NTPC Simhadri NTPC140MW Bilhaur
NTPC Limited, India
DMR Panda
Green Hydrogen Transition 9650992364
[email protected]Follow us on: /ntpc1 /ntpcltd1 /ntpclimited /Company/ntpc /ntpclimited
Contents
• NTPC and its Energy Transition
1
• NTPC Green Hydrogen Pilot Projects
2
• Microgrid and Green Ammonia Projects
3
• A way forward
• 4
2
NTPC: India’s largest Power Generating Company
In-house expertise:
Govt. of India enterprise with • Engineering & Project Management;
48 years excellence; • Procurement;
• Erection, Testing and Commissioning
& O&M;
~19600
Developed projects of capacity ~72 GW NTPC Ranked No. 1 Independent
• 88 Projects - Coal, Gas, Hydro, Coal Mines Power Producers (IPP) and Energy
- Solar, Wind, Hydrogen Traders Globally by S&P Platts
3.2 GW RE capacity;
4.7 GW RE in execution; Financials in FY-22:
9.3 GW RE in tendering; • $15.8 Bn revenue;
• $2.1 Bn Profit;
3 3
NTPC Energy Transition
CEO Water Mandate A signatory to the prestigious UN Global Compact’s CEO Water Mandate
1st Energy Company and among few organizations across the globe to
UN HLDE
declare its Energy Compact Goals
Energy Source Energy New Initiatives Emission
1 2 3 4
Decarbonization Advancement Management
• Renewable • Hydrogen-Natural • Energy Storage
• Carbon Capture
Energy Sources Gas Blending System
from Flue gas
• Low Carbon Fuel • Green Methanol • E-Mobility: EVs
• Waste to Energy
(Biomass)
• Green Ammonia • G-Mobility: FCEVs
• Hydrogen-based
Fuel
4
NTPC Long Term Plan
2023 2032
Solar + Wind [CATEGORY [CATEGORY
Hydro 5.6% 1.8% NAME] NAME]
[VALUE]% [VALUE]%
[CATEGORY
Other RE NAME]
[VALUE]% [CATEGORY
Gas 9.7% [PERCENTAG NAME]
E] [VALUE]%
~72 130+
GW GW
Coal 82.6% [CATEGORY [CATEGORY
NAME] NAME] 4.6%
[VALUE]%
5
Why Green Hydrogen
• Energy security
• Decarbonisation
6 6
NTPC’S Pilot Projects On Hydrogen
• 200 Households
• 5% v/v, plans to reach 20% by end of 2023
7 7
NTPC’S Pilot Projects On Hydrogen
5 Nos. Fuel Cell Bus,
Leh, Ladakh
Leh – 225 km/day/bus 5 Nos. Fuel Cell
15 kg H2 storage Bus,
New Delhi
Delhi – 600 km/day/bus
50 kg H2 storage
NTPC’S Pilot Projects On Hydrogen
Methanol: 10 TPD Flue Gas - CO2 to Methanol Plant (FG-CTM)
Carbon Capture Unit
Thermal Plant CO2 Capture Unit
o 20 TPD CO2 from thermal plant flue gas
Methanol Storage
o Amine absorption process Absorption 20 TPD CO2
Process
Hydrogen Generation Unit Methanol
Synthesis 10 TPD
o Generating 2 TPD Hydrogen CH3OH
Electrolyser
2 TPD H2
Methanol Production Unit
o Conversion of CO2 to Methanol RE Power Hydrogen Generation
o Catalytic hydrogenation process
Location: NTPC Vindhyachal, MP
7
Green Ammonia Projects in India
Capacity: 50 TPD Capacity: 35 TPD Capacity: 100 TPD Capacity: 300 TPD
Location: Nangal, Punjab Location: Dahej, Gujarat Location: Gajraula, UP
Location: Any where in
Consultant: USAID Consultant: Fichtner Consultant: USAID India
National Fertilizers Gujarat Alkali Private Chemical Company NTPC Limited
Limited Chemicals Limited
Status: Status: Status: Status:
Feasibility Study: Feasibility Study: In Feasibility Study: In Consultant: Fichtner
Completed progress progress
Feasibility Study:
Completed
Green Methanol Projects in India
Capacity: 3x25TPD
Location: GACL - Vadodara Capacity: 185 TPD
GACL - Dahej Location: Gajraula
GNAL - Dahej
Consultant: Fichtner Consultant: USAID
Gujarat Alkali Private Chemical Company
Chemicals Limited
Status: Status:
Feasibility study In-progress Feasibility study In-progress
NTPC - RE Park and Green Ammonia @ Bhuj, Gujarat
1. NTPC RE Park
o Power: 5 GW Renewables (Solar and Wind)
o Land: 100 Sq. km
o Status: Under Execution
Bhuj, Gujarat
2. Green Ammonia (GNH3)Project
o Capacity: 0.4 MMTPA of Green NH3
o Estimated Cost: $1.2 Billion
o Timeline: Project Completion: 2025-2026
o Status: Feasibility Study by KfW, Germany – April 2023
3. Electrolyser: Selection of Technology Partner in place
o 400 MW PEM Electrolyser
o 600 MW Alkaline Electrolyser
12
NTPC - H2 Hub @ Pudimadaka, Andhra Pradesh
1. NTPC RE Source
o Power: Required capacity (Solar, Wind, Hydro, BESS)
o Operation: Anywhere in India (Waiver from ISTS Charges, some
Open access charges) Pudimadaka, And
ra Pradresh
2. Integrated Green Hydrogen Project
o GH2 (0.5 MMTPA), GNH3 (0.45 MMTPA), GCH3OH (0.4 MMTPA)
o H2 based Industries
3. Green Ammonia (GNH3) Project
o Capacity: 0.45 MMTPA of Green NH3
o Estimated Cost: $1.5 Billion
o Timeline: Project Completion: 2027-2028
o Status: Obtained approval from State Govt. of Andhra Pradesh
13
NTPC’S Project On HESS – Isolated Microgrid
Altitude: 4400m
Temp. : -45 oC
Solar: 3.6 MW
Electrolyser: 1.8 MW
BESS: 1 MW
Fuelcell: 200 kW
8
Migratory Birds at NTPC Dadri
Thank You
NTPC Ramagundam
Website: www.ntpc.co.in