Application of Time Buffers To Construction (Ok)
Application of Time Buffers To Construction (Ok)
Task Durations
Marion M. Russell 1; Gregory Howell, M.ASCE 2; Simon M. Hsiang 3; and Min Liu, A.M.ASCE 4
Abstract: For this research, a time buffer is defined as the extra time added during planning to individual task durations to compensate for
Downloaded from ascelibrary.org by University of Nebraska-Lincoln on 09/17/13. Copyright ASCE. For personal use only; all rights reserved.
uncertainty and protect against workflow variation to assure a predictable hand-off to subsequent crews. Although previous research has
acknowledged this addition of time buffers, their use in practice has not been studied. This paper reports on what causes people to add and size
time buffers. A nationwide survey was administered to project managers, superintendents, and foremen to identify the most frequent and
severe reasons for adding time buffers to construction task durations. Forty-seven buffer factors were grouped into nine categories: project
characteristics, prerequisite work, detailed design/working method, labor force, tools and equipment, material and components, work/jobsite
conditions, management/supervision/information flow, and weather. Contributions to the body of knowledge include (1) identifying the 12
most frequent and severe causes of time buffer; (2) analyzing (understanding) how buffers are viewed differently by foremen, superintendents,
and project managers, between trades and between general contractors and subcontractors, and the perception among different levels of
experience; and (3) investigating how companies that do not regularly use the Last Planner System and those that do view those factors
differently. Additionally, the research quantitatively developed risk profiles of the buffer factors through an integrated risk assessment
approach. Understanding the application of time buffers and their associated frequency and severity will help construction managers address
potential problem areas and inefficiencies in a prioritized manner. DOI: 10.1061/(ASCE)CO.1943-7862.0000735. © 2013 American Society
of Civil Engineers.
CE Database subject headings: Construction management; Uncertainty principles; Time factors.
Author keywords: Construction; Time; Buffer; Uncertainty; Labor and personnel issues.
Introduction are used in construction, but the underlying causes of time buffers,
both the frequency and severity thereof, are unclear. Although we
There exists a natural tendency in construction to add a buffer probably cannot eliminate all uncertainty and associated time buff-
to tasks due to the inherent uncertainty and resulting variability. ers, understanding and addressing the root causes of time buffers
Buffers in production (such as excess inventory, added capacity, will help us allocate them where they are needed most and conse-
and deliberate delays) are commonly used to protect against uncer- quently reduce project durations and costs. This research serves to
tainty. Perhaps most importantly, buffers mask the sources of fill a gap in the body of knowledge pertaining to the causes of time
uncertainty that make them necessary. While there are several types buffers in construction project task durations. The three primary
of buffer, the focus of this research is the study of time buffers research objectives are as follows:
(hours, days) added to individual construction project task dura- 1. Determine which factors are the most prevalent and severe
tions by construction personnel to compensate for uncertainty causes of time buffers included in construction task durations.
and potential variation. Based on the research to date, there seems Goldratt (1997) and Ballard (2000) have acknowledged the
to be a definite and growing interest in the study of several aspects existence of time buffers in task durations and recommended
of buffers in construction (Howell et al. 1993; Ballard and Howell methods to manage buffers. Neither author examined the cause
1995; Goldratt 1997; Ballard 2000; Horman 2000; Horman et al. of time buffers. This research investigates the causes of uncer-
2003; Alves and Tommelein 2004; Horman and Thomas 2005; Lee tainty or potential problem areas that construction personnel
et al. 2006; Hopp and Spearman 2008). It seems evident that buffers consider when adding time buffers to work plans or task
durations and determine which are the most important from
1
Graduate Student, Dept. of Civil, Construction, and Environmental both a frequency and severity standpoint.
Engineering, North Carolina State Univ., Raleigh, NC 27695-7908. E-mail: 2. Using an integrated risk assessment approach, classify the 47
[email protected] individual risk factors as risk profiles.
2
President, Lean Construction Institute, 1400 N. 14th St., #400, Ideally, it would be desirable to eliminate all of the uncer-
Arlington, VA 22209. E-mail: [email protected] tainty and variation associated with the different factors; how-
3
Derr Professor, Dept. of Industrial Engineering, Texas Tech Univ., ever, in today’s construction industry environment of limited
Lubbock, TX 79409. E-mail: [email protected] resources, risk profiles help to categorize and prioritize the fac-
4
Assistant Professor, Dept. of Civil, Construction, and Environmental tors that management needs to address.
