TECH ART SDN BHD V METROPOLITAN BUMI SDN BHD
TECH ART SDN BHD V METROPOLITAN BUMI SDN BHD
Counsel:
For the plaintiff: K Selva Kumaran (Shankar Gunaratnam and Yau Jie Luan with
him); M/s Rose Hussin
For the defendant: Balbir Singh (Daniel Ong with him); M/s Najiana Wan Balbir
[Order accordingly.]
JUDGMENT
Aliza Sulaiman J:
[1] The need for legal practitioners to have a firm grasp of the rules of
pleadings cannot be understated. This case serves as yet another reminder on
the significance of pleadings in civil suits. Basically this case involves the claim
for costs, fees and other items by the Plaintiff, who is the main contractor for
the construction of a university campus in Rembau, Negeri Sembilan, against
the Defendant, the sub-contractor for the project. The Defendant denied
liability for the claims and it also pleaded the right to set off the amount of the
Plaintiff's claim against the higher amounts which was purportedly owed by
the Plaintiff to the Defendant.
[2] This Grounds of Judgment contains the full reasonings of the Court in
respect of the following:
(ii) t h e D e f e n d an t ' s c o u n t er c l a i m f o r t h e su m o f
RM6,838,927.08 was allowed with interest at the rate of 5%
per annum from the date of filing of the Counterclaim (on 3
October 2018) until full settlement. This amount was allowed
to be set off against the sum as stated in subpara (i) above; and
application in encl 153. The said sum and the accrued interest thereon
shall be released in accordance with the order that will be made by the
Court of Appeal. Cost was ordered to be in the cause of the Plaintiff's
appeal.
[3] The Plaintiff is a company incorporated under the laws of Malaysia and
has its main business address at B-5-7, 5th Floor, Block H, Ostia Bangi
Premier Business Avenue, Jalan Ostia Utama, Seksyen 14, 43650 Bandar Baru
Bangi, Selangor Darul Ehsan.
[5] Konsesi Kota Permatamas Sdn Bhd ('KKP') had, vide the Letter of Award
dated 8 May 2013 ('KKP's LoA'), appointed the Plaintiff as the main
contractor of the total development for the project known as "Proposed
Development & Construction of UiTM Campus On Lot 472, Mukim Kundor,
District of Rembau, Negeri Sembilan Darul Khusus On Private Finance
Initiative (PFI) Basis" ('Project') for the lump sum fixed price of RM230
million. The construction period was 30 months from the date of site
possession.
[6] On the same date, the Plaintiff issued the Letter of Award to irrevocably
appoint the Defendant as the Sub-Contractor, Management Consultants and
Payment Agents for a range of works ('LoA').
[7] Clause A(i) of the LoA states that the contract sum shall be a lump sum
fixed price of RM108,811,854.83. The detailed scope of works can be found in
the same clause which is re-produced below:
Tech Art Sdn Bhd
pg 4 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
"C....
...
2. Payments for all works under Item A above including all differences
between our contract sum to you and the contract sum to NSCs shall
be made to you within 7 working days from the receipt of our claims
subject to 3 (a), (b), (c) and (d) below and such payments to the NSCs
appointed by you at the contract sum determined by you and after the
proportionate deduction of our 2% profit and attendance.
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 5
...
i. CIDB levy;
[9] Among the agreed facts for purposes of the trial are that
(a) the Defendant does not dispute the percentage rate of 47.3% as
stated in the LoA;
(b) the Defendant agreed to pay the Plaintiff the profit and attendance
fee for all the subcontractors which were nominated by the Defendant
to carry out the works at site for the sum of RM447,972.48;
(c) the Plaintiff has the right to profit and attendance fee on the
following subcontractors nominated by the Defendant:
(d) at the Defendant's request, the Plaintiff had advanced the sum of
RM2.5 million to the Defendant to help the Defendant to bear the
expenses for the Project ('Loan');
[11] The Plaintiff had filed an application for summary judgment against the
Defendant. On 2 October 2018, Lee Swee Seng J (now JCA) allowed the
Plaintiff's application whereby the Defendant is to pay to the Plaintiff, among
others, as follows:
[12] The learned Judge had summarily decided that the Plaintiff was entitled
to 27.4% of the total amount which was claimed by the Plaintiff for the
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 7
insurance premium, CIDB levy, stamp duty and the Loan and the rest (19.9%
of the amount as prayed) is to be decided at the trial. Hence, for these items,
the only issue is on quantum as the issue of liability has been decided by the
learned Judge.
[13] In the Annexure to the Agreed Issues For Trial, the Defendant does not
dispute liability for the following claims:
(c) the outstanding amount for the Loan in the sum of RM520,305.46
(RM1,237,500.01 - RM717,194.55).
[14] The total sum that was admitted by the Defendant is thus RM698,013.92.
[15] The trial was held for 14 days where the Court heard the evidence of the
following witnesses:
[16] The Issues To Be Tried which were agreed by the parties are as follows:
Tech Art Sdn Bhd
pg 8 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
1. Whether the Plaintiff had paid the amounts claimed towards the
Contractor's All Risk Policy for this Project?
2. Whether the Defendant is liable to pay the Plaintiff for the provision
of the Hyundai Starex, Perodua Kembara and rental cars under the
Letter of Award?
3. Whether the Defendant is liable to pay the Plaintiff for the Gross
Floor Area difference under the Letter of Award? And if so, how
much?
4. Whether the Defendant has shown that the Plaintiff owes any
amounts to the Defendant under the Letter of Award for the Project?
5. And if so, whether such amounts are due and payable to the
Defendant at the time of filing of the counterclaim.
6. If due and payable, whether such amount can be set-off against the
Plaintiff's claim (if successful).".
1st Issue: Whether The Plaintiff Had Paid The Amounts Claimed Towards
The Contractor's All Risk Policy For This Project?
[17] The Defendant admits its liability to reimburse the Plaintiff for this
expense, however the Plaintiff is put to strict proof in terms of quantum (see
paras 16 and 17 of the Amended Statement of Defence And Counter-Claim
('Amended Defence and CC') and the decision in the summary judgment
application).
[18] Midway through the trial and for the purpose of narrowing the issues, the
Defendant agreed not to dispute the percentage rate of 47.3%. This means that
the quantum representing 47.3% of the expenditure for the insurance premium
is RM115,326.86.
[19] The sole challenge raised by the Defendant in this regard was that the
policy or its cover-note was not produced at the trial. Furthermore, even
though the Plaintiff did produce the receipts of payments issued by MAA
Takaful Berhad ('MAA') (see pp 71 - 75, B1), none of the receipts show that
the sums received by MAA were in respect of the "Contractor All Risk" Policy
as alleged by PW3 in her answer to Question 7, WS-PW3.
[20] The Defendant submitted that, while the receipts show that some sort of
payment was made to MAA, there is no evidence that MAA received the same
in consideration of any purpose related to the Project as envisaged by Clause
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 9
C.3.c. of the LoA. Hence, the claim for the reimbursement of 47.3% of the
alleged insurance premium payment has not been made out.
[21] I have considered the oral evidence of PW3, PW4 and DW3 on this
matter and the documentary evidence at pp 71 - 75, B1 and I find that there
are:
[22] At the clarification session with the learned counsels, the Court had
pointed out the absence of MAA's invoice and the Plaintiff's Payment Voucher
for the sum of RM36,580.00.
[23] MAA's receipt dated 12 September 2013 merely shows that it is payment
for Cover Note TG13 - 0004175 whereas the invoice issued by MAA dated 26
August 2013 for the total sum of RM207,240.00 and the receipt dated 12
September 2013 for that amount shows that it is not only payment for Cover
Note TG13-0004176, but the words "Contractor All Risk" and the name of the
project are stated in MAA's invoice for the sum of RM207,240.00 and the
Plaintiff's Payment Voucher dated 2 September 2013.
