Karnataka Renewable Energy Policy 2009-14
Karnataka Renewable Energy Policy 2009-14
2009-14
To Harness Green, Clean Renewable Energy Sources for Environmental benefits
&
Energy Security
Published by KREDL
PROCEEDINGS OF THE GOVERNMENT OF KARNATAKA
PREAMBLE:
Building on its current strengths and a capacity of 24 Megawatts, Karnataka intends to establish a
dynamic renewable sector with emphasis on different forms of generation-wind, mini hydro, bio mass, co
generation and solar. There is need to have a clear policy framework to provide and sustain efforts in this
direction.
The energy consumption in the State is anticipated to be around 64,000 MU per annum by 2015.
At present, renewable energy sources contribute to about 4600 MU of energy per annum (11.5%) out of the
total 40,000 MU available from various installed capacities. To achieve a 20% share, the renewable energy
sources are required to contribute 12,800 MU by 2014. This necessitates a renewable energy capacity
addition of 6600 MW by 2014. A clear –cut policy is, therefore, essential to regulate and ensure speedy
development of renewable energy.
Till now, the State did not have clearly spelt out policy for development of Renewable Energy.
Karnataka Renewable Energy development Limited (KREDL) is promoting RE projects through
participation of the private sector in wind, mini hydro, bio mass, co generation respectively. Despite
significant achievements, developers have complained of many impediments in the quick resolution of the
projects. Assessed against our potential in Renewable Energy, the State can accomplish more substantial
achievement to make it the number one Renewable Energy State in the Country. The Renewable Energy
Policy at systematic and faster development of Renewable Energy sources to achieve a capacity of 6600
MW by 2014.
On its part, KREDL has attempted to promote Renewable Energy in the State in a number of
ways. These include:
a. Encouraging the private sector to identify and develop small capacity projects in wind, mini
hydro, bio mass, co generation respectively.
b. Create an information network for advancing RE understanding through communication,
education and publicity.
c. Promote emphasis on green energy, harmful effects of global warming and ozone layer depletion.
d. Start demonstration projects to establish cost effectiveness, economic viability and the reliability
of various technologies (eg. Wind Projects at Sogi and mavinhunda).
e. Frequent interactions with developer to ensure capacity additions expeditiously.
f. Promote greater awareness and compliance with energy conservation and energy efficiency issues.
The new Renewable Energy Policy attempts to stimulate addition to capacity generation by a minimum
of 1000 MW each year. It has the following substantial objectives:
The policy proposed contains some key measures to address the constraints and ensure substantial
capacity additions in the next 5 years:
Renewable Energy Development is to be classified as an “Industry”. Land is, therefore, to be
made available to the developers by the Government through allotment by the Commerce and
Industries Department Single Window System. This will obviate the extensive time delays
currently taking place with the developers having to obtain permission for purchasing land
from the Deputy Commissioner of the districts or other modes of purchase.
A Green Energy cess at Rs. 0.05 per unit on commercial and industrial consumers to generate
Rs. 55 crores annually. Out of Rs. 55 crores to be collected as cess, a part will be set aside for
Energy Conservation Fund, part for Renewable Energy Project Financing and strengthening
the evacuation system and the remainder for an integrated information and communication
programme in the State. (Provision for the same has been made in the tariff proposals filed by
the Distribution Companies).
Constitution of a State Level Empowered Committee headed by the Chief Secretary to co-
ordinate departmental issues and clearances in Renewable Energy Projects.
Enforcement of time frame for completion of projects i.e. 3 years from the date of clearances.
In keeping with contemporary requirements and to utilize various environmental credits available,
it is proposed that the KREDL be transformed into a dynamic result oriented entity. With
substantial skill and capacity addition KREDL will actively take up implementation of the RE
Policy including Energy Efficiency, Conservation, Demand Side Management and CDM
activities.
Several consultations were held with stakeholder Associations. The draft RE Policy has
been discussed at various official levels, including the Chief Secretary on 22.10.2009. The draft
policy was circulated among technical experts, financial consultants, Renewable Energy
Developers and Government Departments. The opinions and suggestions offered by various
Departments have been taken care of and they have been incorporated suitably in the policy.
In light of the above, a decision has been taken by the Government to formulate and
adopt a Renewable Energy Policy for the period 2009-2014.
The Karnataka Renewable Energy Policy 2009-14 shall come into effect from the date of its
publication in the Official Gazette and will remain in force till 2014 or until further Orders.
This Order issues in consultation with Finance Department, Forest, Environment & Ecology
Department and Commerce & Industries Department. ETC and with the approval of the Cabinet vide
No. C. 606/2009 dated 23.12.2009.
Sd/-
(K.JAIRAJ)
ADDITIONAL CHIEF SECRETARY
TO GOVERNMENT,
ENERGY DEPARTMENT
To:
2
The Compiler, Karnataka Gazette, Government Press for publication in the extra ordinary Gazette and
supply 500 copies to this department.
Copy to:
INDEX
Sl No Particulars Page No
1. Vision 1
2. Mission 1
3. Objectives 1
4. Scope of the Policy 1
5. Goals 2
5. (i) Renewable Energy Power Generation 2
Proposed Targets for Renewable Energy Generation, 2009-14 3
5.2 (ii) Energy Conservation & Energy efficiency 3
Target for Energy Conservation 4
6 Year wise Renewable Energy target and Capital Investment 2009-14 4
6. (i) Renewable Energy project Financing 4
6. (ii) Akshaya Shakthi Nidhi (Green Energy Fund) 5
3
7 Land Policy for Renewable Energy Projects 5
7. (i) Land identification for Renewable Energy Projects 5
7. (ii) Government Barren Lands meant for Industrial use 6
4
20. Local Employment 17
21. Corporate Social Responsibility 18
22. Education, Publicity, and Awareness 18
23. Monitoring 18
24. Amendments, Relaxation, Interpretation of the Policy 18 to 20
1. Vision
To harness Green and clean Renewable Energy Sources in the state for environment benefits and Energy
Security. To initiate energy efficiency measures in all sectors for sustainable growth.
2. Mission:
1. To enhance the contribution of environment friendly Renewable Energy sources, to the socio-
economic development and supplement rural energy needs through speedy and expeditious
commissioning of sustainable Renewable Energy projects.
