HSE-RA-019 Steel Fixing - Rev 0

This risk assessment procedure outlines the potential risks and recommended controls for steel fixing work. The document identifies six key tasks: 1) Pre-use equipment inspection, 2) Use of PPE, 3) Use of trained employees only, 4) Competent supervision, 5) Lifting steel to the work area, and 6) Carrying steel to fixing locations. Failure to follow recommended controls such as using proper equipment, PPE, training, supervision, lifting procedures and manual handling techniques could result in injuries or property damage. The assessment was compiled by an HSE team and requires multiple levels of review and authorization from project management.

Uploaded by

عمرو
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
376 views15 pages

HSE-RA-019 Steel Fixing - Rev 0

This risk assessment procedure outlines the potential risks and recommended controls for steel fixing work. The document identifies six key tasks: 1) Pre-use equipment inspection, 2) Use of PPE, 3) Use of trained employees only, 4) Competent supervision, 5) Lifting steel to the work area, and 6) Carrying steel to fixing locations. Failure to follow recommended controls such as using proper equipment, PPE, training, supervision, lifting procedures and manual handling techniques could result in injuries or property damage. The assessment was compiled by an HSE team and requires multiple levels of review and authorization from project management.

Uploaded by

عمرو
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 15

DOC No DS/CA006P02/00021

PAGE No 1 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

Index:
Form 1 Task Analysis Initiation
Form 2 Risk Assessment Process As per Risk Assessment Procedure.
Form 3 Written Safe Work Procedure Result

Compiled by the following team:


NAME DESIGNATION SIGNATURE
Project Manager
Construction Manager
Site Engineer
Safety Officer
Risk Assessment Review 1 Review 2 Review 3 Review 4
Review Date: Date : Date : Date:

Name and Signature


of person reviewing :
AUTHORISATION
Prepared by: Approved by
Signature Date Signature Date
HSE Manager Project Manager

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 2 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

TASK ANALYSIS - FORM 1


Impact
SEQUENCE OF TASK STEPS POTENTIAL INJURIES OR HAZARDS RECOMMENDED CONTROLS
H, S, E
1. Pre-use inspection and use of all equipment. Failure of equipment will cause injuries to  Faulty equipment to be repaired/maintained or replaced.
persons and / or property damage.  Guards to be on all Machinery and appropriate PPE to be
Fuel/oil leaks could cause environmental worn.
concerns. H, S, E  Engine ran machinery to have fire extinguishers available
locally.
 Drip trays/heavy gauge plastic to be insitu in case of leaks
and spill kit to be within the project for accidental spills.
2. Wear appropriate Personal Protective Failure to use Personal Protective
Equipment. Equipment will cause injuries to employees
Gloves.
Safety boots.
H
Overalls.
Hard hat.
Hearing protection.  Enforce the use of Personal Protective Equipment AT
Eye protection. ALL times

3. Use trained employees only Failure will result in injuries to persons and /  Enforce the use of competent persons only
H, S
or property damage
4.  Competent supervisor should be appointed for every
activity to monitor the workers.
 Work task instruction should be provided for every
H, S activity.

Competent supervision Failure will cause injuries to employees and


or property damage
5. Lifting steel to the work area Failure will increase the risk of injuries H  Steel to be unloaded by forklift then lifted to the work
Struck by load carried by crane area by crane where available
Manual Handling  Only competent forklift driver to operate forklift
HSE/QUALITY SYSTEM DOCUMENTATION
DOC No DS/CA006P02/00021
PAGE No 3 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

Poor communication  Only competent crane operator to operate crane


 All materials to be loaded and unloaded by a competent
rigger.
 Keep clear of when load is landing in work area
 Rigger and crane operator to maintain proper
communication.
 All lifting chains and slings to be tested and tagged for
current period.

6. Carrying of steel to fixing location Failure will result injuries to persons and  Ensure walkways are clear and nobody is in the way of
property damage. steel ends.
 All penetrations to be covered securely before any work
Manual handling begins
H,S
 Proper lifting procedure must be applied.
 Proper positioning when lifting.
 Enforce the use proper PPE.
Do not lifts heavy and defective materials.