[24] It is also observed that, vide letter dated 2 October 2013 to DBA Akitek
(M) Sdn Bhd and copied to KKP, the Plaintiff had forwarded the original
insurance policy for Contractor's All Risks and Workmen's Compensation to
the Architect for safekeeping (see p 70, B1). The original or a copy of the
insurance policy was not tendered in court.
[25] As the Defendant had pleaded that the Plaintiff is put to strict proof as to
quantum and the Plaintiff has not discharged the burden of proof to establish
that the MAA receipt dated 12 September 2013 was issued for the Contractor's
All Risk premium for the Project, the Court had allowed the Plaintiff's claim
Tech Art Sdn Bhd
pg 10 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
2nd Issue: Whether The Defendant Is Liable To Pay The Plaintiff For The
Provision Of The Hyundai Starex, Perodua Kembara And Rental Cars Under
The Letter Of Award?
[26] As opposed to the 1st Issue, the quantum in relation to the Plaintiff's
claim as to the provision of vehicles is not disputed and the Defendant's
challenge is on the aspect of liability.
(a) provided the Hyundai Starex (W 5635 D) for the UiTM staff;
(b) provided the Perodua Kembara (NBE 7773) for the use of the
Consultants for the Project; and
[28] In addition, the Defendant agreed that, if the Defendant is found liable for
this claim, the sum to be paid is as pleaded in para 10 of the Amended
Statement of Claim ('Amended SoC') ie RM96,422.15 on 100% basis
(RM67,451.00 for the Hyundai Starex, RM25,158.60 for the Perodua
Kembara and RM3,812.55 for the rental of cars).
[29] Mr Balbir Singh's argument for the Defendant was mainly premised on
the point of pleadings. The attention of the Court was drawn to para 9 of the
Amended SoC and the fact that the relevant clause of the LoA on which this
liability arises is not mentioned.
(English translation:
"Pursuant to the Letter of Award, the Defendant has agreed with the
Plaintiff to jointly bear the vehicle costs which are necessary for the
Project as well as transportation costs.").
[31] The Defendant's counsel then referred to WS-PW3 and the answer to
Question 21 in contending that, at the trial, the Plaintiff completely abandoned
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 11
its pleading and sought to justify the claim on a different and unpleaded basis
that the Defendant had instructed the Plaintiff to provide the vehicles. The
relevant excerpt from the Witness Statement is shown below:
"21: Why did the Plaintiff charge the whole costs of transportation to
the Defendant?
A: This is due to the fact that the agreement between the Plaintiff and
the Defendant does not provide for the costs for the transportation to
be borne by the Plaintiff. In fact, as for the Hyundai Starex, I was
instructed by Nik and Datin Salmah to procure the said vehicle for the
use of the UiTM staff. As for the Perodua, I was instructed by Puan
Yasmin bin Zolkifly to purchase the said vehicle for the usage of the
project consultants. I was instructed by the Plaintiff's Board of
Directors to charge the Defendant for the entire costs of transportation
including the rental.".
(b) that PW3 had testified during re-examination that the provision of
the vehicles was not in the Plaintiff's preliminaries and so, it must be
the balance of the contract. PW3 is said to have given a correct version
of the events surrounding the provision of transportation which is
uncontroverted by the Defendant;
(c) that PW4 had given the following evidence in her Witness
Statement:
project."; and
(d) the presumption in s 114(g) of the Evidence Act 1950 [Act 56]
should be invoked against the Defendant for its failure in not calling
Datin Salmah as a witness.
[33] The Court has considered the submissions of the parties concerning this
claim and is in agreement with the Defendant that the Plaintiff has failed to
prove, on a balance of probabilities, that the Defendant is liable for this claim.
The justifications for this finding are as follows:
(a) The Plaintiff submitted that the basis for the claim is the fact that DW3 and
Datin Salmah, who is DW3's wife, had requested and/ or instructed for the
transportation to be provided. Consequently, the Plaintiff had procured, and
the Defendant's staff and consultants had used, the vehicles. As the costs for
the transportation were not factored into the LoA, these would have to be
borne by the Defendant pursuant to the relationship created between the
Plaintiff and Defendant under the LoA.
It is obvious that the alleged request and/ or instruction by DW3 and Datin
Salmah is nowhere to be found in the Amended SoC and the Amended Reply
and Defence to Counterclaim. It is clear from paras 9 to 11 of the Amended
SoC that the basis for the claim as contended by the Plaintiff at the trial is not
reflected therein. This has led the Defendant to plead its defence in the manner
as can be seen in paras 19 to 28 of the Amended Defence and CC, namely
that:
(i) even if the Defendant is to reimburse the Plaintiff for the value of
the Hyundai Starex and Perodua Kembara, the Defendant's liability is
only until 3 January 2017 and the value of the vehicles as at that date
must be accounted for;
(ii) the Plaintiff's liability to account for the value of the two vehicles
arises because the Defendant has acquired a right of ownership to the
vehicles and the Plaintiff would otherwise be unjustly enriched (s 71 of
the Contracts Act 1950 [Act 136] was cited); and
(iii) it is an implied term of the LoA that the Plaintiff must account for
the value of the two vehicles if the Defendant is to indemnify the
Plaintiff for the cost of the acquisition and maintenance of the
vehicles, the particulars of which were pleaded in para 24C.
By pleading the Plaintiff's case in the way that it did, the Defendant
had no opportunity, and in fact had no good reason, to plead its case
in defence to the allegations surrounding the request and/ or
instruction by DW3 and Datin Salmah and what were the terms of the
agreement between the parties, if any, on the costs associated with the
provision of the transportation. If this Court was to decide in favor of
the Plaintiff as to liability for this claim, there would be a failure of
natural justice as the Defendant is denied the right to present its case
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 13
fully on the unpleaded issue before the decision is made. It is not the
duty of the court to make a case for a party when that party does not
raise or wish to raise a point in the litigation (see Janagi v. Ong Boon
Kiat [1971] 1 MLRH 360; [1971] 2 MLJ 196 and RHB Bank Bhd
(substituting Kwong Yik Bank Bhd) v. Kwan Chew Holdings Sdn Bhd
[2009] 3 MLRA 162; [2010] 2 MLJ 188; [2010] 1 CLJ 665).
pleadings have the effect of not only binding the parties, inter
se, but it also operates to ensure that the court only grants the
reliefs that have been prayed for as pleaded as forming the
Plaintiff's causes or causes of action. There may be exceptions
to this rule of the thumb, but only rarely will the courts depart
from this crucial rule of civil litigation.".
[Emphasis Added]
Applying the legal principles as above quoted to the instant case, there
is no doubt in my mind that the Plaintiff had abandoned its pleaded
case and set up an entirely new case during the trial.
(c) Section 114(g) of the Evidence Act 1950 [Act 56] provides that:
114. The court may presume the existence of any fact which it thinks
likely to have happened, regard being had to the common course of
natural events, human conduct, and public and private business, in
their relation to the facts of the particular case.
...
..."
However, the Court is of the view that the application of the presumption in
the circumstances of this case is not justified because the fact that Datin
Salmah had requested and/ or instructed for the purchase and rental of the
vehicles was not even pleaded by the Plaintiff. Moreover, DW1 was called to
testify for the Defendant and yet the Plaintiff's counsel did not question DW1
as to the request and/ or instruction which he allegedly gave to PW3 as well
on the procurement of the Hyundai Starex and whether there was any
agreement between the parties on the issue of costs for the provision of the
vehicles, and if so, what were the terms of the agreement.
3rd Issue: Whether The Defendant Is Liable To Pay The Plaintiff For The
Gross Floor Area Difference Under The LoA? And If So, How Much?
