100% found this document useful (2 votes)
1K views6 pages

Sample Estimate Computations

The document provides calculations for determining material quantities for a construction project. It includes volumes and areas for various building components as well as reinforcement quantities. The summary includes concrete, rebar, hollow block, and mortar quantities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views6 pages

Sample Estimate Computations

The document provides calculations for determining material quantities for a construction project. It includes volumes and areas for various building components as well as reinforcement quantities. The summary includes concrete, rebar, hollow block, and mortar quantities.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Note: V = (3.60m) (3.60m) (0.

100m) (1)
Concrete: Use Class A Mixture V = 1.296m3
Cement Mortar: Use 10x20x40 CHB TOTAL VOLUME OF CONCRETE
Cement Plaster: Use 20mm thickness of
VT = 1.20m3 + 0.66m3 + 1.00m3 + 0.66m3 +
plaster; both side of the wall. 0.90m3 + 1.296m3
Metal Reinforcement: VT = 5.72m3
F1/FTB-1/G1: Use 16db for bend
Column Main reinforcement: Use 12db QUANTITY FOR CONCRETE
for hook length
Ties & Stirrups: Use 6db for hook Using Class A Mixture:
Cement = 5.72m3 x 9.0 = 51.5 say 52 bags
Sand = 5.72m3 x 0.5 = 2.86 say 3.00m3
CONCRETE
Gravel = 5.72m3 x 1.0 = 5.72 say 6.00m3

FOOTINGS
CONCRETE HOLLOW BLOCKS
Footing 1 (F1) (CHB)
V=LxW xHxn
V = (1.00m) (1.00m) (0.30m) (4) AREA OF WALLS
V = 1.20m3
Front Elevation
FOOTING TIE BEAMS A = L x H – Adoor
A = (3.00m – 0.250m) (2.70m) – (2.10m x
Footing Tie Beam 1 (FTB-1) 0.90m)
V=LxW xHxn A = 5.535m2
V = (3.00m – 0.250m) (0.200m) (0.300m) (4)
V = 0.66m3 Right Side Elevation
A = L x H – Awindow
COLUMNS A = (3.00m – 0.250m) (2.70m) – (1.00m x
1.00m)
Column 1 (C1) A = 6.425m2
Height of C1 = 0.30m + 2.70m + 0.30m +
1.00m – 0.30m Left Side Elevation
H = 4.00m A = L x H – Awindow
A = (3.00m – 0.250m) (2.70m) – (1.00m x
V=LxW xHxn 1.00m)
V = (0.250m) (0.250m) (4.00m) (4) A = 6.425m2
V = 1.00m3
Rear Elevation
BEAMS A=LxH
A = (3.00m – 0.250m) (2.70m)
Girder 1 (G1) A = 7.425m2
V=LxBxDxn
V = (3.00m – 0.250m) (0.200m) (0.300m) (4) TOTAL AREA OF WALLS
V = 0.66m3
AT = 5.535m2 + 6.425m2 + 6.425m2 + 7.425m2
SLAB ON FILL AT = 25.81m2

V=LxW xtxn QUANTITY OF CHB


V = (3.00m) (3.00m) (0.100m) (1)
V = 0.90m3 N = AT x 12.5
N = 25.81m2 x 12.5
SLAB N = 322.625 say 323pcs of CHB

V=LxW xtxn
CEMENT MORTAR For 9.0m length steel bar:
9.00
N= = 7.20 ≈ 7pcs
Using 10 x 20 x 40 CHB and Class A Mixture: 1.25
Cement = 25.81m2 x 0.981 waste = 9.00m − 7(1.25m) = 0.25m
= 25.32 say 26 bags
Sand = 25.81m2 x 0.0545 Choose 7.5m length steel bars (no waste).
= 1.41m3 say 2.00m3
Number of 7.5m length steel bars
56
CEMENT PLASTER N= = 9.33 say 10pcs
6

Use Class A Mixture and 20mm thickness of Therefore, use 10pcs – 12mm diameter –
plaster. Assume both side of the wall is to be 7.5m length steel bars for footing
plastered. reinforcement.
A = 25.81m2 x 2
A = 51.62m2 COLUMNS