2. To create conditions conducive to private/ public/community participation and investment in
Renewable Energy power projects.
3. To achieve commercial viability and expeditiously operationalize the Renewable Energy
Projects
4. To enhance the contribution of Renewable Energy in the total installed capacity of the state
from 2400 MW to about 6600 MW by 2014.
5. To conserve 7901 MU (900 MW) by 2014 through the Energy Efficiency & Energy
Conservation measures in all sectors.
3. Objectives:
4. Scope of the Policy: The policy will be applicable for the development of all sectors of Renewable
energy Sources including Energy Conservation and Energy Efficiency. The policy is valid for a 5 year
period up to 2014. This policy supersedes all the policy guidelines/instructions issued in this behalf from
time to time. The provisions contained in this Renewable Energy Policy will be applicable to all the
Renewable Energy Projects. This policy will be applicable to all the Renewable Energy projects sanctioned
5
prior to the commencement of the policy and those Renewable Energy projects in the process of
development including already commissioned Renewable Energy projects. Under the policy, Government
has the right to approve capacity allotment Government Order essential to become eligible for availing the
benefits for the renewable energy projects. Under this policy, it is obligatory to sell the electricity generated
from the Renewable Energy Projects commissioned to the respective geographical ESCOMs in which the
projects located, at the Tariff determined by KERC, under a long term Power purchase agreement. The
policy covers the Energy Efficiency and Energy Conservation along with Demand Side Management
(DSM) and Clean Development Mechanism (CDM) implementation. Once the target fixed under this
policy is achieved, a new policy shall be launched. For Cogeneration in Sugar industries a separate policy
will be brought out by the Cooperation department and the Industries and Commerce department for
comprehensive development of the sector. Similarly for Bio-Fuels the Bio-Fuel Board will come out with a
separate policy.
5. Goals: The policy sets twin goals of (i) Renewable Energy power Generation and (ii) Energy
Conservation & Energy efficiency.
5.(i) Renewable Energy power Generation: Presently Renewable Energy Sources contribute about 4600
MU of energy per annum (11.5 %) of the total 40000 MU available from various installed capacities (8600
MW including share from CGS) in the state. The energy demand is projected to attain 10 % growth.
Committed to the green energy the state has mandated, vide GO No EN 216 NCE 2006 dated 2.3.2007, to
enhance the upper limit share of Renewable Energy mix to 20% in the total quantum of energy. Over the
next five years the energy consumption is anticipated to be around 64000 MU per annum. To attain 20 %
Renewable Energy mix the Renewable Energy sources required to contribute 12800 MU by 2014. This sets
the tone for doubling the installed capacity of the various RE sources combined together. Considering the
average plant load factor of various Renewable Energy sources (25 %) this necessitates the cumulative
Renewable Energy capacity addition of about 5850 MW by 2014. However, the policy has a goal of
commissioning 4200 MW additional capacity with accumulative Renewable Energy capacity addition of
6600 MW by 2014.
In the above background the Green Power option for Karnataka are as follows.
6
For the various above Renewable Energy sources there are proven technologies. The targets for significant
Renewable Energy sectors are set as below.
There are about 20,000 industries which have boilers and turbines for manufacture of their
products like, steel, rice, paper, textile etc. Cogeneration units could be set up in these units. As per rough
estimate, about 2000 MW of power can be generated from these industries by setting up cogeneration
plants.
However, the tidal wave energy and Geo-thermal energy are still in early stages and Technology
Demonstrations from laboratory scale Research & Development to Field level will be encouraged by
establishing Prototype Demonstration Projects to produce Energy from Tidal wave and Geo-Thermal
Energy.
5.2 (ii) Energy Conservation & Energy efficiency: One unit of energy saved is equivalent to two units of
energy generated. Energy Efficiency and Energy Conservation is a cheaper option than Generation. The
state government is committed to implement the Energy Conservation Act 2001 and accordingly introduce
Efficiency measures in all sectors of economy and attain the Energy Conservation. Of the total energy
consumption major share of energy is consumed by Agriculture sector (35 %), other sectors consume
Industrial sector (24 %), Commercial sector (14 %), Domestic sector (21 %), Municipal Utilities and others
(6 %). The Planning Commission of India estimated that the potential for Energy Conservation in various
sectors of economy is about 25 % (Bulletin on Energy Efficiency: IREDA, volume 8; January 2008 page
16). It is targeted to conserve 25 % of energy consumed in each of the sectors. During the policy period it
is targeted to conserve about 7901 MU of energy as a cumulative of all the major sectors by 2014. The
Energy conservation sector wise Goals are as below.
Sector Wise Target for energy conservation during the policy period, 2009-2014:
S. No Sector
Consumption Energy conservation
Target (25 %) MU
7
MU % consumption MU Per
2009 to 14 Annum
1 Agriculture 10814 35 2703 540
2 Industries 7263 24 1815 363
3 Domestic 6690 21 1672 334
4 Commercial 4006 14 1001 200
5 Municipal Utilities and 2841 6 710 142
others
Total 31614 100 7901 1579
6. Year wise Renewable Energy Target and Capital investment 2009 to 2014:
The year wise target for different Renewable Energy sources and the investment necessary during the
policy period is given below:
6. (i) Renewable Energy Project Financing: It is estimated that from the targets of additional capacity of
4200 MW Renewable Energy power in the next 5 years by 2014 entails an investment of about Rs 22,000/-
crores at current prices. During the previous years, the investment in the various Renewable Energy
developments has come from the private entrepreneurs. However during the previous three years of
Renewable Energy development, in the state, on an average annually about 300 MW Renewable Energy
capacity additions brought in about Rs 1,800 crores investment by the private sector. It is expected that the
present policy initiative may bring in an additional investment of Rs 1,600 crores annually by the private
sector. With this the private sector investment would amount to Rs 17,000 crores during the policy period.
The profit making Central and State Public Sector Undertakings may also invest in the Renewable Energy
projects and may bring in Rs 5,000 crores.
