Project
REN KORAT ENERGY PROJECT
Owner
REN KORAT Energy CO., LTD.
Owner’s Engineer
TRACTEBEL ENGINEERING LTD.
Contractor
Revision History
Rev. Revision Date Created by Checked by Approved by Description
A 19/07/2023 Smith S. Seri S, Nirut N. Prapas P. Issue for Approval
Originator
Originator document No. Lang. Format Sheet Approval Stamp
N/A EN A4 1 of 10
Created by Checked by Approved by
Smith S. Seri S, Nirut N. Prapas P.
Title
System Turnover Package List
(Construction)
Project Document/Drawing No. Rev. Date
REN-E-SG-10-LS-000-0007 A 19/07/2023
REN KORAT ENERGY PROJECT
Content
Page no.
1. Mechanical Completion Package 3
1.1 Construction Completion Certificate 3
1.2 Mechanical 3
1.3 Electrical 6
2. Punch List
2.1 Mechanical 9
2.2 Electrical 10
Originator document No.: REN-E-SG-10-LS-000-0007 Rev. A Sheet 2 of 10
REN KORAT ENERGY PROJECT
Description
Upon verification by Owner that a System Turnover Package is complete Owner
shall accept the System Turnover Package and shall evidence such acceptance by
written notification thereof to Contractor.
1. Mechanical Completion Package
1.1 Construction Completion Certificate
1.2 Mechanical
1.2.1 Pipe rack / pipe bridge installation
1.2.1.1 Pipe rack Fabrication
1.2.1.2 Pipe rack installation
1.2.1.3 General arrangement
1.2.1.4 Calibration certificate
1.2.2 Gas Engine
1.2.2.1 Gas Engine installation
1.2.2.2 General arrangement
1.2.2.3 Calibration certificate
1.2.3 Fuel Gas Supply
1.2.3.1 Pipe Installation
1.2.3.2 Hydrostatic test
1.2.3.3 Pig cleaning
1.2.3.4 Painting
1.2.3.5 P&ID
1.2.3.6 General arrangement
1.2.3.7 Calibration certificate
1.2.4 HRSG
1.2.4.1 HRSG installation
1.2.4.2 General arrangement
1.2.4.2 Calibration certificate
Originator document No.: REN-E-SG-10-LS-000-0007 Rev. A Sheet 3 of 10
REN KORAT ENERGY PROJECT
1.2.5 Radiator
1.2.5.1 Radiator installation
1.2.5.2 General arrangement
1.2.5.3 Calibration certificate
1.2.6 Cooling Water System
1.2.6.1 Pipe Installation
1.2.6.2 Pump Installation
1.2.6.3 Hydrostatic test
1.2.6.4 Flushing
1.2.6.5 Painting
1.2.6.6 P&ID
1.2.6.7 General arrangement
1.2.6.8 Calibration certificate
1.2.7 Service water System
1.2.7.1 Pipe Installation
1.2.7.2 Service water tank installation
1.2.7.3 Pump Installation
1.2.7.4 Hydrostatic test
1.2.7.5 Flushing
1.2.7.6 Painting
1.2.7.7 P&ID
1.2.7.8 General arrangement
1.2.7.9 Calibration certificate
1.2.8 RO Water System
1.2.8.1 Pipe Installation
1.2.8.2 Pump Installation
Originator document No.: REN-E-SG-10-LS-000-0007 Rev. A Sheet 4 of 10
REN KORAT ENERGY PROJECT
1.2.8.3 Hydrostatic test
1.2.8.4 Flushing
1.2.8.5 Painting
1.2.8.6 P&ID
1.2.8.7 General arrangement
1.2.8.8 Calibration certificate
1.2.9 Oil Water Separator
1.2.9.1 Pipe Installation
1.2.9.2 Pump Installation
1.2.9.3 Hydrostatic test
1.2.9.4 Flushing
1.2.9.5 Painting
1.2.9.6 P&ID
1.2.9.7 General arrangement
1.2.9.8 Calibration certificate
1.2.10 Starting Air compressor package
1.2.10.1 Pipe Installation
1.2.10.2 Starting Air compressor Installation
1.2.10.3 Air tank Installation
1.2.10.4 Pneumatic test
1.2.10.5 Air Flushing
1.2.10.6 Painting
1.2.10.7 P&ID
1.2.10.8 General arrangement
1.2.10.9 Calibration certificate
1.2.11 Station and Instrument Air Compressor
1.2.11.1 Pipe Installation
Originator document No.: REN-E-SG-10-LS-000-0007 Rev. A Sheet 5 of 10
REN KORAT ENERGY PROJECT
1.2.11.2 Air compressor Installation
1.2.11.3 Air tank Installation
1.2.11.4 Pneumatic test
1.2.11.5 Air Flushing
1.2.11.6 Painting
1.2.11.7 P&ID
1.2.11.8 General arrangement
1.2.11.9 Calibration certificate
1.2.12 Fire Protection
1.2.12.1 Pipe Installation
1.2.12.2 Fire pump installation
1.2.12.3 Hydrostatic test