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 15
[34] The same issue on pleadings bears relevance to the 3rd Issue. In para 15 of
the Amended SoC [Emphasis Added], the Plaintiff pleaded as follows:
(English translation:
"Through the Letter of Award, the Defendant has to pay the Plaintiff
the difference of contract sum as a result of the changes in the
measurement of Gross Floor Area. The changes of this Gross Floor
Area caused the need of the Defendant to pay the Plaintiff for the sum
of RM4,291,071.76").
[35] As the aforesaid statement makes reference to the LoA, the Defendant
firstly denied the Plaintiff's averments and went on to plead that:
32B. Further, todate, the Plaintiff has yet to provide the 'as-built
drawing' and other plans to show fully what is the actual gross floor
area that was constructed. Therefore, even if the Defendant is to
indemnify the Plaintiff, the Defendant is unable to study what the new
area is."
[36] In its Amended Reply, the Plaintiff stated that it will refer to the
correspondence between the parties to prove its claims during the trial and that
all the as-built drawings had been provided to KKP, which is the Defendant's
alter ego.
[37] Basically, the Plaintiff claimed for the difference between the Agreed
GFA and the Actual GFA on site, which was calculated by PW1, the
Quantity Surveyor who was appointed by the Plaintiff vide the letter dated 19
March 2019 to calculate the GFA for the Project. In order to carry out his task,
PW1 was furnished with the as-built drawings which are listed in Appendix C
to PW1's Expert Report (see PB4 and PW1's Affidavit as the Plaintiff's expert).
[38] The Agreed GFA of 51,161 m² can be seen in Appendix 1 to the
Tech Art Sdn Bhd
pg 16 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
We hereby agree that within 6 weeks from the date of our receipt of
the full contract drawings and pricing document from our Employer
but not later than 15th of July 2013, we shall confirm whether we
could agree to your proposal for the joint venture. Upon our
confirmation in writing to you of our election to undertake our scope
of works totally on a joint venture with you, you shall be bound to
irrevocably accept the same on the following terms and conditions:
...".
"We wish to refer to Clause Item F - Proposal for Joint Venture in our
Letter of Award to you dated 8 May 2013 with regards to the above
matter.
...".
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 17
[40] Appendix 1 to the 19 September 2013 Letter sets out the breakdown of the
preliminary cost estimate for, among others,:
[41] The Agreed GFA of 51,161 m² is also set out in the copy of the
Preliminary Detailed Abstract which was enclosed to the Plaintiff's letter dated
30 May 2017 to the Defendant regarding the claim for differences in GFA.
[43] The Defendant's first line of defence against this claim is, again, on
pleadings. It was submitted that, contrary to the Plaintiff's own pleading, there
is nothing in the LoA which provides for any additional payment to the
Plaintiff by the Defendant arising from any increase in the GFA.
[44] The Plaintiff seems to accept this position since, in para 35 of its Reply
Submission, the Plaintiff "... reiterates that the right to claim the difference in
the GFA arises from the letter dated 19 September 2013...", however this "...
should be read with the Letter of Award to the Defendant dated 8 May 2013
specifically in response of Clause F - Proposal for Joint Venture.".
[Emphasis Added]
(a) the Defendant did not reply or make any objections to the 19
September 2013 Letter. Hence, by relying on the decision by the Court
of Appeal in David Wong Hon Leong v. Noorazman Adnan [1995] 1
MLRA 708; [1995] 3 MLJ 283; [1995] 4 CLJ 155 wherein reference
was made to the judgment of Lord Esher MR in Wiedemann v.
Walpole [1891] 2 QB 534 where His Lordship said that, in business
and mercantile cases, the courts have taken notice that "... in the
ordinary course of business, if one man of business states in a letter to
another that he has agreed to do certain things, the person who
receives that letter must answer it if he means to dispute the fact that
he did so agree." (see too, Small Medium Enterprise Development Bank
Malaysia v. Lim Woon Katt [2017] 1 MLRA 206; [2016] 5 MLJ 220;
Tech Art Sdn Bhd
pg 18 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
[2016] 9 CLJ 73), the Plaintiff posited that the non-denial of the 19
September 2013 Letter means that the Defendant had agreed to pay
the difference in the GFA;
(b) the Defendant also did not reply or make any objections to the
letter dated 30 May 2017 from the Plaintiff to the Defendant ('30 May
2017 Letter'). In the 30 May 2017 Letter, the Plaintiff referred to the
LoA and the 19 September 2013 Letter, specifically to item 1 which ".
qualifies that our confirmation of contract amount for building works
is to be derived from the agreed GFA...". The Plaintiff claimed for
RM1,426,184.20 for the differences of 1,191 m2 between the agreed
GFA and the actual on site based on the consultants' latest drawings.
The non-denial of the claim in the 30 May 2017 Letter shows that the
Plaintiff could charge the Defendant for the difference in GFA;
(c) the Plaintiff has sufficiently pleaded its claim for the difference in
GFA in the Amended SoC;
(d) the Defendant failed to request further and better particulars with
regards to the Amended Reply. Therefore, the Plaintiff is entitled to
refer to the 19 September 2013 Letter and the 30 May 2017 Letter
which constitute a separate or collateral contract and exists side by
side with the LoA. Citing the cases of Tindok Besar Estate Sdn Bhd v.
Tinjar Co [1979] 1 MLRA 81; [1979] 2 MLJ 229, Industrial &
Agricultural Distribution Sdn Bhd v. Golden Sands Construction Sdn Bhd
[1993] 5 MLRH 610; [1993] 3 MLJ 433 and Tan Swee Hoe Co Ltd v.
Ali Hussain Bros [1979] 1 MLRA 71; [1980] 2 MLJ 16, the device of
collateral contract "... does not offend the extrinsic evidence rule
because the oral promise is not imported into the main agreement.
Instead it constitutes a separate contract which exists side by side with
the main agreement."; and
[47] There is absolutely no mention of the 19 September 2013 Letter and the
30 May 2017 Letter in the Amended SoC. Whilst the Plaintiff states in its
Amended Reply that it will refer to "the correspondence between the parties to
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 19
prove its claims during the trial", this goes to show the Plaintiff's intention of
producing certain correspondence as evidence, the details of which were
undisclosed, but as submitted by the Plaintiff, the Defendant could have
applied for further and better particulars. Nevertheless, this does not invalidate
the Defendant's argument that the Plaintiff must specifically plead and identify
its cause or causes of action against the Defendant in the SoC (see Yap Seong
Yee v. Eureka Property Management Sdn Bhd and another appeal [2018] 4
MLRA 560; [2018] 6 MLJ 799; [2018] 8 CLJ 713).
[48] In this regard, O 18, rr 7(1), 8(1) and 10 of the Rules of Court 2012 ('RC
2012') provide that:
7. (1) Subject to the provisions of this rule and rr 10, 11 and 12, every
pleading shall contain, and contain only, a statement in a summary
form of the material facts on which the party pleading relies for his
claim or defence, as the case may be, but not the evidence by which
those facts are to be proved, and the statement shall be as brief as the
nature of the case admits.
...
(c) which raises issues of fact not arising out of the preceding
pleading.
...
Departure
10. (1) A party shall not in any pleading make an allegation of fact or
raise any new ground or claim inconsistent with a previous pleading of
his.
(2) Paragraph (1) shall not be taken as prejudicing the right of a party
to amend, or apply for leave to amend, his previous pleading so as to
plead the allegations or claims in the alternative.".
Tech Art Sdn Bhd
pg 20 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
[49] It is trite law that a plaintiff must not set up in his reply a new cause of
action which was not raised in the Writ or the SoC, or in other words, the
reply must not contradict or depart from the SoC (see Mat bin Lim & Anor v.