6. (ii) Akshaya Shakthi Nidhi (Green Energy Fund): In order to facilitate Renewable Energy project
financing and Energy Conservation and Efficiency measures Green Energy Fund „‟Akshaya Shakthi
Nidhi‟‟ will be established. “Green Energy Cess” of Rs 0.05 (five paise) per unit would be levied on the
electricity supplied to commercial and industrial consumers. It is estimated to generate about Rs 55 crores
annually. Out of the Rs 55 crores, 10 % of this fund to the tune of Rs 5 crores will be set apart as
8
contribution to Energy Conservation Fund for Energy Conservation activities. The balance Rs 50 crores
will be set apart for Renewable Energy project financing. The Akshaya Shakthi Nidhi will be
administered by KREDL for promotion of Renewable Energy particularly in Public Private Participation
(PPP) mode, decentralized generation and distribution Renewable Energy projects for the benefit of rural
sector. The funds may also be utilized for land acquisition and land development activity for Renewable
Energy projects including Net Present Value and compensatory afforestation, soil moisture conservation etc
for forest land clearance.
7. Land Policy for Renewable Energy Projects: The availability of suitable land and making the land
available expeditiously is a major issue for RE development. To realise the targeted potential of 4200 MW
during the policy period about 12000 Ha of various categories of lands like Government Barren lands,
Revenue lands, Private lands, Panchayat lands and Forest lands etc are estimated to be necessary in
different districts of the state. To address the land issue following is proposed.
7.(i) Land Identification for Renewable Energy Projects: Inventory of surplus and unused land
available with Public Sector Undertakings, State Govt., Urban Local Bodies/ Gram Panchayath lands and
suitable private waste lands, unproductive single crop agricultural lands will be undertaken District wise,
by the Deputy Commissioners to identify lands for the Renewable Energy projects. Care will be taken to
exclude archaeological heritage lands, prayer and temple lands, burial grounds and monuments etc. The
Government will provide such available lands, waste lands for developing the Renewable Energy projects
under the provisions of Section 71 of Land Revenue Act to Karnataka Renewable Energy Development
Limited. Further necessary amendments to section 79(a), 79(b) and 80 of the Karnataka Land Reforms Act
are to be made to enable the Renewable Energy project developers to purchase suitable private land directly
from the owners of the land.
For waste to energy Renewable Energy projects the Municipal Bodies will identify and keep the
lands at the disposal of Karnataka Renewable Energy Development Limited. The identified lands will be
acquired through the Karnataka Industrial Area Development Board (KIADB), under the provisions of The
Karnataka Industrial Policy, and made available to the Karnataka Renewable Energy Development Limited
for the Renewable Energy projects. Further, keeping in view the welfare interest of the Farmers, certain
equity of not less than 5% of gross energy generated will be provided to take the land owner Farmers as
equity partners in the Renewable Energy projects. Non Agricultural conversion for the express purpose will
be accorded within a period of one month from the date of applying for the same. Government will review
the applicable stamp duty.
7. (ii) Government. Barren lands meant for Industrial Use: The barren Government lands, reserved, as
per the industrial planning for industrial use, at declared Renewable Energy sites, 10% of such lands will be
kept at the disposal of Karnataka Renewable Energy Development Limited for developing the land to set
up the Renewable Energy power projects.
7. (iii) Forest Land: Wherever Forest land is identified for the Renewable Energy projects the same will
be processed and considered by the Karnataka Forest Department under the provisions of the Forest
Conservation Act (1980) subject to the Ministry Of Environment & Forest guidelines within a period of 4
(four) months.
7. (iv) Land Development for Renewable Energy Projects: The identified Revenue, Private and Forest
lands will be developed by Karnataka Renewable Energy Development Limited to facilitate setting up of
various Renewable Energy projects expeditiously. The Akshaya Shakthi Nidhi Funds will be utilised to
develop the lands including the payment towards Net Present Value and Compensatory Afforestation in
case of Forest Lands. This will enable the State to offer ready to use developed land to set up Renewable
Energy projects. Karnataka Renewable Energy Development Limited will sub lease the developed lands to
the Renewable Energy developer for a period of 30 years. After 30 years the project stands transferred to
the Government. Land-Lease Rent will be as per the prime lending rate over current market price as on the
date of handing over of the project, subject to land availability and financial limits on case-to-case basis.
However, it is not permissible to mortgage the lands by the Renewable Energy developers to any financial
or other agency/institution/body.
9
7. (v) Consent From Departments: The Karnataka Renewable Energy Development Limited
/Government will obtain consent from the concerned departments like Forest about the location visa-versa
the Wild Life Sanctuaries, National Parks, Eco-sensitive Zones etc. From Irrigation department to the
effect that the proposed Projects(s) does not infringe with the drinking and irrigation rights of the local
inhabitants, from Revenue department regarding approval under the Karnataka Land Reforms Act. Consent
from the Gram Panchayat etc, Departments will offer their opinion within 90 days time. The Administrative
Department will monitor the reports in a time bound manner.
7. (vi) statutory clearances: Various statutory clearances that are essential for the development and
commissioning of the Renewable Energy projects will be dealt by the Karnataka Renewable Energy
Development Limited with the concerned departments and agencies. The developers will apply in the
formats prescribed to the different departments and furnish a copy to K Karnataka Renewable Energy
Development Limited. The Karnataka Renewable Energy Development Limited will pursue with the
departments and co-ordinate for speedy approvals and clearances within 90 days for all departments /
agencies and 120 days in case of Forest clearance. The issues pending for longer periods will be placed
before the Quarterly Review Meetings held at the level of the Chief Secretary, Government of Karnataka.
Regarding the lands developed by Karnataka Renewable Energy Development Limited. The Karnataka
Renewable Energy Development Limited will obtain all statutory clearances from different departments
before hand and offer such lands for Renewable Energy Project development.
8. Renewable Energy Special Economic Zone (SEZ): The Renewable Energy and allied sector requires
to be supported with Renewable Energy equipment manufacturing industries. Renewable Energy Sources
like wind and solar require considerable extent of land for setting up manufacturing units of Solar Photo
Voltaic and wind Turbine etc. The Renewable Energy manufacturing industrial activity needs to be
supported with land.
