The director of Parks, Recreation and Facilities Management is requesting approval to increase the contract with Skidmore, Owings & Merrill from $2,892,633 to $4,272,451 for architectural services on a project. The original fees were based on a construction cost of $24.4 million, but private donations increased the estimated cost to $35.2 million, triggering a fee increase of $973,800 according to the contract. An additional $381,018 in fees and $25,000 in reimbursables were needed after a redesign to reduce costs and stay within the approved budget.

Uploaded by

Jonathan Krause
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
306 views1 page

2023 Architectural Contract 6.16.23

The director of Parks, Recreation and Facilities Management is requesting approval to increase the contract with Skidmore, Owings & Merrill from $2,892,633 to $4,272,451 for architectural services on a project. The original fees were based on a construction cost of $24.4 million, but private donations increased the estimated cost to $35.2 million, triggering a fee increase of $973,800 according to the contract. An additional $381,018 in fees and $25,000 in reimbursables were needed after a redesign to reduce costs and stay within the approved budget.

Uploaded by

Jonathan Krause
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

“…meeting community needs…enhancing quality of life.


PARKS, RECREATION & FACILITIES
MANAGEMENT
Dean R. Gazza, Director
1819 East Witzke Boulevard
Appleton, Wisconsin 54911-8401
(920) 832-5572 FAX (920) 993-3103
Email - [email protected]

TO: Finance Committee

FROM: Dean R. Gazza, Director of Parks, Recreation and Facilities Management

DATE: 6/19/2023

RE: Action Item: Approval of increased contract to Skidmore, Owings & Merrill (SOM)
from $2,892,633 to $4,272,451.

The Request for Proposal by architects required that fees were based on the cost of construction
totaling $24.4 million dollars to ensure all architects provided equal cost proposals and represented
the amount the City of Appleton had allocated towards the project. The City of Appleton’s
allocation increased by $2 million and private donations were estimated at $12 million thus the
architectural fees were increased per the contract by $973,800 to represent the estimated cost of
construction of $35.2 million.

After the initial bids were received it was decided a redesign to get the project within the approved
budget was required. The additional redesign fees totaled $381,018 plus $25,000 in reimbursables.

Overall, the architects’ fees have been adjusted to $4,167,451 and reimbursables total $105,000
totaling a contract amount of $4,272,451.

Please feel free to contact me at 832-5572 with any questions, or by email at


[email protected].