Ho Yut Kam & Anor [1966] 1 MLRH 682; [1967] 1 MLJ 13). A plaintiff who
intends to set up a new or an alternative basis to his claim is required to make
an application to amend the SoC and he cannot, supplement his SoC by
including in his reply, matters which ought to have been included in the SoC
(see the function of a reply in the overall scheme of pleadings in a civil action
as elucidated in Nirumalan K Pillay & Ors v. A Balakrishan [1997] 1 SLR 322
and Romar Positioning Equipment Pte Ltd v. Merriwa Nominees Pty Ltd [2004]
4 SLR 574).
[50] In this case, the Plaintiff did not exercise its right to amend the SoC and to
plead that the 19 September 2013 Letter and the 30 May 2017 Letter constitute
a collateral contract. Reliance on this correspondence is a major shift from the
Plaintiff's Amended SoC which simply states that the LoA, standing alone,
stipulates that the Defendant has to pay for the differences in the GFA.
[51] Therefore, the evidence given at the trial is, in my considered opinion, a
radical departure from the Plaintiff's pleaded case and is not a "mere
development, variation or modification of pleadings" (see Ang Koon Kau &
Anor v. Lau Piang Ngong [1984] 1 MLRA 488; [1984] 2 MLJ 277; [1985] CLJ
(Rep) 24 and Superintendent of Lands and Surveys (4th Div) v. Hamit Bin
Matusin [1994] 1 MLRA 300; [1994] 3 MLJ 185; [1994] 3 CLJ 567; [1994] 3
AMR 1882).
(a) outlined the "origin of the whole arrangement' between the Plaintiff
and the Defendant and their intention at the onset of the relationship
based on the letter issued by the Plaintiff to KKP dated 30 April 2013
('30 April 2013 Letter'); and
(b) explained that at the time of the issuance of KKP's LoA and the
LoA between the Plaintiff and the Defendant, the drawings have not
been finalised.
[53] The 30 April 2013 Letter regarding the appointment of the Plaintiff as a
Total Development Contractor ('TDC') and Project Management Consultant
states, among others, that:
"...
We also note that the softcopy of the drawings and BQ which you
have given to us on the same day will be further revised to meet the
agreed proposed contract amount of RM127 million as discussed.
...".
[54] However, as was submitted by the learned counsel for the Defendant, the
30 April 2013 Letter was issued before the execution of the LoA. It would thus
be caught by the parol evidence rule as expressed in s 91 EA 1950 as follows:
Hence, no evidence can be accepted by the Court of the terms of the contract
except the contract itself, namely, the LoA.
[55] Assuming for a moment that this Court has erred and the issue of
pleadings ought to be determined in the Plaintiff's favour, the other aspect of
this claim which requires consideration is whether, as a matter of evidence, the
Plaintiff has proven its claim on a balance of probabilities.
[56] The Defendant contended that there is no provision under the LoA which
involves building works where the question of addition to the GFA would
become relevant. The scope of the Defendant's work is as quoted in para 7
above. The fact that the express provision on building works can only be found
in Clause F of the LoA on the proposal for the joint venture is indisputable.
[57] Mr Balbir Singh had conveniently provided the relevant pages of the
Notes of Evidence ('NoE') of PW4's and DW'3 evidence in his Written
Submissions (No 2). Based on PW4's evidence, it can be summarised that the
alleged agreement between the parties as to the Plaintiff's obligation to carry
out the building works and for the Defendant to pay the Plaintiff the difference
between the Actual GFA and the Agreed GFA is premised on the 30 April
2013 Letter, KKP's LoA, the LoA between the parties and the 19 September
2013 Letter, all read together.
[58] DW3 was asked about the Plaintiff's position on this matter in Q 32 of his
Tech Art Sdn Bhd
pg 22 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
But after this meeting, there was a change of heart on all three sides.
As such, some time before the letters of award dated 8 May 2013 were
issued, I spoke to Zolkifly (PW2) and I was told by Nik (DW1) that he
too spoke to Zol. The end result was that we all agreed that a direct
award would be issued, meaning there will be an award by KKP to the
Plaintiff for RM230 million and another award from the Plaintiff to
the Defendant for RM108 million.
The contents of such awards would be exactly what was said in it,
namely that it created a client-contractor and contractor-subcontractor
relationship.
They did not do this and this was the end of any JV proposal.
The 19 September 2013 letter merely stated the obvious which was
that there won't be any JVA and is consistent with what I stated
above. It provided for the demarcation of works, the appointment of
the NSCs (to be under the purview of the Defendant) and did not
provide for any liability on the Defendant for any increase in the
GFA.
Having rejected the JVA, and thereby accepting the terms of the
Letters of Award as they should be accepted, there is no basis to say
that liability for any dues to the NSC or for increase in the GFA
should be borne by the Defendant whether with or to the exclusion of
KKP.".
[59] Crucially, DW3's evidence as above quoted was not challenged by the
Plaintiff's counsel as the cross examination was limited to merely confirming
the contents of the 19 September 2013 Letter. It is essential that a party's case
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 23
be expressly put to his opponent's material witness when they are under cross-
examination lest the party may be barred from raising it in submissions at the
end of the trial (see Sivalingam A/L Periasamy v. Periasamy & Anor [1995] 2
MLRA 432; [1995] 3 MLJ 395; [1996] 4 CLJ 545; [1996] 3 AMR 3506).
Moreover, as submitted by the Defendant, there is nothing incredible,
implausible or unreasonable about DW'3 account of the events. In
comparison, PW4's evidence is a clear departure from the Plaintiff's pleaded
case.
[60] Having scrutinised these pages and the NoE in its entirety together with
the contemporaneous documents, this Court is persuaded to find that:
(b) PW4 had testified that "So, despite the fact that we have been
awarded RM230 million contract, we are supposed to undertake only
item (2) which is the relevant construction works.". GFA is part of the
construction works. Hence, the claim for the difference of contract
sum arising from the difference in the Actual GFA and the Agreed
GFA in fact relates to the contract sum under KKP's LoA. Surely, the
Defendant cannot be made liable for any price variation to the main
contract between KKP and the Plaintiff, and more so pursuant to the
unpleaded 19 September 2013 Letter.
Secondly, at the trial, the Plaintiff pursued the "alter ego" issue which
was pleaded in para 9 of the Amended Reply to rebut the Defendant's
statement in para 32B of the Amended Defence and CC. These
pleadings are set out below for the ease of reference:
"32B. Further, todate, the Plaintiff has yet to provide the 'as-
built drawing' and other plans to show fully what is the actual
gross floor area that was constructed. Therefore, even if the
Defendant is to indemnify the Plaintiff, the Defendant is
unable to study what the new area is."; and
However, in the Points of Claim for the arbitration, the Plaintiff stated
that:
The basis for the assertion on "alter ego" can be found mainly in
PW1's Witness Statement wherein the following relationships are said
to exist:
Bank Bumiputra Malaysia Bhd & anor [1987] 1 MLRA 198; [1988] 1
MLJ 97; [1987] CLJ (Rep) 50). In such circumstances, the cases of
Alcatel-Lucent (M) Sdn Bhd (formerly known as Alcatel Network
Systems (M) Sdn Bhd) v. Solid Investments Ltd and another appeal
[2012] 2 MLRA 731; [2012] 4 MLJ 72; [2013] 2 CLJ 734, Law Kam
Loy and anor v. Boltex Sdn Bhd and others [2005] 1 MLRA 521; [2005]
3 CLJ 355; [2005] 4 AMR 525, Giga Engineering & Construction Sdn
Bhd v. Yip Chee Seng & Sons Sdn Bhd & Anor [2015] 6 MLRA 686;
[2015] 6 MLJ 449; [2015] 9 CLJ 537; [2015] 6 AMR 765 as cited by
the Defendant on the requirement to plead actual or equitable fraud
are applicable (see too, the decisions by the Court of Appeal in Tenaga
Nasional Bhd v. Irham Niaga Sdn Bhd & Anor [2010] 3 MLRA 126;
[2011] 1 MLJ 752; [2011] 1 CLJ 491, Theta Edge Bhd v. Infornential
Sdn Bhd & Another Appeal [2017] 3 MLRA 669; [2017] 2 MLJ 34;
[2017] 7 CLJ 53; [2017] 2 AMR 901 and Takashimaya Construction &
Development Sdn Bhd & Anor v. My Influx Sdn Bhd & Other Appeals
[2019] MLRAU 168; [2020] 2 CLJ 92). It is incontrovertible that the
Plaintiff did not plead fraud in this case;
and
(c) having adverted to the position of the 30 April 2013 Letter vis-à-vis
s 91 EA 1950, in so far as the 19 September 2013 Letter goes, s 92 of
the same statute bears relevance and it stipulates that:
Provided that:
...