Under the Industrial Policy 2009 the state has identified areas covering Bidar, Belgaum, Bagalkot,
Shimoga and Mandya Districts for Sugar and co-gen, power development. Similarly areas covering
Raichur, Bellary, and Bijapur & Chitradurga Districts for Power Generation sector specific industrial zone
development. It is proposed under this policy that the Government will keep 10% portion of these lands at
the disposal of Karnataka Renewable Energy Development Limited to develop them for Renewable Energy
projects and allied Renewable Energy industries. Further 10% of lands will be set apart for Renewable
Energy project in all future SEZs to be identified under Industrial Policy 2009 and also in the already
approved SEZs at Shimoga, Hassan, Bangalore, Udupi, Mysore and Bellary. 10% of all SEZ lands will be
kept at the disposal of Karnataka Renewable Energy Development Limited to develop Renewable Energy
projects.
Further action will be taken to establish Renewable Energy SEZ under the provisions of the Industrial
Policy 2009, particularly in the backward areas of Karnataka to promote setting up of solar manufacturing
units and other Renewable Energy allied manufacturing units. Waste lands and surplus unproductive lands
of about 2000 hectares will be identified for the purpose.
9. Implementation of Renewable Energy Projects: Various measures will be put in place to facilitate
expeditious implementation of Renewable Energy Projects. Renewable Energy projects Identified by
Karnataka Renewable Energy Development Limited will be offered for development on Public Private
Partnership/ Build Own Operate Transfer Mode on developed lands ready to set up the Renewable Energy
Projects specially in wind and Mini Hydro projects.
9. (i) Allotment Committee: A committee under the Chairmanship of Principal Secretary, Energy
Department will consider for allotment of capacity of the renewable energy projects to the private
entrepreneurs. The allotment committee will meet periodically, at least once every quarter, to consider the
various Renewable Energy proposals. The Karnataka Renewable Energy Development Limited will place
the proposals received during the preceding quarter before the allotment committee with due
scrutiny/evaluation and recommendations. The Allotment Committee will be constituted and separately
notified.
10
9. (ii) Clearance of Renewable Energy Projects: Clearance of Renewable Energy projects involves
sanctions/clearances from a number of Government Agencies/Departments. The concerned department will
give necessary approval and clearance within 90 days of the application submitted. KREDL will monitor
with the concerned departments.
9. (iii) Single Window Clearance: A State Level Empowered Committee with the Chief Secretary
Government Of Karnataka as Chairman will provide single window clearance for developing the
Renewable Energy Source Power Plants. The Single Window will review the issues relating to the statutory
clearances of various departments. The clearances / approvals which are not accorded within the specified
time period will be dealt by the Single Window empowered committee. Inter departmental co-ordination
will be strengthened to achieve better results. Benefits of supportive policies will be taken to the maximum
extent. The composition of the Empowered Committee will be separately notified.
9. (iv) Evacuation Arrangement: Often the Renewable Energy projects are located in remote areas
wherein the evacuation arrangements/substations are not readily available and the project commissioning
depends on grid strengthening. To overcome the situation Karnataka Power Transmission Company
Limited and Karnataka Renewable Energy Development Limited will jointly undertake the survey of LV,
HV and EHV Substations and required transmission and distribution lines necessary for the Renewable
Energy projects. A committee will examine the Grid issues related to the Renewable Energy projects.
Karnataka Power Transmission Company Limited will undertake the augmentation of transmission lines
and lying of new lines and receiving stations as required. Respective Renewable Energy Project Developers
will bear the cost of transmission lines from the project site to the substation as per grid norms.
9. (v) Time Limit for project Completion: It is mandatory for the developer to complete the project in all
respect and commission the project with grid synchronization within a period 3 years from the date of the
statutory clearances. Karnataka Renewable Energy Development Limited will endeavour to obtain all
required statutory clearances within 6 months period.
10. Regulatory Issues: Following facilities will be extended to all the Renewable Energy Projects.
10. (i) Grant of Incentives Available to Industries: Generation of electricity from Renewable Energy
Sources will be treated as Industry under the provisions of the Industrial policy 2009 and incentives
available to industrial units under such schemes will also be extended to the Renewable Energy Power
Projects irrespective of the Zone.
10. (ii) Renewable Energy Obligation: The state Government is committed to procure & utilize the
Renewable Energy power as required and determined by Government of Karnataka by time to time, subject
to Karnataka Electricity Regulatory Commission (KERC) guidelines. Due grid strengthening will be
undertaken to meet this commitment. The state Government reserves the first fight of refusal in respect of
purchase of power produced by the Renewable Energy Sources which come under this Renewable Energy
Policy.
10. (iii) Feed in Tariff: Various sources of Renewable Energy power procurement by the Energy Supply
Companies/distribution licensees will be at Tariffs as determined by the KERC. When plant completes 11
years have to sell power to Energy Supply Companies on Tariff based on variable cost subject to KERC
norms.
10. (iv) Solar Tariff: KERC has determined a Tariff of Rs. 3.40 per unit. The Ministry of New &
Renewable Energy (MNRE) Government of India supported Solar Grid connected Power projects of 1 MW
and above. MNRE has allowed an incentive upto Rs. 12 per KWh for Solar PV and upto Rs. 10 per KWh
for Solar Thermal projects in addition to the Tariff allowed by KERC. Under this policy Solar Grid
connected Power projects will be encouraged as per the above policy of the Ministry of New And
Renewable Energy.
11
10. (v) Roof Top Solar Tariff: The Roof Top Grid connected solar KWp level projects of 5 KWp to 100
KWp will be allowed connecting at 415 V, 3 phase, 11 KV level of distribution system of the licensee in
such a manner that the maximum energy injection will not be more than 70% of the consumption from the
distribution licensee„s source by the Solar Roof Top consumer. Any injection in a billing period exceeding
70% of the consumption will be treated as inadvertent and will not be considered for commercial purpose;
neither the deficit is carried forward to next billing period. Such injection will be settled on Net Basis with
the consumption of the said consumer from the distribution licensee‟s source in each billing period. Roof
Top Grid connected solar power quantum fed to the Grid will be eligible for a Tariff of Rs 3.40 per KWh
along with Net Metering facility. If any incentives available from Ministry of New and Renewable Energy
Government of India, it will be passed on to the Developer. However, Roof Top systems will be
additionally eligible for any other subsidies extended to the Roof Top Projects. Solar Photo Voltaic systems
below 2 KWp will be battery backed isolated stand alone systems. Isolated Solar Photo Voltaic sources up
to 200 KWp will be for Rural Applications.