Engineering, North Carolina State Univ., Raleigh, NC 27695-7908 (corre-
3. Determine the differences in opinion and perception between
sponding author). E-mail: [email protected]
Note. This manuscript was submitted on March 11, 2012; approved on different levels of management, different trades, and different
May 13, 2013; published online on May 15, 2013. Discussion period open levels of experience, the difference between general contrac-
until December 24, 2013; separate discussions must be submitted for indi- tors and subcontractors, and the difference between contrac-
vidual papers. This paper is part of the Journal of Construction Engineer- tors using traditional management approaches and those
ing and Management, © ASCE, ISSN 0733-9364/04013008(10)/$25.00. using lean construction techniques.
tioned, to identify 166 factors. Tommelein et al. (1999) stated that by a project manager, collecting information such as the company
successful project managers take proactive steps to establish buffers type (subcontractor or general contractor), company size, annual
to shield crews from variability in construction. They noted that revenue, average project size, backlog or pending work, and
common causes included change orders, late replies to requests whether or not they use the Last Planner System. The time buffer
for information, lack of materials, physical interference between survey included three sections. The first section asked participants
materials, work-space congestion, and others but did not develop to provide background information such as trade, position, and
a thorough list of factors or explore them further. experience. Sections 2 and 3 involved obtaining feedback pertain-
ing to the previously discussed categories and individual reasons
for adding buffers in task durations. In Section 2 the participants
Methodology were asked to rank order the nine overall categories based on which
categories they felt contained the most critical and prevalent causes
A survey was developed to study which causes of uncertainty or of uncertainty when they are budgeting time into task durations.
concerns about potential for variation result in the most frequent The participants were also asked whether or not they felt the
and severe addition of a time buffer in construction task durations. uncertainty associated with the category was their responsibility
Through a combination of a literature review and research team to control or mitigate. The third section expanded the nine catego-
discussions with construction project managers, superintendents, ries into the 47 factors or reasons that affect task duration estimates.
and foremen, 47 individual factors related to time buffers in con- The purpose of the third section was to find out which factors most
struction tasks were identified and included in the survey. The frequently and severely affect task duration estimates. For each
seven categories that impact productivity established by Koskela factor, the respondents were asked how frequently the factor influ-
(2000) to include connected work, detailed construction design, enced their duration estimate by circling one of the following seven
components and materials, workers, equipment and tools, space, frequency responses: never, rarely, occasionally, sometimes, fre-
and external conditions, along with Wambeke et al. (2011) added quently, usually, or always. Next, for each factor, the respondents
eighth category of management/supervision/information flow, were were asked to consider a 2-week (10-day) activity and estimate how
used as a framework to separate the 47 buffer factors. Based on much time (days) they would include or allocate for the given factor
the nature of some of the identified buffer factors, one additional in their duration estimate to protect against the effects of uncer-
category was included: project characteristics. The nine categories tainty. The respondents chose one of the following seven severity
are listed and described below: responses: 0, 0.5, 1, 2, 3, 5, or 7. The decision to use seven choices
1. Project characteristics: concerns/uncertainty about characteris- for both frequency and severity was made to balance having too
tics specific to a project and a given trade. many choices with still being able to capture just noticeable dif-
2. Prerequisite work: items that must be completed before one ferences. Fig. 2 provides an example of a question from the third
can start a task. If there is concern or uncertainty that the item section of the contingency survey. The question in the example is
(permits, prerequisite work, or rework on a prerequisite task) about factors related to labor.
will not be completed on time, then consider the extent to A pilot study was conducted with a construction company in
which one’s duration estimate is affected. This can also be Colorado and a local construction company to help avoid potential
thought of as confidence in the schedule or work plan. problems associated with the length and clarity of the questions and
3. Detailed design/working method: concerns/uncertainty about the instructions provided for completion of the survey. Addition-
having an accurate and available design and a feasible working ally, the pilot study was used to help validate the relevance of
method to complete the required task. the factors chosen and allow suggestions for additional factors.
