Electromechanical Meter Testing Guide
Electromechanical Meter Testing Guide
2
Meter
1 Meter
1.1 About Meter
Meter is a test module for testing electronic and electro-mechanical energy
meters with a meter class of up to 0.2S1 for the following types:
• Watt-hours (Wh)
• var-hours (varh)
• VA-hours (VAh)
• V-hours (Vh)
• V2-hours (V2h)
• I-hours (Ih)
2
• I -hours (I2h)
• Q-hours (Qh)
The Q-hour meter is a regular watt-hour meter that is installed with the
potential circuits wired one phase behind the standard watt-hour
connection (lagging the watt-hour connection by 60 degrees).
• Multifunctional, i.e., meters with more than one pulse output and various
physical quantities of the above-mentioned types.
Once the parameters for a particular meter have been entered in the module's
test object parameter section, the data can be saved to be used again later. For
the test, a meter is connected to the OMICRON CMC test set and its
corresponding data file is reloaded.
Meter can be used with the following test equipment:
• CMC 56
• CMC 156
• CMC 151
• CMC 256
• CMC 256plus
If the meter under test has more than one output, all of these outputs can be
connected to the CMC's binary inputs at the same time. Meter is then configured
accordingly and measures these outputs sequentially.
3
OMICRON Test Universe
0 1 2 3 4 5 6 7 8 9
test object
reference meter
reference measurement
t
1 2 3 6
4 7
5
4
Meter
1. Warm-up time:
– If the test is started with the icon, the specified warm-up time
precedes the actual test.
– If the button N O M I N A L V O L T A G E O N is pressed prior to the test
and the test is started later, the specified warm-up time is ignored. In
this case the warm-up time is the time period between switching on the
nominal voltage manually and the start of the test.
2. Start-up time: Here the values that are set in the following test line are
output but pulses are not yet recorded.
3. The specified start-up time has elapsed: The start-up time is delayed until
the meter under test outputs a pulse.
4. The first pulse received after the specified start-up time has elapsed is the
initialization pulse that starts the actual test. However, this pulse is not
counted.
The time measurement for the meter under test is started.
5. If the test is carried out with a reference meter, the time measurement for
the reference meter is started with the first pulse received from the
reference meter after the initialization pulse of the meter under test.
6. When the pulse specified under "Pulses | Nominal" (here pulse number 9)
is received, the end of the first test line (line 1 in the test table) has been
reached and the program goes to line 2. The time measurement stops
when the last pulse is received. Now the time for the test object
measurement is known. Independently of the mode, the next test line
starts with the start-up time again (topic 2).
7. If the test is performed with a reference meter, the first pulse of the
reference meter received after the stop pulse of the meter under test is
the stop criterion. Until this moment, the generators remain switched on.
Now the time for the reference measurement is known. Normally this time
will differ slightly from the time of the test object measurement. To obtain
exactly the same time base for both measurements, the energy value of
the reference meter is corrected by calculating the meter error by the
factor tTO / tRef.
The test continues with the next test line with no interruption of the voltage.
When the last test line is reached, the voltage remains switched on if the button
"Nominal Voltage ON" was set.
Otherwise the voltage is switched off after the last test line is passed.
5
OMICRON Test Universe
Task
A three-phase meter with the ML266 (Landis & Gyr) induction measuring
element is to be tested.
The meter measures "active power import" (Wh.-exp.) and has a backstop for
the other energy direction. The rotations of the meter disk are read optically with
a photoelectric pick-up head.
The meter is used in a three-phase four-wire system and is connected to the test
set accordingly. The meter is connected directly to the voltages (3 x 220 V L-N)
and via a 100/5 current instrument transformer.
The specifications of the meter are as follows:
• Three-phase four-wire meter for active power
• One energy direction
• Accuracy: class 0.5 s
• Meter disk for a pick-up of the rotations
• Vnom: 3 x 220 V / 380 V
• Inom: 5 A
• Primary pulse rate: 37.5 rotations / kWh which results in 750 pulses / kWh
secondary
• Pulse width of the pick-up head: approx. 1 ms
6
Meter
The following test steps are carried out, based on the PTB standard:
• Accuracy test for a number of specified test points
• Test the creep behaviour
• Test the no-load behaviour
• Check the counting mechanism
A CMC 256 test set with the Meter software module and accessory equipment
(consisting of CMLIB B, power supply for CMLIB B, photoelectric pick-up head
SH2003 and connecting cables) is available for the test.
According to the test procedures of the user, a reference meter must be used.
For this purpose the three-phase TVE 102/3 (Landis & Gyr) meter is available.
Solution
The test is carried out with the following steps:
7
OMICRON Test Universe
CMLIB B
B A
TVE 102/3
Reference Meter
ML 266
Optical
Meter to be tested pickup
SH 2003
8
Meter
9
OMICRON Test Universe
Values are:
Defines the entries and readings as primary or secondary values.
Warm-up time:
Defines the time period during which the nominal voltage is output to the
voltage inputs of the meter.
This period allows the meter to reach its operating temperature prior to the
beginning of the actual test. In particular for class 0.2 meters, an appropriate
warm-up time is important, because the influence of the operating
temperature on the meter error is the highest for such meters (for warm-up
times see the manufacturer's description or DIN EN 61 036, 5/7, section
3.6.13).
Note: If the nominal voltage is manually switched on prior to the test (Test
tab at Test View) and the test is then started, the warm-up time is ignored.
10
Meter
Start-up time:
Defines the time that immediately follows the warm-up time without any
interruption of the voltage. During the start-up time, the quantities defined for
the subsequent test line are output. The meter starts to output pulses. The
first pulse after the start-up time has elapsed is the initialization pulse
(number 0) for the start of the test.