10. (vi) Wheeling of Electricity: wheeling charges @ 5 %will be applicable subject to the KERC norms.
10. (vii) Banking of Electricity: The banking facility for the power generated shall be allowed as
determined by KERC from time to time for the energy banked with the Karnataka Power Transmission
Company Limited / distribution licensee. Energy banked beyond the time prescribed will be utilized and
paid for by the Karnataka Power Transmission Company Limited / distribution licensee at tariff applicable
as per KERC norms.
10. (viii) Power Purchase Agreement (PPA): The sale of electricity by Power Producer of Energy Supply
Company will be governed by the Power Purchase Agreement executed between the Power Producer and
witnessed by Karnataka Electricity Regulatory Commission. The Power Purchase Agreement will be
executed in a time bound manner. Power Company of Karnataka Limited will assign Power Purchase
Agreements to the ESCOMs with back to back arrangement.
10. (ix) Settlements: All transactions between the Karnataka Power Transmission Company Limited /
ESCOMS /Distribution Licensee and the producer involving wheeling or sale of power will be settled on
monthly basis. The Karnataka Power Transmission Company Limited / distribution licensee will pay
interest on payments delayed beyond a month @ State Bank of India short term Prime Lending Rate for
delayed amount for actual period of delay.
10. (x) Grid Tie Policy and Net metering: Net metering facility will be extended to Solar power systems
installed on commercial establishments and individual homes connected to the electrical grid to feed excess
power back to the grid with power credits accruing to the Photovoltaic energy producer.
10. (xi) Exemption from Demand cut: Exemption of demand cut to the extent of 50% of the installed
capacity assigned for captive use purpose, will be allowed.
10. (xii) Security Deposit and Royalty: The Government will determine suitable Security Deposit for the
Renewable Energy projects to bring in earnestness in project implementation. The quantum of royalty to be
levied on energy generation from Renewable Energy sources will be determined by the Government.
11. Policy on Financial Incentives: Following incentives will be extended to all the Renewable Energy
Projects.
11. (i) Government Of India Incentives: The various concession and incentives allowed by Ministry of
New And Renewable Energy /Government Of India regarding Detailed Survey & Investigation/Detailed
Project Report, Generation Based Incentive etc will ipso-facto continue to be passed on by the State
Government to the project developer through Karnataka Renewable Energy Development Limited.
11. (ii) Entry Tax: Entry tax and other fiscal incentives to Renewable Energy generation units are in
accordance with the Industrial Policy 2009-10.
12
11. (iii) Value Added Tax (VAT): The Value Added Tax applicable on various Renewable Energy
equipments and instruments as well as the Energy Efficient and Power saving appliances etc, like the
Renewable Energy and energy Efficient consumer durables directly purchased by the consumers will be
considered for suitable revision under the provisions of Karnataka State Sales Act.
11. (iv) Incentives for Biomass Power Generation projects: The Government of Karnataka will facilitate
Biomass power Plants with an enabling Tariff atmosphere in Co-ordination with KERC.
11. (v) Letter of Credit: The ESCOMs will extend the facility of Letter of Credit to the Developer for
realizing payment in scheduled period for the Renewable Energy power sold to the ESCOM. The cost for
opening the Letter of Credit shall be reimbursed to the ESCOMS from Akshaya Shakthi Nidhi Funds by
Karnataka Renewable Energy Development Limited.
11. (vi) Registration: The various agreements executed by the Renewable Energy project developers with
different departments of Government regarding capacity allotment, project implementation, Revenue &
other land lease including Forest land lease agreements will be considered for revision of registration fee
towards registering the respective agreements under the relevant provisions of Karnataka Stamps &
Registration Act by suitable Amendment.
12. Strategy for Energy Conservation and Energy Efficiency (EC&EE): Karnataka Renewable Energy
Development Limited is “The Designated Agency” vide no. DE 22 PSR 2002 dated. 13.5.2004, to
coordinate, regulates and enforces the provision of the “The Energy Conservation Act 2001”. The
Government of Karnataka vide no. EN 396 NCE 2006 dated. 13.11.2007 and corrigendum, No. EN 87
NCE 2008 dated. 8.4.2008 notified the following under section 18, Energy conservation act 2001. (i) The
Mandatory use of solar water heating systems. (ii) Mandatory use of Compact Florescent Lamp (CFL) in
Government Buildings / aided institutions / Boards/ Corporations. (iii) Mandatory use of ISI mark Energy
Efficient Motor pump sets, Power capacitor, Foot valves in Agriculture sector and (iv) Promotion of
Energy Efficient Building design. With a view to facilitate and enforce the implementation of various
provisions of Energy Conservation Act-2001 and to take policy decisions, a State Level Committee has
been constituted vide GO No EN 87 NCE 2008 dated 3.4.2009. The committee will guide on the
following matters.
12. (i) Strategic Action Plan: In the direction to implement the Energy Conservation Act 2001 Karnataka
Renewable Energy Development Limited will prepare a strategic action plan. Thrust areas for the Strategic
Action plan will be, (i) Regulatory activities for enforcing Energy Conservation Act in State. (ii) School
and collage education, policy promotion & research. (iii) Information dissemination on Energy Efficiency.
(iv) Co-ordination with other state Designated Agencies. (v) Developing Energy Efficiency/DSM
programs. (vi) Delivery Mechanism for Energy Efficiency programs. As part of the Strategic Energy
Conservation Plan, Karnataka Renewable Energy Development Limited will develop a set of databases to
support the development and implementation of EC programs, and launch a general information and
education campaign to promote energy conservation activities.
12. (ii) Energy Conservation programs: To achieve the Energy Conservation and Energy Efficiency
objectives Karnataka Renewable Energy Development Limited as apart of Strategic Energy Conservation
13
Plan will implement a set of proactive energy conservation programs. These programs will be implemented
in cooperation with relevant state government agencies and the private sector. Karnataka Renewable
Energy Development Limited will develop the preliminary designs of 12 energy conservation programs,
which will be implemented during the policy period. A list of the programs is provided below.