Cement = 51.62m2 x 0.360 Main Reinforcement:


= 18.58 say 19 bags Hook Length = 12db = 12(16mm) = 192mm say
Sand = 51.62m2 x 0.020 200mm
= 1.03 say 1.50m3
L = 0.45m + (1.00m – 0.075m) + 0.30m +
REINFORCING BARS 2.70m + 0.30m + 0.20m
L = 4.875m
FOOTINGS
Number of vertical bars in one column
Length of one cut bar: N = 4pcs
Development Length/Bend, Ld = 16db
Ld = 16 (12mm) = 192mm say 200mm Total no. of vertical bars
N = 4pcs x 4 columns
L = LT – Cc + Ld N = 16 pcs
L = 1.00m – 2 (0.075m) + 2 (0.200)
L = 1.25m Choose economical bar size
For 6m length steel bar:
Number of cut bars in one footing 6.00
N= = 1.23 ≈ 1pc
1.00 4.875
N= = 6.67 say 7pcs bothways waste = 6.00m − 4.875m = 1.125m
0.150
N = 7pcs x 2 = 14pcs
For 7.5m length steel bar:
7.50
Total no. of cut bars N= = 1.54 ≈ 1pc
N = 14pcs x 4 footings 4.875
waste = 7.50m − 4.875m = 2.625m
N = 56 pcs
For 9.0m length steel bar:
Choose economical bar size 9.00
N= = 1.85 ≈ 1pc
4.875
For 6m length steel bar: waste = 9.00m − 4.875m = 4.125m
6.00
N= = 4.80 ≈ 4pcs
1.25 Choose 6.0m length steel bars (least waste).
waste = 6.00m − 4(1.25m) = 1.00m
Number of 6.0m length steel bars
For 7.5m length steel bar: 16
N= = 16pcs
7.50 1
N= = 6pcs
1.25
waste = 7.50m − 6(1.25m) = 0 Therefore, use 16pcs–16mm diameter–6.0m
length steel bars for column reinforcement.
LATERAL TIES N = 16pcs

Length of one lateral tie Choose economical bar size


Hook Length = 6db = 6(10mm) = 60mm For 6m length steel bar:
Concrete Cover = 40cm 6.00
N= = 1.63 ≈ 1pc
3.69
L = 4 (0.25m – 0.04m – 0.04m) + 2 (0.06mm) waste = 6.00m − 3.69m = 2.31m
L = 0.80m
For 7.5m length steel bar:
Number of lateral ties in one column 7.50
N= = 2.03 ≈ 2pcs
N = 39 pcs 3.69
waste = 7.50m − 2(3.69m) = 0.12m
Total no. of lateral ties
N = 39 pcs x 4 columns For 9.0m length steel bar:
N = 156 pcs 9.00
N= = 2.44 ≈ 2pcs
3.69
Choose economical bar size waste = 9.00m − 2(3.69m) = 1.62m
For 6m length steel bar:
6.00 Choose 7.5m length steel bars (least waste).
N= = 7.50 ≈ 7pcs
0.80
waste = 6.00m − 7(0.80m) = 0.40m Number of 7.5m length steel bars
16
N= = 8pcs
For 7.5m length steel bar: 2
7.50
N= = 9.38 ≈ 9pcs Therefore, use 8pcs – 16mm diameter – 7.5m
0.80
waste = 7.50m − 9(0.80m) = 0.30m length steel bars for footing tie beam
reinforcement.
For 9.0m length steel bar:
9.00 STIRRUPS FOR FOOTING TIE BEAM
N= = 11.25 ≈ 11pcs
0.80
waste = 9.00m − 11(0.80m) = 0.20m Length of one stirrup
Hook Length = 6db = 6(10mm) = 60mm
Choose 9.0m length steel bars (least waste).
L = 2 (0.20m – 0.04m – 0.04m) + 2 (0.30m –
Number of 9.0m length steel bars 0.04m – 0.04m) + 2 (0.06mm)
156 L = 0.80m
N= = 14.18 ≈ 15pcs
11
Number of stirrups in one footing tie beam
Therefore, use 15pcs–10mm diameter–9.0m N = 2 + 10 + 8 = 20 pcs
length steel bars for lateral ties.
Total no. of stirrups
FOOTING TIE BEAMS N = 20 pcs x 4 footing tie beams
N = 80 pcs
Main Reinforcement
Length of one cut bar Choose economical bar size
Development Length/Bend, Ld = 16db For 6m length steel bar:
Ld = 16 (16mm) = 256mm say 260mm 6.00
N= = 7.50 ≈ 7pcs
0.80
L = LT – Cc + Ld waste = 6.00m − 7(0.80m) = 0.40m
L = 3.25m – 2 (0.040m) + 2 (0.260)
L = 3.69m For 7.5m length steel bar:
7.50
Number of cut bars in one footing tie beam N= = 9.38 ≈ 9pcs
0.80
N = 4pcs waste = 7.50m − 9(0.80m) = 0.30m