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 4 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

TASK ANALYSIS - FORM 1 (continued)


SEQUENCE OF TASK STEPS POTENTIAL INJURIES OR HAZARDS RECOMMENDED CONTROLS
7. Placing steel reinforcement Failure will result injuries to persons and  All penetrations to be covered securely before any work
property damage. begins
 Appropriate edge protection to be in place i.e
scaffolding, or edge protection.
 Provide safe working platform or good standard
scaffolding.
H,S
 Use full body harness while working at heights.
 Rigid hard barriers to protect from falling.
 Notify other trades in the work area that steel fixing will
be taking place and to keep clear
 Wear leather heavy-duty gloves and safety boots.
 Two employees to lift / move large diameter bars
8. Cutting steel reinforcement Failure of equipment and power tools may H,S,E  Never lift steel that is too heavy for you.
result injuries to person and property  Place steel on the ground cautiously, never throw it.
damage.  Ensure feet are clear when placing steel.
 Wear leather heavy duty gloves, Safety boots, eye and
Use of angle grinder Compressed gas explosions could cause hearing protection
fire resulting injuries or death and property.  All column starter bars to be fitted with caps
Gas cutting  Machinery to have guards in place and be well
maintained.
 Proper handling and firm grip by the operator to be
Environmental concern
ensure to avoid jerking and strike to operator and
nearby operatives.
Fumes could cause damage to the
 Use fire blanket and remove the combustible materials
environment.
in the area
Noise and dust could cause potential
environmental damage.  Use the appropriate PPE to ensure safe working
procedure.

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 5 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

 Provide adequate mechanical fume extraction or force


ventilation wherever work is carried out.
 Noise levels to be monitored and restricted to social
able timings where ever practicably possible.
 Noise and dust could cause potential environmental
damage.
9. Fixing steel reinforcement Failure may results in hands eyes and finger  Tie wire to be fitted firmly, ensure that it is not tightened
injuries too greatly
 Tie wire to be bent in / down
 Ensure use correct length of wire
 Enforce concentration on work.
 All column starter bars to be fitted with caps
Outdoor works Heat Exhaustion H
 Ensure use correct pliers
Exposure to UV Light
 Increase the intake of water, provide shaded areas and
schedule the work on cooler part of the day.
 All employees to wear PPE, (shade brim on safety
helmet, 30+ sunscreen, sunglasses, safety boots,
heavy duty gloves and hearing protection)
10. Walkways on new steel slab areas. Potential trip, fall and injuries on raw steel.  Provide proper safe walkways on new steel areas.
H,S
11. Fixing steel for columns and core wall at Persons falling from heights resulting  Provide safe working platform or good standard
height and on edges injuries or death. scaffolding.
Falling of materials / property damage.  Scaffold erected by competent scaffolding erectors.
 Use step ladder and follow the safe usage.
 Use full body harness while working at heights.
 Materials to be protected from falling.

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 6 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

RISK ASSESSMENT – FORM 2


Risk Rating Calculation
Risk Rating = A + B + C + D.
A + B + C + D
Injury Severity Potential Damage / Loss Frequency or Likelihood Environmental Impact
0 No injury 0 No damage 0 Never happened before 0 No effect
1 Minor – (FAC) 1 Minor < 500 AED, No delay 1 Happened somewhere 1 Minor Effect - Short term < less 1 month
2 Major – (MTC) 2 Major > 500 AED, No delay 2 Happens occasionally 2 Major Effect - Long term > greater 1 month
3 LTI 3 Major > 10 000 AED, one day delay 3 Happened before  
4 Disabling Injuries 4 Serious > 100, 000 AED, >1 day delay 4 Happens regularly Risk Rating Matrix
5 Fatality 5 Severe > 1, 000, 000 AED, Weeks delay. 5 Daily occurrence

Result Classification:
Risk Rating
16
Critical = 17►15 High = 14►11 Medium = 10►7 Low = 6►0 14

Immediate action. Action in 24 hours. Action in a week. ASAP. 12


10
8

Risk Reduction Hierarchy: 6


4
1. Engineering to reduce risk. 2
0
2. Replacement with lower risk. 1
5
3. Isolation of risk – Barricading or Guarding. 2
3
4
4
3
4. Reduction of exposure to risk. Potential Impact
5
6
2
Probability
(C)
7
5. PPE and Training (A / B / D) 8
9 1

RISK ASSESSMENT – FORM 2 (continued)


HSE/QUALITY SYSTEM DOCUMENTATION
DOC No DS/CA006P02/00021
PAGE No 7 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