12. (iii) Energy Conservation Fund: In order to overcome the financial barriers in the implementation of
Energy Efficiency activities by energy consumers in Karnataka an Energy Conservation Fund (Energy
Conservation Fund) will be established. The Karnataka Energy Conservation Fund Rules 2007 Dtd
1.9.2007 have been issued under section 16 of the Energy Conservation Act, providing for the Energy
Conservation Fund. Under the policy it is proposed to augment the fund with a contribution of Rs 5 crores
annually from Akshaya Shakthi Nidhi for 5 years till 2014.The Fund will facilitate the development and
growth of an Energy Efficiency infrastructure that includes energy service providers such as ESCOMs to
help consumers develop and implement cost-effective Energy Efficiency projects. Karnataka Renewable
Energy Development Limited will develop the rationale for use of the funds and eligibility for receiving
funding for Energy Efficiency projects etc. The Energy Conservation Fund may also be utilised for Energy
Conservation Awards and Publicity Awareness Campaigns capacity building and Trainings etc. The Energy
Conservation Fund will be managed and administered by a committee with Managing Director Karnataka
Renewable Energy Development Limited as Chairman and members being Chief Electrical Inspectorate to
the Government, Government of Karnataka, Managing Director BESCOM, one representative of Bureau of
Energy Efficiency, Government Of India, one representative of Central Power Research Institute Bangalore
and Secretary Federation of Karnataka Chamber of Commerce & Industry.
12. (iv) Energy Auditing: Energy Auditing and adopting Energy efficiency measures will be mandatory
for all Industrial and commercial installations of 600 KVA and above contract demand and this will be
monitored the Karnataka Renewable Energy Development Limited. All LT-2 and LT-4 consumers to adopt
Energy Efficient measures as per Government Order dated 13.11.2007 and Energy department will
approach KERC for amendments in ES&D code. Similarly Energy department and Urban Development
and Housing Departments will come out with proposals to amend the rules for mandatory use of solar water
14
heaters / CFLs/ LEDs etc. accordingly all the urban local bodies will make amendments in the by laws to
enforce Solar Water Heating systems as per Government Order dated. 13.11.2007. In this regard the State
Government will approach KERC to obtain necessary clearances. To promote Solar Water Heaters
(SWHS), a rebate in electricity bill for domestic users at the rate of Rs 100 per month will be extended on
installation of Solar Water Heaters. Energy Efficiency and Energy conservation measures are mandatory
for all Public Utilities. These measures will lead to saving of about 1000 MW in the first 5 years and up to
20% in the next 5 years. To popularize Energy Conservation the Energy Conservation awards will be
given.
12. (v) Energy Obligation: Large Industries having 2000 KVA and above as connected load, should
produce at least 5 per cent of their requirement through captive power plants using Renewable Energy
Sources.
13. (i) Strategy for Wind projects: Under the policy it is proposed to develop additionally 2969 MW of
wind power projects during the five years up to 2014. This would involve a total investment of Rs 15680
crores. To facilitate successful expeditious commissioning of the targeted wind projects the various
statutory clearances will be cleared through single window mechanism. Karnataka Renewable Energy
Development Limited will undertake Wind Resource Assessment and offer the identified windy sites for
development on Public Private Participation/Build Operate Own and Transfer (BOOT) mode. To avoid
locking of huge capacities the wind project allotment will be restricted to 50 MW at a given area each time.
In case of potential in the said location further allocation considered after successful commissioning of the
allotted project. Further only 3 sites will be considered including the ones under the process of
development. The government waste lands in windy locations identified for industrial development will be
offered to set up wind Projects. The capacity of the earlier commissioned wind projects which are more
than 10 years old will be considered for augmentation by replacing with efficient higher capacity Wind
Turbine Generators. Earlier allotments not commissioned beyond time period will be reviewed. Small wind
energy generators will be promoted up to 10 kw for stand alone systems.
The Karnataka Power Corporation Limited is the Karnataka public sector undertaking is the
premier Power Generating Company in the State. A priprerancial allotment of Wind Power Projects above
500 MW and Solar Power Projects above 100 MW will be considered. The followings geographical regions
in Karnataka State are reserved for allotment of Wind Power Projects to Karnataka Power Corporation
Limited.
(a) 50 MW at Kappadagudda Extension.
(b) 270 MW at Hill ranges of Guledagudda –Gudur.
(c) Hill ranges of Sureban,Yere Kittur, Kallur, Mallur and Basidoni.
(d) Hill ranges of Halolli to Katkol (Godachi, Khanpet, Torgal)
(e) Hill ranges of Halagatti, Mudakavi, Tadasi, Vasan, Govinakoppa.
(f) Hill ranges of Soudatti to Ugargol.
(g) Hill ranges of Hanumana Hatti to Kakti.
(h) Zalki of Indi Taluk.
13. (ii) Strategy for Small Hydro Projects: During the policy period, it is targeted to harness 600 MW of
power through mini hydro projects involving Rs. 2700 crores of investment. Karnataka Renewable Energy
Development Limited will take steps to identify the potential sites watershed basin wise including canal
based projects and offer the identified sites for development on Public Private Partnership/Build Operate
Own Transfer mode. The Mini Hydro Project proposals which do not involve diversion of the water flow
resulting in drying up the stream/river stretch will be considered for development. Keeping in view the
environmental issues, the Mini Hydro projects in the Western Ghats‟ Districts/Forest areas will be
restricted to maximum 5.00 MW and preferably Run of the River (ROR) projects encouraged. To facilitate
successful expeditious commissioning of the targeted hydro projects the various statutory clearances will be
facilitated through single window mechanism. Earlier allotments not commissioned beyond time period
will be reviewed. PICO Hydel projects (less than 10 KWH) will be identified by Karnataka Renewable
Energy Development Limited in a fast track mode and central financial assistance of 90 % of the PICO
Hydel project cost provided by Ministry of New and Renewable Energy will be passed on to the eligible
beneficiaries speedily.
