAL TIES N = 16pcs
Length of one lateral tie Choose economical bar size
Hook Length = 6db = 6(10mm) = 60mm For 6m length steel bar:
Concrete Cover = 40cm 6.00
N= = 1.63 ≈ 1pc
3.69
L = 4 (0.25m – 0.04m – 0.04m) + 2 (0.06mm) waste = 6.00m − 3.69m = 2.31m
L = 0.80m
For 7.5m length steel bar:
Number of lateral ties in one column 7.50
N= = 2.03 ≈ 2pcs
N = 39 pcs 3.69
waste = 7.50m − 2(3.69m) = 0.12m
Total no. of lateral ties
N = 39 pcs x 4 columns For 9.0m length steel bar:
N = 156 pcs 9.00
N= = 2.44 ≈ 2pcs
3.69
Choose economical bar size waste = 9.00m − 2(3.69m) = 1.62m
For 6m length steel bar:
6.00 Choose 7.5m length steel bars (least waste).
N= = 7.50 ≈ 7pcs
0.80
waste = 6.00m − 7(0.80m) = 0.40m Number of 7.5m length steel bars
16
N= = 8pcs
For 7.5m length steel bar: 2
7.50
N= = 9.38 ≈ 9pcs Therefore, use 8pcs – 16mm diameter – 7.5m
0.80
waste = 7.50m − 9(0.80m) = 0.30m length steel bars for footing tie beam
reinforcement.
For 9.0m length steel bar:
9.00 STIRRUPS FOR FOOTING TIE BEAM
N= = 11.25 ≈ 11pcs
0.80
waste = 9.00m − 11(0.80m) = 0.20m Length of one stirrup
Hook Length = 6db = 6(10mm) = 60mm
Choose 9.0m length steel bars (least waste).
L = 2 (0.20m – 0.04m – 0.04m) + 2 (0.30m –
Number of 9.0m length steel bars 0.04m – 0.04m) + 2 (0.06mm)
156 L = 0.80m
N= = 14.18 ≈ 15pcs
11
Number of stirrups in one footing tie beam
Therefore, use 15pcs–10mm diameter–9.0m N = 2 + 10 + 8 = 20 pcs
length steel bars for lateral ties.
Total no. of stirrups
FOOTING TIE BEAMS N = 20 pcs x 4 footing tie beams
N = 80 pcs
Main Reinforcement
Length of one cut bar Choose economical bar size
Development Length/Bend, Ld = 16db For 6m length steel bar:
Ld = 16 (16mm) = 256mm say 260mm 6.00
N= = 7.50 ≈ 7pcs
0.80
L = LT – Cc + Ld waste = 6.00m − 7(0.80m) = 0.40m
L = 3.25m – 2 (0.040m) + 2 (0.260)
L = 3.69m For 7.5m length steel bar:
7.50
Number of cut bars in one footing tie beam N= = 9.38 ≈ 9pcs
0.80
N = 4pcs waste = 7.50m − 9(0.80m) = 0.30m
Total no. of cut bars
N = 4pcs x 4 footing tie beams
For 9.0m length steel bar: STIRRUPS FOR BEAM
9.00
N= = 11.25 ≈ 11pcs
0.80 Length of one stirrup
waste = 9.00m − 11(0.80m) = 0.20m Hook Length = 6db = 6(10mm) = 60mm
Concrete Cover = 40cm
Choose 9.0m length steel bars (least waste).
L = 2 (0.20m – 0.04m – 0.04m) + 2 (0.30m –
Number of 9.0m length steel bars 0.04m – 0.04m) + 2 (0.06mm)
80 L = 0.80m
N= = 7.27 ≈ 8pcs
11
Number of stirrups in one beam
Therefore, use 8pcs–10mm diameter–9.0m N = 2 + 10 + 8 = 20 pcs
length steel bars for stirrups.
Total no. of stirrups
BEAMS N = 20 pcs x 4 beams
N = 80 pcs
Main Reinforcement
Length of one cut bar Choose economical bar size
Development Length/Bend, Ld = 16db For 6m length steel bar:
Ld = 16 (16mm) = 256mm say 260mm 6.00
N= = 7.50 ≈ 7pcs
0.80
L = LT – Cc + Ld waste = 6.00m − 7(0.80m) = 0.40m
L = 3.25m – 2 (0.040m) + 2 (0.260)
L = 3.69m For 7.5m length steel bar:
7.50
Number of cut bars in one beam N= = 9.38 ≈ 9pcs
0.80
N = 4pcs waste = 7.50m − 9(0.80m) = 0.30m
Total no. of cut bars For 9.0m length steel bar:
N = 4pcs x 4 beams 9.00
N = 16pcs N= = 11.25 ≈ 11pcs
0.80
waste = 9.00m − 11(0.80m) = 0.20m
Choose economical bar size
For 6m length steel bar: Choose 9.0m length steel bars (least waste).