4. Labor force: concerns/uncertainty about availability, reliabil- Overcommitment was modified as liability pressure and included
ity, and capability of the labor force to complete the required concerns about overcommitting due to a tight schedule, liquidated
task. damages, and contractual deadlines. The factors of positive com-
5. Equipment and tools: concerns/uncertainty about the availabil- pany recognition, preparing for duration negotiation, concerns
ity, reliability, and capability of the required equipment and about being pushed into using more manpower, and poor perfor-
tools to complete the required task. mance due to unfamiliarity (with the scope) were added. The sur-
6. Material and components: concerns/uncertainty about receiv- vey was distributed (online and hard-copy versions) to general
ing the correct and necessary materials from suppliers when contractors and subcontractors throughout the United States. All
and where you need them. This can be thought of as trust or participating companies and respondents completed the surveys
confidence in one’s suppliers. voluntarily. Four local contractors were provided surveys for dis-
7. Work/jobsite conditions: concerns/uncertainty about the phy- tribution, and another nine contractors from six different states were
sical space available to perform one’s job. contacted via a construction consulting company. Two professional
8. Management/supervision/information flow: concerns/ civil engineering organizations also provided contact information
uncertainty about the management system regarding issues for multiple construction companies throughout the United States.
Delays in inspections for previously completed surveys, and foremen the remaining 22%. The trades were sepa-
work rated into four trade groups for comparison. The utilities category
Detailed design Design constructability included the mechanical, electrical, plumbing, and fire protection
and Quality of documents trades and accounted for 44% of the responses. The structural cat-
working method Poor performance due to unfamiliarity with scope of egory included the steel, concrete, masonry, roofing, and earthwork
work
trades and accounted for 22% of the responses. The finishing/
Strict specification requirements
Quality control requirements surface category included carpentry, drywall, ceiling, painting, and
Low degree of repetition in tasks glazing and accounted for 17% of the responses. The last category
Labor force Reliability of labor force was for general contractors responsible for multiple trades. This
Availability of labor force category accounted for the remaining 17% of responses.
Inefficiencies in crew due to lack of experience/skills
Concerns about being pushed into using more
manpower and creating inefficiencies Survey Analysis
Low morale or lack of motivation
Language barrier among workers/supervisors
Equipment and Reliability of equipment or tools Research Objective 1
tools Availability of equipment or tools The first objective of the research was to determine which factors
Capability (productivity) of equipment and tools are the most prevalent and severe causes for time buffers to be
Time required to repair equipment if breakdown
added to construction task duration estimates.
occurs
Table 3 summarizes the results of Section 2, which asked the
Time required to replace equipment if breakdown
occurs participants to rank order the uncertainty in the nine categories
Materials and Receiving incorrect quantity of materials and then answer whether or not they felt the uncertainty related
components Receiving incorrect material type or damaged to that category was their responsibility to manage. It is interesting
materials to note that as the category rank went up (i.e., less uncertainty
Receiving materials for task later than expected/ associated with the category), the percentages of participants who
planned felt responsible for managing the category were higher. This means
Work and jobsite Overcrowded or cluttered work area/jobsite the categories such as management/supervision/information flow,
conditions congestion labor force, equipment and tools, and materials and components
Difficult access to work area had less uncertainty as a result of responsibility to control or
Method of material transfer required from receiving
mitigate that uncertainty. On the other hand, the detailed design/
area to task location
Distance of material transfer required from receiving working method, project characteristics, work/jobsite conditions,
area to task location and prerequisite work had the most uncertainty associated with
Management, Confidence in request for information (RFI) process them, yet less than half of the participants felt the uncertainty was
supervision, and Liability pressure (e.g., liquidated damages, their responsibility to mitigate.
information flow contractual deadlines) To determine the most prevalent and severe causes for time
Preparing for duration negotiation buffers to be added to construction task durations, the 47 factors
Positive company recognition contributing to uncertainty in task duration planning were rank
Trust in superintendent (based on reputation, ordered based on their average frequency and severity responses.
experience, and knowledge) The frequency responses were first assigned a quantitative value.