Ambient Temperature and Relative Humidity:
Define the values of the ambient temperature and the relative humidity.
These values later appear in the test report.
The TVE 102/103 meter is used as the reference for the test. Select "Use
Reference Meter" and click the N E W button to define the reference meter.
Figure 1-4:
Defining a new
reference meter
In this example, the reference meter has three different meter constants based
on the current input range.
When you have finished defining the reference meter, click O K to return to the
Settings tab.
Note: To make the settings of this reference meter available for other tests, save
them to a text file (*.rmf). You can do this with the E X P O R T button in the
Settings tab.
The settings of several meters can be saved together in one .rmf file. The data
of the reference meter you have just defined are shown in Figure 1-5.
11
OMICRON Test Universe
Figure 1-5:
Extraction from a .rmf
file
This reference meter can now be used for future tests by importing this file.
Switch to the Test tab in order to define the test lines.
Step 1
The error limits are verified (accuracy test). According to the PTB standard, the
load points in Table 1-1 will be output for all measurement quantities.
Table 1-1:
Three-phase four-wire Three-Phase Four-Wire System Meter for Active Power Consumption
system meter for active
power consumption
P Load current (in % of In) cos ϕ Error limit
(% of PN) I1 I2 I3 (%)
0.05 0.05 0.05 0.05 1 0.5
0.1 0.1 0.1 0.1 1 0.5
0.05 0.2 0.2 0.2 0.25 1.0
0.067 0.2 0 0 1 0.6
0.067 0 0.2 0 1 0.6
0.067 0 0 0.2 1 0.6
0.25 0.5 0.5 0.5 0.5 0.5
1 1 1 1 1 0.5
12
Meter
13
OMICRON Test Universe
After defining the 8 load points, the dialog box appears as in Figure 1-7.
Figure 1-7:
Test View 1
Note: The Detail View, shown in Figure 1-8, is not needed to define symmetrical
loads (test points 1-3, 7, 8). If the currents of the individual phases are different
(test points 4-6), open the Detail View to enter the current values.
The permissible error limits depend on the particular load point and must be
defined for every line individually in the "Tolerance" input field. The number of
test runs should be 1 for all test lines.
Figure 1-8:
Detail View
14
Meter
Step 2
The next step is testing the creep behaviour, i.e., testing whether the meter
starts or not. The "Creep" test mode must be selected and, according to the PTB
standard, a load current of 0.005 x IN = 25 mA must be output at cos ϕ = 1.
This test can be performed with either a single pulse as passed/failed criteria or
the necessitiy of an additional pulse.
This test line is inserted into the test table as line 9 shown below.
Figure 1-9:
Test View 2
15
OMICRON Test Universe
Step 3
The no-load behaviour is tested. For this test, the "No-Load" test mode is
selected, the voltage is set to 110 V (L-L) and the test time is set to 300 s. The
current in all phases is 0 A and the voltage is between 80 % and 110 % of the
nominal voltage (according to the PTB standard).
For this test to be assessed as "passed," the meter disk must not make a
complete rotation. The standard does not specify the duration of the test period;
so choose 5 minutes.
This test can be performed with either no pulse or max. one pulse as passed/
failed criteria.
Note: The assessment of this test is rigorous. If the option "Accept one pulse in
the no-load test" is not selected, and one pulse is registered, the meter is
considered moving/started, and the assessment is negative ("test failed").
Depending on the position of the mark on the meter disk, even a very small
movement of the meter disk can result in the registration of a pulse; e.g., if the
mark was near to the pick-up head at the beginning of the test.
We recommend to select the option "Accept one pulse in the no-load test". This
way Meter accepts exactly one pulse and still assesses the test as "passed".
Figure 1-10:
Test View 3
Please note that now the test mode "No-Load" is selected, the voltage is set to
110 V (L-L) and the test time is set to 300 s.
16
Meter
Step 4
In the fourth and last step the counting mechanism is tested.
For this purpose 10 kWh at nominal load is output to the meter. The necessary
time (3 hours, 1 minute and 50 seconds) is calculated by the software and
displayed in the field "Nominal Time."
Note: At the beginning of this test line, a dialog box appears where you enter the
meter reading at the beginning of the counting mechanism test. This dialog box
appears again at the end of the test where you enter the meter reading at the
end of the test. The error of the counting mechanism is calculated based on the
entered values.
The complete test appears as in Figure 1-11.
Figure 1-11:
Test View 4
The test can be started. The test lines in the table are performed beginning at
test line 1. The results of each test line are entered into the table immediately
after the test line is finished.
17
OMICRON Test Universe
etc.
At the end of line 6 an information box appears prompting you to change the
input range of the reference meter:
18
Meter
Figure 1-13:
The test is paused
The test continues with line 7 after the input range has been changed and the
C O N T I N U E button has been pressed. Line 11 (counting mechanism test)
requires manual input as well.
Figure 1-14:
Counting Mechanism
Test dialog box
When the test is finished, the results are available for the report.
19
OMICRON Test Universe
20
Meter
The report can either be printed or exported to a file in RTF format (Rich Text
Format). The file is later available for further processing with other programs
(e.g., Word for Windows).
21
OMICRON Test Universe
22
OMICRON Service Centers
Asia – Pacific
OMICRON electronics Asia Ltd.
Suite 2006, 20/F, Tower 2
The Gateway, Harbour City
Kowloon, Hong Kong S.A.R.
Phone: +852 3767 5500
Email: [email protected]
Web: www.omicron.at
For address details of other OMICRON Service Centers in your area, please visit our
website www.omicron.at or www.omicronusa.com.
23
OMICRON Service Centers
24