Method Statement For Electrical Works
Method Statement For Electrical Works
1. SCOPE / OBJECTIVES
1. This Method Statement for blockworks defines the sequence and describes the
control procedures to be followed for Electrical Works.
2. REFERENCES
3. RESPONSIBILITIES
1. Construction Manager/Engr. shall study, analyze and schedule all construction
activities with his department to include manpower and equipment line up as well as
other possible resources required for the successful implementation of the
construction work activities.
2. Electrical In-charge shall study and review all necessary documents for the installation
works in his area to include the technical scope of work, specification, bill of
quantities, planned milestone dates and construction procedure in support to his
Electrical Supervisor/Foreman.
3. Electrical In-charge shall study and review all necessary documents for the Cable
Laying and Termination works in his area to include, specifications, bill of quantities
and construction procedures. He shall monitor the availability of materials in
accordance with the schedules and construction analysis.
4. The Electrical Foreman shall be directly responsible for the work supervision at site
installation following all schedules and specific work activities ensuring that the works
are performed in accordance with scope of work and latest approved IFC drawings.
5. Safety Engineer / Supervisor shall be responsible in monitoring safety aspects and
ensuring that the work is done in accordance with the project. He shall discuss to the
workers the characteristics of related materials and status of work area giving
reminders as an additional point to work safely.
Contractor’s Common Facility Project
GNPower Mariveles Energy Center Ltd.Co.
4. PROCEDURE
4.1 Installation of Electrical Conduit Pipe
1. During the course of the installation of the conduit system, procedures for working and
dressing the installation as recommended shall be employed.
2. All bends and sets shall be in accordance with IEE regulation 522-08 formed with the aid
of a helical spring fitted internally, with if necessary, the conduit warmed sufficiently for it
to move without avoidable wall thinning of the out side of the bend.
3. All bends and sets shall be in accordance with IEE regulation 522-08 formed with the aid
of a helical spring fitted internally, with if necessary, the conduit warmed sufficiently for it
to move without avoidable wall thinning of the out side of the bend.
4. Joints between PVC conduit + fittings shall be made with suitable adhesive, but
expansion couplings shall be installed where any length of conduit , inclusive of draw in
boxes etc, exceeds five meters in length.
5. The minimum and maximum sizes of conduit to be employed shall be 20mm and
32mmdiameter respectively, unless otherwise stated in subsequent sections of
the specification.
4.2 Fixing of Electrical Conduit Pipe
1. When conduits are run on shuttering, prior to the laying of concrete insitu, additional
security must be provided near to every box and at intervals of not more than 1.2 meters
by binding short lengths of steel wire, of not less than 2mm diameter twisted around the
conduit and reinforcing steel. The conduits shall be adequately fixed to prevent
excessive movement and damage during the pouring and setting of concrete and shall
be protected from mechanical damage. Check there is no damage before screed /
concrete is poured. Unless otherwise indicated to cast in conduits shall not be less than
30mm.cores to plastered over conduits shall not be less than 5mm.
2. Where conduits are left "open ended" prior to wiring they shall be protected by caps or
plugs to prevent the ingress of building material.
3. All conduits runs must be designed to permit wiring to be readily installed after the
complete erection of the conduits through the available draw-in, accessory and luminary
suspension boxes.
4. Where surface mounted equipment (other than luminaries) is specified, all concealed
conduits shall be terminated and an adaptable box installed recessed into the wall at
every surface mounted equipment position.
5. Where conduits pass through an external wall/roof the conduit box shall be fitted on the
side and after wiring filled with an inert, permanently plastic compound having a high
insulation value.
6. Make provision in conduit and trunking, installation where building expansion joints are
crossed or settlement is likely.
7. Ensure conduits are not concealed until works has been inspected and approved.
Ensure that conduit and fittings buried in concrete or behind plaster are protected
against corrosion or electrolytic action prior to rendering.
5. RESOURCE REQUIREMENTS
1. Manpower
1. Project Engineer
2. Site Engineer
3. Safety Officer
4. Helpers (skilled, semi-skilled)
2. Material
1. Electrical Conduit Pipe
2. Electrical Wire
3. Junction Box
4. Utility Box
5. Lighting Fixtures
Prepared by:
Veronica De Jesus
BQA Construction and Trading