1.2.12.4 Flushing
1.2.12.5 Painting
1.2.12.6 P&ID
1.2.12.7 General arrangement
1.2.12.8 Calibration certificate
1.2.13 HVAC
1.2.13.1 Pipe Installation
1.2.13.2 Air condition installation
1.2.13.3 Ventilation Fan installation
1.2.14 Crane and Hoist
1.2.14.1 Crane and hoist installation
1.2.14.2 Calibration certificate
1.2.15 Stack
1.2.15.1 Stack installation
1.3 Electrical
Originator document No.: REN-E-SG-10-LS-000-0007 Rev. A Sheet 6 of 10
REN KORAT ENERGY PROJECT
1.3.1 Auxiliary transformer
1.3.1.1 FAT Test Report
1.3.1.2 Installation Transformer
1.3.1.3 Equipment Layout
1.3.1.4 Single Line Diagram
1.3.1.5 Schematic Diagram
1.3.2 EDG (Emergency Diesel Generator)
1.3.2.1 FAT Test Report
1.3.2.2 Installation Emergency Diesel Generator (EDG)
1.3.2.3 Equipment Layout
1.3.3 Grounding and Lightning
1.3.3.1 Cable Test Report
1.3.3.2 Installation Grounding
1.3.4 GSUT (Generator Step up Transformer)
1.3.4.1 FAT Test Report
1.3.4.2 Installation Generator Step up Transformer
1.3.4.3 Equipment Layout
1.3.5 UAT (Unit Auxiliary Transformer)
1.3.5.1 FAT Test Report
1.3.5.2 Installation Unit Auxiliary Transformer
1.3.5.3 Equipment Layout
1.3.6 MV Switchgear
1.3.6.1 FAT Test Report
1.3.6.2 Installation MV Switchgear
1.3.6.3 Equipment Layout
1.3.6.4 Single Line Diagram
1.3.6.5 Calibration certificate of test devices
Originator document No.: REN-E-SG-10-LS-000-0007 Rev. A Sheet 7 of 10
REN KORAT ENERGY PROJECT
1.3.7 LV Switchgear/DB
1.3.7.1 FAT Test Report
1.3.7.2 Installation LV Switchgear/DB
1.3.7.3 Equipment Layout
1.3.7.4 Single Line Diagram
1.3.7.5 Calibration certificate of test devices
1.3.8 Fire Alarm
1.3.8.1 Fire Alarm installation
1.3.8.2 Equipment Layout
1.3.9 Outdoor Lighting System
1.3.9.1 Installation Outdoor Lighting
1.3.9.2 Equipment Layout
1.3.10 Batteries/DC/UPS
1.3.10.1 Installation Battery Charger
1.3.10.2 Equipment Layout
1.3.11 DCIS
1.3.11.1 Installation DCIS
1.3.11.2 Equipment Layout
1.3.11.3 Schematic Diagram
1.3.12 CEMS (Continuous Emission Monitoring System)
1.3.12.1 Installation CEMS
1.3.12.2 Equipment Layout
1.3.12.3 Schematic Diagram
1.3.13 Telephone
1.3.13.1 Cable and LAN for Telephone Installation Report
1.3.13.2 Equipment Layout
1.3.14 Receptacle System, Air Condition
Originator document No.: REN-E-SG-10-LS-000-0007 Rev. A Sheet 8 of 10
REN KORAT ENERGY PROJECT
1.3.14.1 Receptacle System Installation Report
1.3.14.2 Equipment Layout
1.3.15 Ventilation Fan
1.3.15.1 Ventilation Fan Cabinet Installation Report
1.3.15.2 Equipment Layout
1.3.16 CCTV System
1.3.16.1 Installation CCTV
1.3.16.2 Equipment Layout
2. Punch List
2.1 Construction Completion Certificate
2.1.1 Pipe rack / pipe bridge installation
2.1.2 Gas Engine
2.1.3 Fuel Gas Supply
2.1.4 HRSG
2.1.5 Radiator
2.1.6 Cooling Water System
2.1.7 Service water System
2.1.8 RO Water System
2.1.9 Oil Water Separator
2.1.10 Starting Air compressor package
2.1.11 Station and Instrument Air Compressor
2.1.12 Fire Protection
2.1.13 HVAC
2.1.14 Crane and Hoist
2.1.15 Stack
Originator document No.: REN-E-SG-10-LS-000-0007 Rev. A Sheet 9 of 10
REN KORAT ENERGY PROJECT
2.2 Electrical
2.2.1 Auxiliary transformer
2.2.2 EDG (Emergency Diesel Generator)
2.2.3 Grounding and Lightning
2.2.4 GSUT (Generator Step up Transformer)
2.2.5 UAT (Unit Auxiliary Transformer)
2.2.6 MV Switchgear
2.2.7 LV Switchgear/DB
2.2.8 Fire Alarm
2.2.9 Outdoor Lighting System
2.2.10 Batteries/DC/UPS
2.2.11 DCIS
2.2.12 CEMS (Continuous Emission Monitoring System)
2.2.13 Telephone
2.2.14 Receptacle System, Air Condition
2.2.15 Ventilation Fan
2.2.16 CCTV System
Originator document No.: REN-E-SG-10-LS-000-0007 Rev. A Sheet 10 of 10