Total no. of cut bars


N = 4pcs x 4 footing tie beams
For 9.0m length steel bar: STIRRUPS FOR BEAM
9.00
N= = 11.25 ≈ 11pcs
0.80 Length of one stirrup
waste = 9.00m − 11(0.80m) = 0.20m Hook Length = 6db = 6(10mm) = 60mm
Concrete Cover = 40cm
Choose 9.0m length steel bars (least waste).
L = 2 (0.20m – 0.04m – 0.04m) + 2 (0.30m –
Number of 9.0m length steel bars 0.04m – 0.04m) + 2 (0.06mm)
80 L = 0.80m
N= = 7.27 ≈ 8pcs
11
Number of stirrups in one beam
Therefore, use 8pcs–10mm diameter–9.0m N = 2 + 10 + 8 = 20 pcs
length steel bars for stirrups.
Total no. of stirrups
BEAMS N = 20 pcs x 4 beams
N = 80 pcs
Main Reinforcement
Length of one cut bar Choose economical bar size
Development Length/Bend, Ld = 16db For 6m length steel bar:
Ld = 16 (16mm) = 256mm say 260mm 6.00
N= = 7.50 ≈ 7pcs
0.80
L = LT – Cc + Ld waste = 6.00m − 7(0.80m) = 0.40m
L = 3.25m – 2 (0.040m) + 2 (0.260)
L = 3.69m For 7.5m length steel bar:
7.50
Number of cut bars in one beam N= = 9.38 ≈ 9pcs
0.80
N = 4pcs waste = 7.50m − 9(0.80m) = 0.30m

Total no. of cut bars For 9.0m length steel bar:


N = 4pcs x 4 beams 9.00
N = 16pcs N= = 11.25 ≈ 11pcs
0.80
waste = 9.00m − 11(0.80m) = 0.20m
Choose economical bar size
For 6m length steel bar: Choose 9.0m length steel bars (least waste).
6.00
N= = 1.63 ≈ 1pc
3.69 Number of 9.0m length steel bars
waste = 6.00m − 3.69m = 2.31m 80
N= = 7.27 ≈ 8pcs
11
For 7.5m length steel bar:
7.50 Therefore, use 8pcs–10mm diameter–9.0m
N= = 2.03 ≈ 2pcs
3.69 length steel bars for stirrups.
waste = 7.50m − 2(3.69m) = 0.12m
SLAB ON FILL
For 9.0m length steel bar:
9.00
N= = 2.44 ≈ 2pcs Length of one cut bar
3.69 L = 3.00m
waste = 9.00m − 2(3.69m) = 1.62m
No. of cut bars in x-direction
Choose 7.5m length steel bars (least waste).
3.00m
N= + 1 = 11pcs
Number of 7.5m length steel bars 0.300m
16
N= = 8pcs No. of cut bars in y-direction
2
3.00m
N= + 1 = 11pcs
Therefore, use 8pcs – 16mm diameter – 7.5m 0.300m
length steel bars for footing tie beam
Total no. of cut bars for slab on fill
reinforcement.
N = 11 + 11 = 22pcs
Choose economical bar size Number of 7.5m length steel bars
For 6m length steel bar: 50
6.00 N= = 25pcs
2
N= = 2pcs
3.00
waste = 6.00m − 2(3.00m) = 0 Therefore, use 25pcs – 10mm diameter –
7.5m length steel bars for slab reinforcement.
For 7.5m length steel bar:
7.50 TIE WIRES
N= = 2.50 ≈ 2pcs
3.00
waste = 7.50m − 2(3.00m) = 1.50m
FOOTING
For 9.0m length steel bar:
Number of Intersections
9.00
N= = 3pcs N = 7 x 7 = 49 intersections
3.00
waste = 9.00m − 3(3.00m) = 0
Total number of tie wires
N = 49 x 4 footings = 196 tie wires
Choose 9.0m length steel bars.
Total length of tie wires (1 tie wire = 0.30m)
Number of 9.0m length steel bars
22 L = 196 x 0.30m = 58.8m
N= = 7.33 ≈ 8pcs
3
Therefore, use 8pcs – 10mm diameter – 9.0m Convert meters to kilograms
length steel bars for slab reinforcement. 58.8m / 53m = 1.11 kgs