...".
[Emphasis Added]
[61] In summary, the Court finds, as it did with the 2nd Issue, that the Plaintiff
must be held to the causes of action as pleaded in the Amended SoC. The
Defendant has successfully defended itself against the Plaintiff's claim for the
difference in the GFA on the grounds of both pleadings and evidence.
[62] In the upshot, the Court held that the final sum that must be paid by the
Defendant to the Plaintiff is RM745,161.18 (RM47,147.26 + RM698,013.92)
with interest at the rate of 5% per annum from the date of judgment (as
pleaded) until the date of full settlement.
The Issues:
Whether The Defendant Has Shown That The Plaintiff Owes Any Amounts
To The Defendant Under The LoA?
And If So, Whether Such Amounts Are Due And Payable To The Defendant
At The Time Of Filing Of The Counterclaim
If Due And Payable, Whether Such Amount Can Be Set-Off Against The
Plaintiff's Claim (If Successful)
[63] The crux of the Defendant's counterclaim is that the final contract sum
between the parties is RM63,018,535.83 and the Defendant is entitled to the
amount which remains outstanding, after taking into account Progress
Payment Nos 1 to 33 in the total sum of RM54,141,102.65, pursuant to the
issuance of the CPC. In addition, the Defendant claimed for other amounts
which it alleged were owed by the Plaintiff.
[65] With reference to Item No 6 above, it is an agreed fact that the Defendant
owes the Plaintiff the sum of RM1,237,500.01 whilst Item No 5 was naturally
not disputed by the Plaintiff and the minor calculation error for Item No 7
(which should be RM3,251,314.00) was acknowledged by the Defendant's
counsel.
[66] In the resolution of the issues related to the counterclaim, the Court had
to undertake a meticulous examination of the Draft Final Account (Revision
4) - 31 October 2019 which was prepared by PW4 and marked as p 522(A),
Bundle B2 ('Plaintiff's Draft FA'), the Defendant's Revised Table with
comments denoted in green at p 522(A), B1 in Annexure 'A' to WS-DW3
('Defendant's Table') and the table of payment amounts disbursed by KKP and
received by, among others, the Plaintiff, the Defendant and the NSCs as
annexed to WS-DW2 ('DW2's Table').
[67] The issues which were raised by the parties in respect of the counterclaim
are addressed in the following part of this judgment.
[68] In what has become a dominant feature of this case, the issue of pleadings
is again foremost in the Defendant's submissions at the end of the trial.
[69] The Defendant invited the Court to peruse the Defence to the
Counterclaim which consists of three paragraphs of denials to the Defendant's
allegations on the counterclaim. Even when read with the averments made in
Tech Art Sdn Bhd
pg 28 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
[70] Mr Balbir Singh had earlier referred to O 18, rr 7, 8 and 10 RC 2012 and
for present purposes, the learned counsel also cited O 18, r 13 which reads:
(4) Any allegation that a party has suffered damage and any allegation
as to the amount of damages is deemed to be traversed unless
specifically admitted.".
[71] In addition, the learned counsel cited the compelling authorities of Kiaw
Aik Hang Co Ltd v. Tan Tien Choy [1963] 1 MLRA 335; [1964] 1 MLJ 99, Lee
Ah Chor v. Southern Bank Bhd [1990] 2 MLRA 6; [1991] 1 MLJ 428; [1991] 1
CLJ (Rep) 239 and Gerard Jude Timothy Pereira v. Kasi a/l KL Palaniappan
[2018] 3 MLRA 97; [2017] 6 MLJ 54 to support the submissions, among
others, that the Plaintiff's bare denial is not a sufficient traverse of the
counterclaim; it is not the duty of the Court to invent a defence which was not
pleaded under the guise of doing justice; and a judgment on issues which are
not raised by the pleadings is susceptible to being set aside.
[72] The Plaintiff's sole point of rebuttal is found at para 76 of its Submissions
In Reply wherein the Plaintiff maintains that it has sufficiently pleaded its
defence and emphasised that, by virtue of s 13 EA 1950, it is for the Defendant
to prove its counterclaim.
[73] The Plaintiff's assertion that it has sufficiently pleaded its defence flies in
the face of the Amended Reply and Defence to Counterclaim. It is irrefutable
that the Plaintiff's defence to the counterclaim is a bare denial and hence, it has
the effect as contended by the Defendant, namely that the Plaintiff is deemed
to have admitted the factual matters as pleaded in the Amended Defence and
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 29
CC and it cannot rely on any evidence having the effect of mounting a positive
answer to the counterclaim. However, as acknowledged by the Defendant, by
raising a negative defence, the Plaintiff has, at best, put the Defendant to prove
its counterclaim on the legal issues as opposed to the factual issues.
(a) that at the time before, during and after the acceptance of the LoA,
it had been agreed among PW4, DW1 and DW3 that, if the contract
value between the parties under the LoA was reduced, a percentage of
the costs to be reimbursed by the Defendant would also reduce;
(c) the implied term, the collateral agreement or the pre-condition are
as follows:
(i) the value of the 47.3% which the Defendant must bear was
achieved by rounding the percentage of the contract sum
under the LoA (RM108,811,854.83) compared to the contract
sum under KKP's LoA (RM230 million); and
(d) after the execution of the LoA, the contract sum was reduced by
RM45,793,319.00 upon the nomination by the Defendant, and the
corresponding award by the Plaintiff to Stitec, ASC, Nova Nexus and
Super Sun Sdn Bhd ('Super Sun') for various scope of works.
[77] Apart from Clause A(ii) of the LoA, the Defendant drew support for its
position by referring to:
(a) Clause C.2 of the LoA which provides that it is the Plaintiff who
will pay the NSCs. The said clause reads [With My Added Emphasis]:
Since the obligation to pay the NSCs is on the Plaintiff, the Plaintiff
would not need to pay the Defendant and hence, the Defendant's
contract sum is lowered by that amount paid or payable by the
Plaintiff to the NSCs;
(c) the summary judgment which was entered by the Plaintiff against
the Defendant for profit and attendance fees for Stitec, ASC and Nova
Nexus (see subpara 11(d) above). The Plaintiff benefitted from the
arrangement, and it affirmed the same by applying for, and obtaining,
the said summary judgment. As such, the Plaintiff cannot, through the
testimony of PW4 and the Plaintiff's Draft FA, contend that payment
for any sum due under the nominated subcontracts to these NSCs was
never its responsibility, and that the Defendant's sub-contract price
was not reduced correspondingly by the value of the sub-contracts
awarded to these NSCs and remained at the original sum of
RM108,811,854.83.
[78] The Plaintiff's retort by way of its pleadings was, as outlined previously, a
bare denial. Legally, the Plaintiff is not allowed to set up a positive case. In
any event, the Plaintiff's reliance on the second part of Clause A(iii) of the
LoA in submitting that the scope of works remains under the Defendant's
responsibility and that the contract sum is not reduced by virtue of the NSCs'
contracts, is totally misconceived. The relevant part of Clause A(iii) of the
LoA states as follows:
[79] By reading the clear words in the said part of Clause A(iii) of the LoA, it
is obvious that it does not apply in the factual matrix of this case because there
is no "default termination of any NSC's employment'. In such situation, the
sums due to the Defendant will be reduced corresponding to the amounts paid
or payable to the NSCs. In effect, the Plaintiff does not have to pay the
Defendant that part of the NSCs' contract sum as it is the Plaintiff who will
pay the NSCs. It is only in the event of default of any NSCs resulting in
termination of the NSCs' employment that the remaining scope of works
which is left unfinished by the NSCs becomes the Defendant's responsibility to
complete.
