Itp & Check List For Fence
Itp & Check List For Fence
Contract No.
20230329004 SCOPE OF WORK Horticulture Works for Propagation and Cultivation of plants - production nursery for King Salman Park H - Hold Point R - Review Point
Discipline Civil ITP Reference No. Rev. No. 00 Date 8-May-23 W - Witness Point S - Surveillance
As per design
Pre-Qualification Prior to start of work Approved PQD
1.1 Document Review drawing and Project Engineer's Approval N/A H R R R R N/A
Submittal Approval (100%) Submittal
Specification
Approved drawings
As per design
Material Submittal Prior to start of work Compliance with Approved MAR
1.2 Document Review drawings and Project N/A H R R R R N/A
Approval (MAR) (100%) Specification / Submittal
Specification
Engineer's Approval
As per design
drawings.
Engineeris Approval
Manufacturer / Prior to start of work Approved Shop
1.3 Shop Drawings Document Review on latest revision of N/A H R R R R N/A
Supplier (100%) drawing
relevant Drawings.
reccomendation and
Project Specification
As per design
drawings. Compliance with the
Manufacturer / Prior to start of work Materal Approval Approved Method
1.4 Method Statement Document Review N/A H R R R R N/A
Supplier (100%) submittal & Statement
reccomendation and Specification
Project Specification
As per Project
As per approved
Materials Receiving Specification / Approved Material
Each delivery Mix Desing /
2.1 Inspection Physical Inspection Approved Material Inspection Request N/A H H W R R N/A
(100%) material submittal/
Submittal/Approved (MIR)
DN
Shop Drawings.
Manufacturer Data
Sheet /
Material / Product Project Specs / Manufacturer Data
Reccomondations /
2.2 Storage and Visual Inspection (100%) Approved MAR / Sheet and N/A H W S S R N/A
Project Specs /
Handling MES / MIR Reccomondations
Weather
Changes/Conditions
3.0 Installation
As per approved
Mock-up IRE for Project Specs / Approved IRE /
construction drawing
3.1 Installation of Chain Visual Inspection Prior to Execution Approved MAR / Checklist / Survey N/A H W W R R N/A
and Project
Link Fence MES / MIR Report
Specification
As per approved As per approved
Setting out and Visual As per approved
drawing / Project Prior to Excavation drawing / Survey
3.2 Excavation Inspection/Survey drawing / Suevey N/A H W R R R N/A
Specification / ITP (100%) Data / Project
Inspection Check Ref.0001 Specification Report
6
Concrete sampling shall be done by an approved independent laboratory.
Slump shall be within the tolerance limit as per approved Concrete Design
8
mix.
12
All Installation shall be completed as per approved Drawing.
Note:
Remarks:
Amran Hossain
Name, Initial 08-05-23 Name, Initial
and Date and Date