13. (iii) Strategy for Biomass projects: The state has 10.5 million Hectors of arable land which generates
around 15 million metric tons of agricultural/agro-processing unit residues excluding Baggasse out of
15
which about 7 million metric tons is estimated to be surplus biomass as per the IISC, Bangalore study. The
state with 3 million hectors of forest land offers Forest residues plus dry Bamboo biomass sources. During
the policy period, it is targeted to harness 300 MW of power through biomass projects based on Rankine
Cycle/Biomass Boiler and Otto Cycle/ Biogas Plant or Biomass Gassifier. The Biomass plants will be
linked to organic fertilizer production units with key input being the waste coming from the Biomass power
plant. To offset the negative factors the biomass projects will be encouraged by extending enabling Tariff
atmosphere. The government waste lands will be identified and offered to set up Biomass Projects.
13. (iv) Strategy for Urban, Municipal and Industrial waste: During the policy period, it is targeted to
harness 50 MW of power through urban, municipal and industrial liquid/solid waste projects. Power
generation based on municipal sewerage treatment plants in Bangalore and other cities are identified as
priority areas. The Municipal corporations will identify the land for the projects. Installation of digesters to
convert green waste to methane gas in all Kalyana Mantaps, Hotels and such other establishments for
power generation will be encouraged and supported in both new and existing establishments.
13. (v) Cogeneration in industry: During the policy period, in order to encourage cogeneration in various
industries, it is proposed to encourage and support industries which have opportunity to cogenerate power.
These industries will be encouraged by extending capital subsidy scheme as one time grant put in place
vide Government Order dtd. 22.10.1998 subject to surplus power fed to the grid.
13. (vi) Solar Thermal / CSP and Solar PV: Grid connected solar projects of 1 MW and above are
considered priority projects. Roof Top small scale Solar PV Installations will be encouraged with Net
Metering facility to feed surplus power generated to the Grid. Under Solar Karnataka Programme it is
targeted for 25000 Solar Roof Tops of 5 to 10 kwp with Net Metering will be taken up with a 250 MW
potential during next 5 years with a generation potential of 350 MU. For villages/habitations where grid
connectivity not feasible or not cost effective, off-grid solutions based on stand-alone lighting systems,
technologies like solar photovoltaic/solar wind hybrid systems, Solar lights and lanterns will be taken up
for community lighting purpose. Solar School and Institution programs will be implemented. Gram
Panchayat and Local bodies will be involved in decentralized solar implementation. Solar steam generating
systems at institutions and industries will be encouraged. Solar water pumps, water purification systems,
Milk Pasteurization plants, solar application to cottage industries will be priority areas. Solar passive
building technology will be encouraged through legislative measures. To conserve electricity in peak hours
solar water heaters, solar lighting systems, solar hoardings etc will be encouraged in domestic, commercial
and industrial applications. Solar cities will be developed in the state. All City Corporations, Municipalities
will amend their bye – laws with due mandatory provisions for providing solar water heating facilities,
right at planning/building stage, both for residential & commercial categories. It will be mandatory for all
the public buildings to have solar devises to meet energy requirements and other applications.
13. (vii) Tidal energy and Geothermal energy: To harness and develop the tidal wave energy Technology
Demonstrations from laboratory scale Research & Development to Field level will be encouraged along
with establishing Prototype Demonstration Projects to produce energy from tidal wave. To explore the
possibility of harnessing and development of Geothermal Energy Research & Development assessment in
collaboration with premier scientific and technological institutes will be explored.
14. Benefits under Clean Development Mechanism (CDM): Government of Karnataka designated
Karnataka Renewable Energy Development Limited as the Nodal Agency vide no. EN 94 NCE 2005 dated
17.6.05 for CDM. In Karnataka, about 31 RE projects have availed 80, 62,9540 of CERs (Carbon Emission
Reduction Rates) by 2008. There is further scope to avail CDM benefits. Karnataka Renewable Energy
Development Limited will facilitate to avail CDM benefits in case of Renewable Energy projects and
Energy Efficiency & Energy Conservation projects and Demand Side Management (DSM) projects.
Karnataka Renewable Energy Development Limited will also take steps to bunch the various Demand Side
Management, Solar application and Energy Efficiency programmes in domestic/ commercial and utility
sectors to avail CDM benefits. The CDM awareness programs will be held by Karnataka Renewable
Energy Development Limited. The CDM eminent consultants will be empanelled by Karnataka Renewable
Energy Development Limited. A separate Division in Karnataka Renewable Energy Development Limited
will deal with CDM process. The Karnataka Renewable Energy Development Limited (KREDL) will
facilitate bundling of various Renewable Energy Projects to avail maximum CER benefits under the
UNFCCC/Keyto protocol.
16
15. Facilitation: Karnataka Renewable Energy Development Limited (KREDL) will be the nodal agency
for Renewable Energy development, Energy Efficiency and Energy Conservation programmes and
implementation of the RE Policy. Karnataka Renewable Energy Development Limited will facilitate
Demand Side Management and CDM activities in the State. Karnataka Renewable Energy Development
Limited will receive and examine the Renewable Energy Project proposals and submit to Government
along with its recommendations. The Government will issue capacity allotment Government Order after
due consideration. Karnataka Renewable Energy Development Limited will undertake Wind resource
Assessment study and identify windy potential sites and notify for development. Similarly Karnataka
Renewable Energy Development Limited will generate data base on Mini Hydel sites with location and
potential capacity details etc. Karnataka Renewable Energy Development Limited will take steps to
develop model development plan to harness targeted capacities of various Renewable Energy Sources.
Karnataka Renewable Energy Development Limited will equip itself with technical particulars, costs,
approved and validated Renewable Energy equipments and vendor particulars etc after due prequalification
process. Karnataka Renewable Energy Development Limited will undertake quarterly review of progress of
various stages of approved Renewable Energy projects and take measures to resolve issues if any with
concerned department/agency. Information kiosks will be set up in Karnataka Renewable Energy
Development Limited for easy access of information. Investors guide / Information booklets will be made
available for information of Renewable Energy investors. All relevant information will also be made
available to the Renewable Energy investors in website / on-line. Karnataka Renewable Energy
Development Limited will undertake Information, Communication and Education (ICE) activity regarding
Renewable Energy, various Ministry of New And Renewable Energy programmes and also Energy
Conservation. Karnataka Renewable Energy Development Limited will bring out annual reports on the
progress in implementation of the Policy.