Trust in project manager (based on reputation,
The responses of never, rarely, occasionally, sometimes, frequently,
experience, and knowledge)
Trust in owner (based on reputation, experience, and usually, and always were assigned values of 0, 1, 2, 3, 4, 5, and 6,
knowledge) respectively. The top 12 (i.e., the top 25%) frequency factors and
Required coordination with other trades severity factors are summarized in Table 4. The most frequent and
Changes in scope of work (tendency of owner to severe factors coincide strongly with the overall category ranking
make changes) completed in Section 2 of the survey and previously discussed. A
Communication between owner/engineer and project few of the top ranked factors are consistent with previous research.
manager Lee et al. (2006) found that design errors (quality of documents)
Communication between project manager/ and changes (tendency for scope changes) are two of the main
superintendent and foreman factors that cause uncertainty in construction. Chan and Au (2009)
Communication between foreman and workers found project complexity to be one of the most important factors
Weather Climate—potential weather conditions associated
that contractors consider when they are pricing time-related
with project location
contract risks. Additionally, one factor just outside the top 12,
at 13, the request for information process, is consistent with that were not included in the top 12 frequency factors. This finding
Kimpland’s (2009) finding that slow responses to questions was leads to the second research objective of determining the risk pro-
one of the top external factors that impacted productivity, which file to which the different factors belong.
led to uncertainty. After speaking to a few of the respondents, it
became apparent that contract period was closely tied to the liability
pressure factor in its interpretation as contract periods result in pres- Research Objective 2
sure to finish on time and can lead to overcommitment. Similarly, The second objective of the research was to classify the 47 indi-
prerequisite work was closely associated with project complexity or vidual risk factors into risk profiles using an integrated risk assess-
interdependency of tasks. The top three factors, project complexity, ment approach.
complexity of trade task, and quality of documents, were the same Risk assessment involves identifying risks in the area of concern
for both frequency and severity, but in a slightly different order. The and then classifying the risk by assigning an appropriate risk level
factors of required coordination with other trades, contract period, (Wheeler 2002). The first objective of this research is equivalent
material transfer distance, material transfer method, and work area to risk identification because it identifies the root causes of time
access were highly ranked frequency factors that did not show up buffers in construction project tasks. As a complement, the second
in the top 12 severity factors. Conversely, the factors of strict speci- objective creates risk profiles through an integrated approach of
fication requirements, quality control requirements, low degree of histogram data analysis and a risk assessment matrix, commonly
repetition, and late materials were highly ranked severity factors used in military planning, to analyze which factors belong to each
risk profile. An integrated approach was used to create risk profiles
for the 47 factors and determine which factors had a high-frequency
Table 3. Summary of Section Two Responses and high-severity time buffer occurrence, a high-frequency and
Overall Responsible low-severity time buffer occurrence, a low-frequency and high-
category (Percentage severity time buffer occurrence, and a low-frequency and low-
Category rank “yes”) severity time buffer occurrence. First, a histogram data analysis was
Project characteristics 2 22
run on the frequency and severity responses for the 180 completed
Prerequisite work 4 48 surveys. Histograms use tabular frequencies over discrete intervals
Detailed design/working method 1 46 or bins to show the proportion of cases that fall into each of several
Labor force 7 85 categories (Howitt and Cramer 2005). The bins for this analysis
Equipment and tools 9 94 were the seven different response options for both frequency
Materials and components 6 86 and severity. An example of the histogram output for the quality-
Work/jobsite conditions 3 44 of-documents factor can be seen in Table 5.
Management/supervision/information flow 5 76 Next, four separate counts were calculated for each factor’s fre-
Weather 8 2
quency and severity. Each count was based on the sum of the upper
clusters. Clustering hierarchically groups or clusters objects so that are the causes of time buffers that construction personnel are most
objects in the same cluster are more similar to each other than concerned about due to uncertainty and potential for variation. As
objects in the other clusters (SAS Institute 2012). The causes in one moves down the steps, the confidence in the causes increases
the upper steps represent those requiring attention first as they and there is less uncertainty and need for a time buffer in the task
This resulting reverse in correlation present in the partitioned ences are evident in both of the aforementioned tables. Overall the
groups is evidence of an occurrence called Simpson’s Paradox. results indicated a perception of larger frequency and severity of
Simpson’s paradox says that a correlation present when a data uncertainty as one moves from project manager to superintendent
set is analyzed becomes reversed when the set is broken into similar to foreman. One area not highlighted by the top 12 most frequent
groups (Pearl 2009). or severe causes is the much greater emphasis put on materials,
equipment, and labor by foremen than superintendents or project
managers. For example, foremen ranked the frequency of crew in-
Research Objective 3 efficiencies, labor reliability, and labor availability 14th, 15th, and
The second objective of the research was to determine the differ- 17th, respectively. Superintendents ranked those same three factors
ences in opinion and perception between the various levels of 32nd, 31st, and 27th, while project managers ranked them 36th,
management, various trades, and various levels of experience, 40th, and 23rd. Here, those actually doing the work are most con-
the difference between general contractors and subcontractors, cerned about the resources it will take to complete the work.