[80] Mr Balbir Singh has rightfully articulated that the Plaintiff's argument is
circular, in that the net effect is still the same as what the Defendant is
contending. Instead of saying that the Defendant's contract sum has been
reduced, it can be expressed that the amount due to the Defendant has been
reduced. In both cases, the sums due to the NSCs must be paid. In the end, the
monies will end up in the NSCs' pockets, only by a different route.
[81] Based on the oral and documentary evidence, the Court is satisfied that
Tech Art Sdn Bhd
pg 32 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
the Defendant has proven, on a balance of probabilities, that the contract sum
has been reduced to RM63,018,535.83.
[83] The Defendant takes the position that Clause C.2 of the LoA is a "pay
when paid" clause as opposed to a "pay if paid" clause.
[84] In Globe Engineering Sdn Bhd v. Bina Jati Sdn Bhd [2014] 5 MLRA 363;
[2014] 5 MLJ 145; [2014] 7 CLJ 1; [2014] 4 AMR 793, Jeffrey Tan FCJ, in
delivering the judgment of the Federal Court, extensively discussed the
approach of the courts within the country and beyond in determining whether
a contractual provision is a "when" clause or an "if" clause and legal articles
which have been written on this matter. The Court finally answered the first
leave question that upon proper construction of the clause in question, it was a
provision that merely fixed time for payment but did not absolve the
respondent of liability to pay the amount certified and attributable to the work
executed by the appellant. In the course of the analysis, the Court held:
words in which the parties have expressed their agreement that this
remedy shall not be available in respect of breaches of that particular
contract (Gilbert-Ash (Northern) Ltd v. Modern Engineering (Bristol) Ltd
[1974] AC 689 at p 718 per Lord Diplock). The burden is on the party
who proposes otherwise, to show that payment was on an NP basis.
Hence, the burden was on the respondent to show that liability for
payment was contingent. Since there were no such provisions to that
effect or from which that could be so construed, it could not be so read
into the subcontract where it was silent, that the liability of the
respondent was contingent. Time for payment of the certificates was
contingent. But under para 14 and cl 11(b), the liability of the
respondent was not contingent. The respondent was liable even MP
the employer defaulted on the contract (for an analogy, see Scobie &
Mcintosh Ltd v. Clayton Bowmore Ltd (1990) 23 ConLR 78, where it
was held that with repudiation of the subcontract by the main
contractor and which was accepted by the subcontractor, the primary
obligations of the party in default which remained unperformed was
substituted by a secondary obligation to compensate the subcontractor
for loss sustained in consequence of the non-performance of the
primary obligations).".
[Emphasis Added]
[86] It follows from the above finding that the Defendant's counterclaim is not
premature because the Plaintiff's liability to pay the Defendant is not
contingent on the Plaintiff having received payment from KKP or on an
outcome of the arbitration in the Plaintiff's favor. And nor can the Plaintiff
contend that "... payment can only be made to the Defendant after deducting
out the Plaintiff's payment to the NSCs" (see para 76 of the Plaintiff's Written
Submissions) as this Court has held that the obligation to pay the NSCs lies on
the Plaintiff and the Plaintiff cannot take the benefit of its own wrong in not
paying the NSCs to claim that the Defendant's counterclaim is premature.
[87] Moreover, by relying on PW4's evidence and Clause C.2 of the LoA, the
Plaintiff was attempting to prove the facts which have the effect of mounting a
positive answer to the counterclaim. This the Plaintiff cannot do when all that
it has pleaded is a negative defence.
[88] The Plaintiff asserted that it has paid RM149,999.00 (or RM150,000.00 as
was stated by PW4 in her evidence) to the Defendant for project management
fees under KKP's LoA. This payment was made following correspondence
from Datin Salmah.
[89] The Defendant's counsel drew the attention of the Court to PW4's and
DW2's evidence and the documents showing the amount which was disbursed
to the Defendant. Under Claim No 1 for the Certificate of Payment dated 26
July 2013 for the amount of RM10,988,086.11 in the Annexure to WS-PW4,
the payment received by the Defendant on 30 September 2013 is stated as the
same amount as the Certificate of Payment. Although KKP, in the Form of
Disbursement Notice dated 26 July 2013 issued to Malaysia Building Society
Berhad ('MBSB'), had requested that RM10,988,086.11 be disbursed to the
Defendant, the Plaintiff's General Ledger 1 for the entry on 31 December 2015
shows an adjustment of account for the Project in the sum of
RM10,838,086.11. In the Statement of Account issued by MBSB to KKP,
among the particulars for 4 September 2013 are the disbursement in the sum of
RM10,838,086.11 to the Defendant and RM150,000.00 to the Plaintiff.
[91] At this juncture, it would be appropriate to mention that the Plaintiff did
attempt to convince the Court to disregard DW2's evidence on the ground of
bias as DW2 had previously represented the Defendant in this suit and he
admitted that he wants to assist the Defendant. It was also contended that
DW2's evidence is replicated by DW3 as both had produced a statement of
account laying out the quantum that is owed by the Plaintiff to the Defendant.
[92] The Plaintiff submitted that the statement of account is the only evidence
that the Defendant has provided to support its claim and hence, by virtue of s
34 EA 1950 and the decisions in Sim Siok Eng & Anor v. Poh Hua Transport
and Contractor Sdn Bhd [1980] 1 MLRA 618; [1980] 2 MLJ 72 and Tey Por
Yee & Anor v. Protasco Bhd [2020] MLRAU 69 this evidence on its own is
insufficient as proof of the Plaintiff's liability for the counterclaim. Section 34
EA 1950 provides that:
ILLUSTRATION
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 35
A sues B for RM1,000 and shows entries in his account books showing
B to be indebted to him to this amount. The entries are relevant, but
are not sufficient without other evidence to prove the debt.".
" The law does not prescribe any special type or form of books of
account to be kept by a businessman, nor does it specify any system by
which these books are to be kept. Of course it is far more satisfactory if
books are kept in a generally recognised form or system showing debts
and credits entries between the parties, thus indicating on the face of
the account the liability of the party against whom the account is
tendered. A book of account kept by an illiterate tradesman is just as
admissible as that kept by a highly educated merchant and banker. All
that is necessary to show to the Court is that the book must be one that
is "regularly kept in the course of business". This expression implies
some sort of system which is followed in the making of entries in the
book in question, although such system need not be elaborate (Kesheo
Rao v. Ganesh AIR 1926 Nag 407). Where there is a system, the fact
that entries in the book are not entered hour by hour or day by day as
transactions took place does not mean that the book is not "a book of
account regularly kept in business"...".
(b) although the Defence to Counterclaim has not traversed the figures
pleaded by the Plaintiff in the counterclaim, the Plaintiff had filed WS-
PW4 with the Annexure and had produced the Plaintiff's Draft FA
and the General Ledgers. This indicates that the Plaintiff intends to
dispute the figures stated in the Counterclaim; and
Tech Art Sdn Bhd
pg 36 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
[96] I found that DW2's Table contains a more detailed breakdown of the
amounts which were received by the Plaintiff, the Defendant, the NSCs, LK
Construction and the Consultants and these were extremely helpful in the
determination of the issues related to the counterclaim. Moreover, I did not
simply accept the figures in DW2's Table at face value. The parts highlighted
in green carried the reference to the relevant pages in the CBoD and the figures
as stated were checked against the documents with the outcome that the
figures as inserted in DW2's Table represent the correct amounts. For
completeness, the Court also took cognizance of paras 105 - 110 in the
Defendant's Reply Submissions, including the table which sets out the
summary of DW3's criticisms of the Plaintiff's Draft FA when compared
against the contemporaneous documents.