16. Organizational Development and Human Resource: For effective implementation of this policy and
delivery of the organisational objectives the organisational pattern of Karnataka Renewable Energy
Development Limited will be reviewed and strengthened appropriately by the Government. Dedicated
Divisions to deal with Operations, Land, CDM, Demand Side Management and Energy Efficiency
Divisions will be established / strengthened. In this respect Karnataka Renewable Energy Development
Limited will associate with leading National and International institutes of repute.
17. Renewable Energy Vision Group: Renewable Energy Vision Group will be constituted by the
Government. The vision group will guide the orderly development of Renewable Energy and trade in the
State. Regular interaction will also be held with financial institution / banks and such agencies to sort out
various issues coming on the way of implementation and successful operation of Renewable Energy
projects. The vision group will also look into the Energy Conservation & Energy Efficiency aspects.
18. Award Scheme: The Renewable Energy project successfully commissioned during the original
agreement period will be awarded with a certificate of appreciation by the government and a cash incentive
from Akshaya Shakthi Nidhi as determined.
19. Environmental Issues: The Renewable Energy developer will make suitable financial provisions for
mitigation of adverse impacts as per the approved Environment Impact Assessment plan, Environment
Management Plan and mitigation of degradation of environment, watershed area management, afforestation
and soil moisture conservation due to disturbance of eco-system will be implemented at the Project cost. It
is required to follow environmental related issues concerning disposal of blasting muck and soil etc, at
appropriate dumping sites. Renewable Energy Projects will be encouraged to adopt cleaner development
techniques in their activities. They will also be motivated to go for green technologies and processes to
protect the environment and ecology. Enterprises adopting such best practices will be recognized with state
awards every year.
20. Local Employment: The Renewable Energy projects will provide employment to the local people, in
respect of all the unskilled/skilled staff and other non–executives required for execution, operation and
maintenance of the Project. In regard to technical manpower like engineers and other executives, the
Renewable Energy developer Company will give preference to the candidates conversant with customs,
culture, language and dialect of Karnataka.
17
21. Corporate Social Responsibility (CSR) and Local Area Development: Adoption of Corporate Social
Responsibility (CSR) by the renewable Energy Project investors will be persuaded. They will be urged to
provide training to local people, fine tune the available skills and also promote furnishing schools. The
Government will constitute a Local Area Development Committee (LADC) to monitor Corporate Social
Responsibility. The Deputy Commissioners shall be the Chairman of the Local Area Development
Committee and other members will be nominated by the Government, which will include the
representatives of Renewable Energy Project Developers. Concerned Assistant Commissioner will be the
Member Secretary.
22. Education, Publicity and Awareness: The state government is committed to undertake Publicity and
awareness activity to promote and popularize the use of Renewable Energy Resources, and Energy
Efficiency and Energy Conservation measures. Necessary curriculum will be introduced in the school and
college syllabus. Karnataka Renewable Energy Development Limited will organize workshops and
exhibitions. Karnataka Renewable Energy Development Limited will associate with other institutions like
Mahatma Gandhi Institute for Rural Energy & Development and other premier national and international
agencies, to organize training programs across the Departments for promotion of renewable energy, energy
efficiency and energy conservation.
23. Monitoring: A high level Inter Departmental Review Committee will be constituted to regularly
monitor implementation of all provisions of the policy. This committee will also ensure issue of necessary
Government. Orders by various departments in relation to the policy without loss of any time for mid-
course corrections, if required for smooth implementation of the Policy.
18
(Renewable Energy project occupy 3 Ha per MW average. Total area
required 12000 Ha, 30 % forest, 40 % Revenue and 30 % private
lands).
Expeditious NA approval
Necessary amendment to the Karnataka Stamp & Registration Act to
revise Agreement registration fee.
CSR co-ordination with Renewable Energy Projects and local
administration.
4 Industries Department Government of Karnataka approved the SEZ in Shimoga, Hassan,
(SEZ) Government of Bangalore, Udupi, and Mysore of 7440 Ha. 10 % of this is to be
Karnataka identified in the hills and barren lands, about 744 Ha. For Renewable
Energy projects.
Exclusive 2000 Ha SEZ to be set up for Renewable Energy and allied
industry.
All future proposed SEZs to provide 10 % land for RE Projects.
Processing benefits to be extended under Industrial policy to the
Renewable Energy Projects.
5 Forest Department, To facilitate identification of 3600 Ha Forest lands free of National
Government of Parks and Sanctuary and process FC clearance and Karnataka
Karnataka Renewable Energy Development Limited will co-ordinate. NPV and
CA implication Rs 400 crores.
6 Irrigation Department, Necessary Approvals within time frame and land clearances, about
Government of 200 to 300 Has of irrigation lands.
Karnataka
7 Energy Department, Connected Government orders, State Level Empowered Committee-
Government of Single Window agency, Inter Departmental Review Committee,
Karnataka Renewable Energy Vision Group
PCKL nodal agency for Power Purchase Agreement.
Letter of Credit to the Developer for realizing payment in scheduled
period for the Renewable Energy power sold.
All transactions between the Karnataka Power Transmission
Company Limited./ distribution licensee and the producer involving
wheeling or sale of power will be settled on monthly basis.
Delay beyond a month @ State Bank of India short term Prime
Lending Rate for delayed amount for actual period of delay.
The Renewable Energy project successfully commissioned during the
original agreement period will be awarded with a certificate of
appreciation by the government and a cash incentive from Akshaya
Shakthi Nidhi
Administrative approval for strengthening Karnataka Renewable
Energy Development Limited.
Grid Strengthening by Karnataka Power Transmission Company
Limited.
Approval to take up MW scale and Roof Top Solar projects.
8 Labour Department, To monitor employment provided. Renewable Energy projects to
Government of provide employment to the local people, in respect of all the
Karnataka unskilled/skilled staff and other non–executives required for
execution, operation and maintenance of the Project. In regard to
technical manpower like engineers and other executives, the
Renewable Energy developer Company will give preference to the
candidates conversant with customs, culture, language and dialect of
Karnataka.
19
Sd/-
(K.JAIRAJ)
ADDITIONAL CHIEF SECRETARY
TO GOVERNMENT,
ENERGY DEPARTMENT