RISK ASSOCIATED WITH Impact HOW IS HAZARD TO BE BY Result


No HAZARD IDENTIFIED H, S, E RR BY WHOM RR
HAZARD DEALT WITH WHEN
1  Faulty hand tools Bruises, cuts. Gloves, trowels in good Supervisor Before &
condition. during
 Mechanical guards not in Entanglement, Skeletal Damage. the use
place Guards in place and equipment of
H,S,E 13 regularly maintained. equipme 6
nt
 Unwanted Fuel/Oil Spillages Contamination of the soil, Care to be taken refuelling and
atmospheric pollution, risk of fire. drip trays/heavy gauge plastic to
be in place as required.
2 Injury to project employees Potential Death, Major/Minor Following PPE to be worn Supervisor Before &
Skeletal damage, cuts and bruises appropriately to the task – during
to all parts of the body, asthma. Gloves. work
Safety boots.
H,S 10 5
Overalls.
Hard hat.
Hearing protection.
Eye protection
3 Un trained employees Poor quality of work, chance for Provided trained/competent PE/FM Always
accident /incident or property H,S 7 worker and supervision 5
lost/damage
4 Poor Supervision Poor quality of work, chance for Ensure the availability of PE/FM Always
accident /incident or property competent supervisor at work
lost/damage place.
H,S 10 3
Work task instruction should be
provided to the workers prior to
the commencement of activity
5 Unsafe lifting of steel to the work Struck by load carried by crane Steel to be unloaded by forklift FM/ Before
area Manual Handling H.S 12 then lifted to the work area by Supervisor starting 4
Poor communication crane where available work

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 8 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

RISK ASSOCIATED WITH Impact HOW IS HAZARD TO BE BY Result


No HAZARD IDENTIFIED H, S, E RR BY WHOM RR
HAZARD DEALT WITH WHEN
Only competent forklift driver to
operate forklift
Only competent crane operator to
operate crane
All materials to be loaded and
unloaded by a competent rigger.
Keep clear of when load is
landing in work area
Rigger and crane operator to
maintain proper communication.
All lifting chains and slings to be
tested and tagged for current
period.

6 Unsafe lifting and shifting of steel Manual Handling Ensure walkways are clear and Supervisor Before
to the work place Puncture wound nobody is in the way of steel and
Cuts and abrasions ends. during
Unsafe manual handling Fall from heights All penetrations to be covered work
Slip, trips or fall on to steel securely before any work begins
Proper lifting procedure must be
applied.
H,S 10 3
Proper positioning when lifting.
Ensure the access over the steel
is fixed with two wooden planks
and free from all trip slip hazards.
Enforce the use proper PPE.
Do not lifts heavy and defective
materials.
7 Unsafe placing of steel Cuts and abrasions All penetrations to be covered FM/ During
H,S 3
reinforcement Fall from heights securely before any work begins Supervisor placing

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 9 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

RISK ASSOCIATED WITH Impact HOW IS HAZARD TO BE BY Result


No HAZARD IDENTIFIED H, S, E RR BY WHOM RR
HAZARD DEALT WITH WHEN
Slip, trips or fall on to steel Appropriate edge protection to be of steel
Puncture wound in place i.e scaffolding, or edge
protection.
Provide safe working platform or
good standard scaffolding.
Use full body harness while
working at heights.
10 Rigid hard barriers to protect
from falling.
Notify other trades in the work
area that steel fixing will be
taking place and to keep clear
Wear heavy-duty leather gloves
and safety boots.
Two employees to lift / move
large diameter bars

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 10 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

RISK ASSOCIATED WITH Impact HOW IS HAZARD TO BE BY Result


No HAZARD IDENTIFIED H, S, E RR BY WHOM RR
HAZARD DEALT WITH WHEN
8 Unsafe steel cutting. Electrocution Ensure hot work permit prior to Supervisor / During
Fire and burns work Operative work
Eye or hearing injury Place steel on the ground
Puncture wound cautiously, never throw it.
Slip, trip or fall on to steel Ensure feet are clear when
Cut and lacerations placing steel.
Fire and explosions. Wear leather heavy duty gloves,
Failure of equipments or power Suffocation from fumes. Safety boots, eye and hearing
tools Potential death protection
All column starter bars to be fitted
with caps
Machinery to have guards in
place and be well maintained.
Proper handling and firm grip by
the operator to be ensure to
10 avoid jerking and strike to
H,S,E 3
operator and nearby operatives.
Use fire blanket and remove the
combustible materials in the area
Use the appropriate PPE to
ensure safe working procedure.
Provide adequate mechanical
Environmental damage fume extraction or forced
Environmental concern ventilation wherever work is
Dust, fumes and noise exposure carried out.
Noise levels to be monitored and
restricted to social able timings
where ever practicably possible.
Noise and dust could cause
potential environmental damage.