and the difference between contractors using traditional manage- The next four comparisons are summarized in the following
ment approaches and those using lean construction techniques. discussions. Upon examining the survey results by trade group,
The survey results do not allow us to determine a specific fre- the utility trades were found to have the largest frequency and
quency or buffer amount for each factor as participants were asked severity for the time buffer factors. The structural trade groups were
to consider the factors one by one and independent of each other. second and the finishing trades third.
Construction personnel likely consider multiple factors at once The researchers also hypothesized that the experience level of
when estimating task durations. However, the survey responses the participants might result in different perceptions. Specifically,
do allow for a comparison of the average frequency and average the least experienced (grouped by 5 years or less) participants
severity among different groups. The first comparison made was would be concerned about more of the factors more frequently
between the different levels of management—project managers, and buffers with greater magnitude. The least experienced group
superintendents, and foremen. The survey responses were sorted was compared to a group having 5–25 years of experience and a
by respondents’ job position and then the average frequency and group having more than 25 years of experience. The survey results
severity were taken for each factor. The frequency of the factors found that although there was not a large percentage difference
as causes of uncertainty and the magnitude of buffer added to pro- between the least experienced and the more experienced groups
tect against that uncertainty were then rank ordered for each job in regards to frequency, the least experienced group buffered with
position. A total of 17 factors were required to capture the top nearly 30% more magnitude (severity) than the more experienced
12 most frequent causes, and a total of 18 factors were required groups. General contractors as well as subcontractors participated
to capture the top 12 most severe causes for each level of manage- in the survey. The scopes and areas of responsibility are different
ment. The top 12 (approximately 25%) were included to highlight for these two entities in the completion of construction projects.
the differences in perception about the causes outside of the top 5. Overall, the frequency for general contractors and subcontractors
The top five most frequent and the top three most severe causes only differed by approximately 8% with the subcontractors buffer-
were nearly identical, aside from occurring in a slightly different ing slightly more frequently. The general contractors buffered more
order. Beyond those, there were some noticeable differences in frequently than the subcontractors for all project characteristic
the top 12 among the levels of management as well as some notable factors. This finding was expected because general contractors
differences outside of the top 12. In regards to frequency, foremen are responsible for the entire project scope and all of the involved
ranked required coordination with other trades as the third most subcontractors. The subcontractors, on the other hand, were more
important; however, superintendents and project managers ranked frequently concerned about the materials, equipment, labor, and
this factor fourth and sixth, respectively. This difference is possibly work/jobsite condition factors than the general contractors. When
a result of the foremen being more involved in those coordination looking at the amount subcontractors buffer compared to general
efforts than higher management levels. Perhaps for a similar reason, contractors, the results are staggering. Subcontractors perceive
material transfer distance and method were ranked higher by the the need to buffer against the uncertainty of factors with 30%
foremen than superintendents or project managers. Another big dif- greater magnitude than the general contractors.
ference between foremen and the superintendents and project man- The participants of the survey were sorted based on their re-
agers was in the factors of overcrowded jobsite and request for sponses in an effort to make a comparison of construction person-
information process. Foremen ranked these 10th and 11th, respec- nel who use lean construction techniques such as LPS with those
tively, while overcrowded jobsite came in at 16th for superintend- who use traditional construction management techniques. One of the
ents and project managers and request for information process goals of the Last Planner System is to reduce the amount of uncer-
came in at 25th for superintendents and 22nd for project managers. tainty that exists in a construction project through the use of col-
The tendency for scope changes ranked 7th among foremen and laborative and pull planning techniques. In theory, more reliable
superintendents, but only 15th for project managers. Conversely, planning and the reduction of uncertainty will reduce variation