- Whether The Plaintiff Is Liable For The Payments Which Were Made By
The Defendant On Behalf Of The Plaintiff To Nova Nexus And Super Sun
[97] Among the items in the counterclaim is the sum of RM924,994.00 and
RM2,326,320.00 which the Defendant alleged that it had paid Nova Nexus
and Super Sun, respectively, before they were appointed as the Plaintiff's sub-
contractors. The total sum which was paid is RM3,251,314.00.
[98] The Plaintiff's stance at the trial was that it was under no obligation to pay
these amounts as it is unaware of where the payments originated from and the
Plaintiff did not consent to the payments and nor was it informed of the same.
The Plaintiff asserted that it was natural for it to be wary of the purported
payments by the Defendant as these were made before the Plaintiff issued the
Letters of Award As NSC to Nova Nexus on 2 January 2014 and to Super Sun
on 23 June 2015.
[99] Based on DW3's evidence and the documents produced at the trial, the
Defendant paid Super Sun between the months of February 2014 to April 2015
(see the Defendant's Public Islamic Bank Statement of Accounts dated 28
February 2014, 31 July 2014, 31 October 2014, 31 December 2014, 28
February 2015 and 30 April 2015 and Super Sun's Official Receipts dated 5
February 2014, 11 July 2014, 23 October 2014, 12 December 2014, 13
February 2015 and 13 April 2015 at pp 26 - 37, DB1).
[100] The Defendant does not deny that at the time that it paid Nova Nexus
and Super Sun, these NSCs were not the Plaintiff's sub-contractors yet. In this
regard, the contention that the Defendant must obtain the Plaintiff's prior
consent before making the payments to Nova Nexus and Super Sun simply
does not arise.
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 37
[101] As for the Plaintiff's allegation that it was not informed and has no
knowledge of these payments, the Defendant has proven, on the balance of
probabilities, that it is in fact the opposite. In the case of:
(a) Nova Nexus, based on PW4's, DW2's and DW3's testimonies, the
Court finds that PW4 had signed the undated letter to Nova Nexus
and had placed her initial on the first page of the letter and on each
page of the attachments (which PW4 testified was sent by registered
post to Nova Nexus on 19 October 2016) and, among others, enclosed
"our record of payments to you".
(b) Super Sun, the Tax Invoice issued by Super Sun to the Plaintiff
dated 9 July 2018 shows that Super Sun has received payments in the
sum of RM18,853,97285 and that it has a total claim of
RM6,936,680.90. The sum of RM18,853,97285 includes the amounts
which were paid by the Defendant to Super Sun between February
2014 to April 2015 as alluded to earlier (see pp 512 and 670, B2).
[102] In the light of the above discussion of the oral and documentary
evidence, the sum of RM3,251,314.00 which was paid by the Defendant to
Nova Nexus and Super Sun were treated by the Plaintiff as though it were
payments made by itself to these NSCs. In this sense, the Plaintiff enjoyed the
benefit of these payments as it reduced the amount which it would otherwise
be obligated to pay to Nova Nexus and Super Sun. This Court is satisfied that
the Defendant has established its counterclaim for this head of claim.
[103] The Plaintiff relied on the same "alter ego" argument as was alluded to in
respect of the Plaintiff's claims in denying any liability for the counterclaim for
the reason that "there seems a blurring of lines between the Defendant and
KKP in the counterclaim" (see para 88 of the Plaintiff's Written Submissions).
[104] In my view, the Plaintiff cannot go far with this argument for the simple
and, what has become a repeated reason in the determination of the dispute
between the parties, that it was not pleaded by the Plaintiff. As was shown in
para 60(b) above, the fact as to "alter ego" was pleaded in para 9 of the
Amended Reply in the context of the as-built drawings. It was certainly not
expressly pleaded as one of the defences to the counterclaim.
[108] In Lee Ing Chin @ Lee Teck Seng & Ors v. Gan Yook Chin & Anor [2003]
1 MLRA 95; [2003] 2 MLJ 97; [2003] 2 CLJ 19; [2003] 2 AMR 357, the Court
of Appeal elucidated at p 116 that:
[109] Later, the same Court, this time constituted of a different panel of
judges, expounded the following in Tan Ah Kow & Anor v. Tan Chaui En
[2017] 6 MLRA 141; [2017] 6 MLJ 297; [2018] 2 CLJ 610 at p 306:
"[20] Having considered the judgment of the learned JC, we are of the
view that the learned JC erred in making her decision based mainly on
the demeanour of the first appellant, and the learned JC's perception
of the lack of credibility of the first appellant. We agree that
demeanour and credibility are important in determining which of the
two versions of the parties can be believed and accepted. However, we
are of the view that the trial judge should first of all determine, on a
balance of probabilities, whether the plaintiff has discharged the
burden of proving his case. This will then be considered by the trial
judge, and taking into account at the same time the demeanour and
credibility of the witnesses. The demeanour and credibility of
witnesses should not be accorded such disproportionate weight by the
trial judge to the extent of ignoring and not giving due weight and
importance to the facts established from the totality of the evidence.".
[110] By applying the legal principles derived from the above said cases and
following from the analysis of the Court on the issues which arose for
consideration as discussed thus far, I do not think that the evidence given by
any of the witnesses at the trial should be rejected in their entirety purely on
the ground of his or her demeanour. In weighing the evidence in the course of
determining whose version of the events to believe and whether the Plaintiff or
the Defendant has discharged the burden of proof, as the case may be, I have
considered the totality of the evidence and have tested the oral testimonies of
the witnesses against the contemporaneous documentary evidence which is in
abundance in this case (see OSK Securities Bhd v. Probo Pacific Leasing Pte Ltd
& Anor [2008] 3 MLRA 787; [2009] 3 MLJ 712).
[111] As both the Plaintiff and the Defendant are pursuing their respective
claims, it is not safe to rely solely on the demeanour of, especially PW4, DW 1
and DW3, as the barometer in the final outcome of the dispute.
In Tindok Besar Estate Sdn Bhd v. Tinjar Co(supra, at p 234) Chang Min Tat
FCJ said:
"... For myself, I would with respect feel somewhat safer to refer to
and rely on the acts and deeds of a witness which are
contemporaneous with the event and to draw the reasonable
inferences from them than to believe his subsequent recollection or
version of it, particularly if he is a witness with a purpose of his own to
serve and if it did not account for the statements in his documents and
writings. Judicial reception of evidence requires that the oral evidence
Tech Art Sdn Bhd
pg 40 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
be critically tested against the whole of the other evidence and the
circumstances of the case. Plausibility should never be mistaken for
veracity....".
- Ancillary Matter
[112] In its Written Submission in Reply, the Plaintiff submitted that Clause
A(ii)(6) of the LoA on the scope of works relating to "Management, Structural
Consultancy and Risk Management Fees" in the sum of RM26,190,200.43 is a
sham in that the risk management scope was merely for the purpose of
withdrawing project funds. The Defendant retorted, once again, that this fact
was not pleaded by the Plaintiff. I agree.
Conclusion
[114] On the issue of cost, the Plaintiff's counsel prayed for cost in the cause
since "the Plaintiff won some and lost some and the Defendant won on its
counterclaim".
[115] The Defendant's counsel disagreed, giving the reason that what the
Plaintiff won was already conceded before the trial, and the fact that the
Defendant succeeded in the substantive part of the case which revolve on the
GFA related claim and the counterclaim. A sum of RM100,000.00 as costs
was sought in view of the length of the trial, the amount of work that was
dedicated to this case and the change of solicitors which happened thrice.