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 11 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

RISK ASSOCIATED WITH Impact HOW IS HAZARD TO BE BY Result


No HAZARD IDENTIFIED H, S, E RR BY WHOM RR
HAZARD DEALT WITH WHEN
9 Unsafe fixing of steel Cuts and abrasions Tie wire to be fitted firmly, ensure FM/ Before
reinforcement. Wire snaps under pressure that it is not tightened too greatly Supervisor and
Puncture wound Tie wire to be bent in / down during
Slip, trip or fall on to steel Ensure use correct length of wire work
Potential death Enforce concentration on work.
UV exposure due to outdoor All column starter bars to be fitted
works Heat exhaustions with caps
Heat cramps Ensure use correct pliers
10
H 2
Increase the intake of water,
provide shaded areas and
schedule the work on cooler part
of the day.
All employees to wear PPE,
(shade brim on safety helmet,
30+ sunscreen, sunglasses,
safety boots, heavy duty gloves
and hearing protection)
10 Not providing safe access Trip, slips and fall on steel 10 Enforce installation of safe plank Supervisor Always
H, S 2
walkways on steel walkways on steel slabs.
11 Cuts and abrasions Provide safe working platform or FM/ Before
Skeletal damage good standard scaffolding. Supervisor and
Fall from height Scaffold erected by competent during
Potential death scaffolding erectors. work
Fail to adhere safe procedure for
Fall of materials. Use step ladder and follow the
fixing steel for columns and core H,S 3
Property damage 12 safe usage.
wall at height and on edges
Use full body harness while
working at heights.
Materials and workers to be
protected from falling.

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 12 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

* RR = Risk Rating

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 13 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

WRITTEN SAFE WORK PROCEDURE


1. OBJECTIVE
1. To prevent injuries to employees and / or property damage incidents.

2. PROCEDURE
1. Do pre-use inspection of all equipment to be used and replace or repair faulty items.
2. Use trained competent employees only.
3. Use appropriate Personal Protective Equipment i.e.:
3.1. Hardhat.
3.2. Safety boots.
3.3. Overalls.
3.4. Eye protection.

Prior to work commencement

1. Must have PPE – safety footwear, gloves, hardhat, goggles, protective clothing etc.
2. Must have appropriate tools and equipment in good condition.
3. Must have weatherproof covers for materials and equipment, waste containers, warning tape.
4. Consider risks and hazards in work area. Refer any concerns to supervisor. Are relevant permits in place?
5. Check if it is necessary to secure area adjacent to work. Refer to supervisor if appropriate.
6. Arrange for transport of materials and equipment to site via supervisor.
7. Ensure materials and equipment are secure or removed when site unattended, eg overnight or during breaks.

Hazards
HSE/QUALITY SYSTEM DOCUMENTATION
DOC No DS/CA006P02/00021
PAGE No 14 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

1. Manual handling of materials and equipment – LITE to be considered at all times.


2. Slips and trips from untidy work area.
3. Fall from height. eg. Working at heights.
4. Falling materials, eg. Steel, angles, welding rod, tools, etc.
5. Collapse of existing structures, eg steel structure, scaffolding structure.
6. Hazards associated with equipment used for welding, eg. Electric shock, striking of equipment, etc.
7. Contact with sharp edges, eg. Steel cutting.
8. Consideration of weather and ground conditions must be made. If in doubt refer to supervisor.
9. Environmental damage.
10. Fire hazard.

Harm
Potential Death, Minor/major cuts and contusion, loss of limbs, fractures, damage to respiratory system, electric shock.

Persons in danger

1. Steel fixers,
2. Supervisors
3. Other workers/visitors in vicinity.

Control measures

No lone working

HSE/QUALITY SYSTEM DOCUMENTATION


DOC No DS/CA006P02/00021
PAGE No 15 of 15
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name:   Festival Living Stream-02 HSE-RA 019
Job Description: Steel Fixing

1. Use appropriate Personal Protective Equipment:


i. Hardhat.
ii. Safety boots.
iii. Overalls.
iv. Eye protection.
v. Dust mask.
vi. Fall protection (full body harness).
2. When off loading steel by hand, ensure:
i. Employees to use gloves
ii. Ensure enough employees for weight of steel.
iii. Taking up correct position.
iv. Ensure proper stacking.
v. Never walk on steel during placement of re-bar, place planks to walk on.
vi. Steel fixers to ensure that they take up proper positions and have firm footing before lifting re-bar in place.
vii. All persons working in elevated positions must make use of full body safety harnesses.
viii. When using scaffolding ensure to adhere to scaffold procedures.

1. Grinder and gas cutting works to be done under hot work permit system
2. Use binding wire in the correct manner and never cut with a grinder.
3. Use the correct cutter / pliers that is in good condition.
4. Beware of hand and finger injuries when binding.

HSE/QUALITY SYSTEM DOCUMENTATION