SLAB COLUMN

Length of one cut bar Number of Intersections


L = 3.60m N = 4 x 39 = 156 intersections

No. of cut bars in x-direction Total number of tie wires


3.60m N = 156 x 4 column = 624 tie wires
N= + 1 = 25pcs
0.150m
Total length of tie wires (1 tie wire = 0.30m)
No. of cut bars in y-direction L = 624 x 0.30m = 187.20m
3.60m
N= + 1 = 25pcs Convert meters to kilograms
0.150m
187.20m / 53m = 3.53 kgs
Total no. of cut bars for slab on fill
N = 25 + 25 = 50pcs FOOTING TIE BEAM

Choose economical bar size Number of Intersections


For 6m length steel bar: N = 4 x 20 = 80 intersections
6.00
N= = 1.67 ≈ 1pc Total number of tie wires
3.60
waste = 6.00m − 3.60m = 2.40m N = 80 x 4 footing tie beams = 320 tie wires

For 7.5m length steel bar: Total length of tie wires (1 tie wire = 0.30m)
7.50 L = 320 x 0.30m = 96m
N= = 2.08 ≈ 2pcs
3.60
waste = 7.50m − 2(3.60m) = 0.30m Convert meters to kilograms
96m / 53m = 1.81 kgs
For 9.0m length steel bar:
9.00 BEAM
N= = 2.50 ≈ 2pcs
3.60
waste = 9.00m − 2(3.60m) = 1.80m Number of Intersections
N = 4 x 20 = 80 intersections
Choose 7.5m length steel bars.
Total number of tie wires SUMMARY OF QUANTITIES
N = 80 x 4 footing tie beams = 320 tie wires
Cement = 97 bags
Total length of tie wires (1 tie wire = 0.30m) Sand = 6.5 m3
L = 320 x 0.30m = 96m Gravel = 6.0 m3
CHB = 323 pcs
Convert meters to kilograms
96m / 53m = 1.81 kgs Reinforcement Bars:
25pcs – 10mm diameter – 7.5m
SLAB ON FILL 39pcs – 10mm diameter – 9.0m
10pcs – 12mm diameter – 7.5m
Number of Intersections 16pcs – 16mm diameter – 6.0m
N = 11 x 11 = 121 intersections 16pcs – 16mm diameter – 7.5m

Total length of tie wires (1 tie wire = 0.30m) Tie Wires = 13 kgs
L = 121 x 0.30m = 36.3m

Convert meters to kilograms


36.3m / 53m = 0.68 kgs

SLAB

Number of Intersections
N = 25 x 25 = 625 intersections

Total length of tie wires (1 tie wire = 0.30m)


L = 625 x 0.30m = 187.5m

Convert meters to kilograms


187.5m / 53m = 3.54 kgs

Total weight of tie wires.


WT = 1.11 + 3.53 +1.81 +1.81 +0.68 + 3.54
WT = 12.48 say 13 kgs