6.00
N= = 1.63 ≈ 1pc
3.69 Number of 9.0m length steel bars
waste = 6.00m − 3.69m = 2.31m 80
N= = 7.27 ≈ 8pcs
11
For 7.5m length steel bar:
7.50 Therefore, use 8pcs–10mm diameter–9.0m
N= = 2.03 ≈ 2pcs
3.69 length steel bars for stirrups.
waste = 7.50m − 2(3.69m) = 0.12m
SLAB ON FILL
For 9.0m length steel bar:
9.00
N= = 2.44 ≈ 2pcs Length of one cut bar
3.69 L = 3.00m
waste = 9.00m − 2(3.69m) = 1.62m
No. of cut bars in x-direction
Choose 7.5m length steel bars (least waste).
3.00m
N= + 1 = 11pcs
Number of 7.5m length steel bars 0.300m
16
N= = 8pcs No. of cut bars in y-direction
2
3.00m
N= + 1 = 11pcs
Therefore, use 8pcs – 16mm diameter – 7.5m 0.300m
length steel bars for footing tie beam
Total no. of cut bars for slab on fill
reinforcement.
N = 11 + 11 = 22pcs
Choose economical bar size Number of 7.5m length steel bars
For 6m length steel bar: 50
6.00 N= = 25pcs
2
N= = 2pcs
3.00
waste = 6.00m − 2(3.00m) = 0 Therefore, use 25pcs – 10mm diameter –
7.5m length steel bars for slab reinforcement.
For 7.5m length steel bar:
7.50 TIE WIRES
N= = 2.50 ≈ 2pcs
3.00
waste = 7.50m − 2(3.00m) = 1.50m
FOOTING
For 9.0m length steel bar:
Number of Intersections
9.00
N= = 3pcs N = 7 x 7 = 49 intersections
3.00
waste = 9.00m − 3(3.00m) = 0
Total number of tie wires
N = 49 x 4 footings = 196 tie wires
Choose 9.0m length steel bars.
Total length of tie wires (1 tie wire = 0.30m)
Number of 9.0m length steel bars
22 L = 196 x 0.30m = 58.8m
N= = 7.33 ≈ 8pcs
3
Therefore, use 8pcs – 10mm diameter – 9.0m Convert meters to kilograms
length steel bars for slab reinforcement. 58.8m / 53m = 1.11 kgs
SLAB COLUMN
Length of one cut bar Number of Intersections
L = 3.60m N = 4 x 39 = 156 intersections
No. of cut bars in x-direction Total number of tie wires
3.60m N = 156 x 4 column = 624 tie wires
N= + 1 = 25pcs
0.150m
Total length of tie wires (1 tie wire = 0.30m)
No. of cut bars in y-direction L = 624 x 0.30m = 187.20m
3.60m
N= + 1 = 25pcs Convert meters to kilograms
0.150m
187.20m / 53m = 3.53 kgs
Total no. of cut bars for slab on fill
N = 25 + 25 = 50pcs FOOTING TIE BEAM
Choose economical bar size Number of Intersections
For 6m length steel bar: N = 4 x 20 = 80 intersections
6.00
N= = 1.67 ≈ 1pc Total number of tie wires
3.60
waste = 6.00m − 3.60m = 2.40m N = 80 x 4 footing tie beams = 320 tie wires
For 7.5m length steel bar: Total length of tie wires (1 tie wire = 0.30m)
7.50 L = 320 x 0.30m = 96m
N= = 2.08 ≈ 2pcs
3.60
waste = 7.50m − 2(3.60m) = 0.30m Convert meters to kilograms
96m / 53m = 1.81 kgs
For 9.0m length steel bar:
9.00 BEAM
N= = 2.50 ≈ 2pcs
3.60
waste = 9.00m − 2(3.60m) = 1.80m Number of Intersections
N = 4 x 20 = 80 intersections
Choose 7.5m length steel bars.
Total number of tie wires SUMMARY OF QUANTITIES
N = 80 x 4 footing tie beams = 320 tie wires
Cement = 97 bags
Total length of tie wires (1 tie wire = 0.30m) Sand = 6.5 m3
L = 320 x 0.30m = 96m Gravel = 6.0 m3
CHB = 323 pcs
Convert meters to kilograms
96m / 53m = 1.81 kgs Reinforcement Bars:
25pcs – 10mm diameter – 7.5m
SLAB ON FILL 39pcs – 10mm diameter – 9.0m
10pcs – 12mm diameter – 7.5m
Number of Intersections 16pcs – 16mm diameter – 6.0m
N = 11 x 11 = 121 intersections 16pcs – 16mm diameter – 7.5m
Total length of tie wires (1 tie wire = 0.30m) Tie Wires = 13 kgs
L = 121 x 0.30m = 36.3m
Convert meters to kilograms
36.3m / 53m = 0.68 kgs
SLAB
Number of Intersections
N = 25 x 25 = 625 intersections
Total length of tie wires (1 tie wire = 0.30m)
L = 625 x 0.30m = 187.5m
Convert meters to kilograms
187.5m / 53m = 3.54 kgs
Total weight of tie wires.
WT = 1.11 + 3.53 +1.81 +1.81 +0.68 + 3.54
WT = 12.48 say 13 kgs