[116] The Plaintiff's solicitors then suggested the sum of RM60,000.00 as costs
and this was duly ordered as the Court viewed it as a befitting amount in the
circumstances of the case. The order for costs was made subject to the
payment of the standard allocatur fees.
[117] Soon after the decision after the full trial was pronounced, the Plaintiff
filed the application in encl 153 for, among others, a stay of the execution of
the judgment pursuant to O 45, r 11 RC 2012 and/ or the Court's inherent
jurisdiction under O 92, r 4 RC 2012, including the winding up of the Plaintiff,
pending the final determination of the Plaintiff's appeal against the judgment
('Appeal').
[118] On the date of the hearing of the application, the Plaintiff's counsel
informed the Court that the Plaintiff does not wish to pursue prayer 2 in encl
153 which is an order for stay of the execution of the judgment pending the
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 41
(c) the Defendant's AIR (No 1) affirmed by DW3 (encl 172); and
[120] After an oral hearing and taking into consideration the evidence on
affidavit and the submissions of the parties, the Court had allowed the
Plaintiff's application for stay of the execution of the judgment sum pending
the disposal of the appeal by the Court of Appeal on condition that this
amount is deposited with the Defendant's solicitors as stakeholder in an
interest bearing account within 30 days from the date of the order
('Condition'). The said sum and the accrued interest thereon shall be released
in accordance with the order that will be made by the Court of Appeal.
[121] As the Defendant did not appeal against the decision of this Court in
respect of encl 153 and the Plaintiff's current appeal is only against the
Condition, I now provide the full justifications to warrant the order for the
Condition.
[123] The Plaintiff accepts that it has the burden to prove the existence of
special circumstances which render the order for stay of execution necessary in
line with the high authorities and all the subsequent cases which have applied
the legal principles accordingly (see Ming Ann Holdings Sdn Bhd v. Danaharta
Urus Sdn Bhd [2002] 1 MLRA 214; [2002] 3 MLJ 49; [2002] 3 CLJ 380; [2002]
3 AMR 2867 and Kosma Palm Oil Mill Sdn Bhd & Ors v. Koperasi Serbausaha
Makmur Bhd [2003] 1 MLRA 536; [2004] 1 MLJ 257; [2003] 4 CLJ 1).
something that exceeds or excels in some way that which is usual or common.
There is a myriad of circumstances that could constitute special circumstances
and the list of factors that could establish such circumstances is not closed (see
The Government of Malaysia v. Datuk Kadir Mohamad Mastan & Another Case
[1993] 3 MLRH 207; [1993] 3 MLJ 514; [1993] 4 CLJ 98). It is trite that merits
of the appeal against the judgment and fear of execution are not special
circumstances.
[125] Having read the Defendant's AIR and submission, it is apparent that it
admits that it has not filed its annual statement of accounts. In this situation,
the Defendant's financial standing and the ability to repay the judgment sum to
the Plaintiff (which was calculated as RM7,870,430.37 inclusive of interest and
cost, less the full judgment of RM2,157,183.35 in favor of the Plaintiff,
resulting in the sum of RM5,713,247.03; see para 6, encl 172), if the Plaintiff's
appeal is allowed, is indeed questionable. The Defendant contended that
nonetheless, a blanket stay should not be granted because:
(b) the Court should not lend a hand to grant a stay which has the
mere effect of facilitating the Plaintiff to avoid or delay the execution
or the Plaintiff's legal obligation to honour the judgment debt;
(c) the Plaintiff has not disclosed in its AIS and AIR the state of its
finances such as its fixed and current assets, the amounts payable to its
creditors in the immediate and medium term, the conduct of its
payment to these creditors and whether it is facing any threat of
execution or winding-up by its other creditors;
(d) the Plaintiff was not willing to give an undertaking to preserve its
assets when the Plaintiff sought an order for an ad interim stay until
encl 153 was heard and disposed and further, the Plaintiff did not give
any assurance to the Court that it is able to meet the judgment sum in
the event the appeal is unsuccessful and to fortify the assurance with
evidence; and
(e) there is a risk that the Plaintiff may suffer execution or winding- up
in the hands of some other creditor. The Defendant, as execution
creditor, is entitled to the fruits of its litigation being first in time to
realise the assets of the judgment creditor. Applying the decision in the
case of Pritchard v. Westminister Bank Ltd [1969] 1 AII ER 199, the
Defendant does not need to share the fruits of its diligence with other
creditors.
[126] It is observed that, when the Court heard the Plaintiff's application for an
ad interim stay on the first date of case management for encl 153, the
undertaking by the Plaintiff that it will not dispose of its assets pending the
disposal of encl 153 was not immediately given. The matter was stood down to
enable Mr K Selva to obtain instructions from his client. The undertaking was
then obtained and later formalised by way of the Plaintiff's averment in para 5,
Tech Art Sdn Bhd
[2023] MLRHU 134 v. Metropolitan Bumi Sdn Bhd pg 43
encl 164.
[127] Having considered the submissions of the parties, the Court was inclined
to agree with the Defendant that this is a case suited for a conditional stay for
the following reasons:
(a) After outlining the Plaintiff's efforts in claiming the amounts which
were purportedly due and owing by KKP to the Plaintiff vide two
adjudication proceedings and an arbitration proceeding, the Plaintiff
then affirmed in para 21 of the AIS that "... by virtue of the non-
payment of KKP, the Plaintiff is constrained in their ability to settle
the dues to their sub-contractors including the nominated sub-
contractors...". By its own averment, the Plaintiff admits that there are
sums of monies owing to the subcontractors and this lends credence to
the Defendant's contention of a threat of execution or winding up by
the Plaintiff's other creditors in future and the risk that the Plaintiff
may dispose of its assets and leave the Defendant with a barren
judgment.
(c) In Jaya Harta Realty Sdn Bhd v. Koperasi Kemajuan Pekerja- Pekerja
Ladang Bhd [2000] 1 MLRH 316; [2000] 6 MLJ 493; [2000] 3 CLJ
361; [2000] 3 AMR 3693, the High Court, in allowing the plaintiff's
application to stay the execution of an order setting aside a
garnishment order and the return of the garnished money to the
garnishees, pending the disposal of the plaintiff's appeal to the Court
of Appeal, had, at pp 499 - 501, expounded that:
[Emphasis Added]
(d) The learned counsel for the Plaintiff cited the case of Perkapalan
Dai Zhun Sdn Bhd & Anor v. Formosa Plastics Marine Corporation &
Ors & Another Case [2021] 2 MLRH 199 to illustrate a case scenario
where there was some evidence in the form of the 2015 financial
statement of the company concerned, albeit there was no information
at all for the four years after that, as compared to the present case
where the state of the Defendant's finances was not made known at
all.
The admiralty court was of the view that there were special
circumstances to warrant the exercise of the court's discretion to stay
the execution of the judgment. The court found that the defendant's
financial resources were such as to raise serious doubts as to their
ability to repay the judgment sum to the plaintiffs in the event the
appeal was allowed. The court thus allowed the stay application
subject to two conditions, one of which was for the plaintiffs to make
cash payments over three consecutive months into a joint stakeholder
account to be maintained jointly by the partners of the plaintiffs' and
defendants' solicitors. The court further ordered that in the event any
of the conditions are not complied with, the stay order is set aside.
Tech Art Sdn Bhd
pg 46 v. Metropolitan Bumi Sdn Bhd [2023] MLRHU 134
[128] The Court, having decided that a conditional stay is the most appropriate
order to be made given the present set of facts, then addressed the issue of cost.
[129] Mr Balbir Singh prayed for RM10,000.00 as cost on the ground that it
was a highly contested application. However, the Court agreed with the
Plaintiff that it is befitting for cost to be in the cause of the Plaintiff's appeal.
Order accordingly.