Construction Project Schedule Template G1 Residential Building

The document outlines a work breakdown structure (WBS) for the construction of a residential building with 1 ground floor and 1 first floor. It details the activities required to complete the structure work, finishing work, and handover the project. The structure work includes activities like foundation work, columns, slabs, tie beams, and truss erection. Finishing work includes blockwork, plastering, tiling, plumbing, electrification, doors/windows, and painting. The project is scheduled to start on 1/1/2021 and be handed over upon completion of cleaning on 5/27/2021.

Uploaded by

Sushmita Kumari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views3 pages

Construction Project Schedule Template G1 Residential Building

The document outlines a work breakdown structure (WBS) for the construction of a residential building with 1 ground floor and 1 first floor. It details the activities required to complete the structure work, finishing work, and handover the project. The structure work includes activities like foundation work, columns, slabs, tie beams, and truss erection. Finishing work includes blockwork, plastering, tiling, plumbing, electrification, doors/windows, and painting. The project is scheduled to start on 1/1/2021 and be handed over upon completion of cleaning on 5/27/2021.

Uploaded by

Sushmita Kumari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Project Name: Construction of G+1 Residential Building

Project Owner: ABC


Project Contractor: XYZ
Project Start Date: 1/1/2021

WBS ID Activity Duration Predecessor ID Lead

1 Building Project
A Site Handover to Contractor 0
1.1 Structure Work
1.1.1 Foundation
1.1.1.1 Excavation 3 A 1
1.1.1.2 PCC 2 1.1.1.1 0
1.1.1.3 Reinforcement & Shuttering 6 1.1.1.2 1
1.1.1.4 Casting with RCC 6 1.1.1.3 1
1.1.2 Plinth Level
1.1.2.1 Columns up to Plinth Beam Bottom 6 1.1.1.4 0
1.1.2.2 Backfilling & Compaction 3 1.1.2.1 0
1.1.2.3 Plinth Beam Reinf. & Shuttering 6 1.1.2.2 0
1.1.2.4 Casting of Plinth Beam with RCC 1 1.1.2.3 0
1.1.2.5 Ground Soling & Compaction 4 1.1.3.5 0
1.1.3 First Slab
1.1.3.1 Columns up to First Slab 6 1.1.2.4 0
1.1.3.2 Shuttering & Reinforcement of Beams & Slab 14 1.1.3.1 2
1.1.3.3 Casting of First Floor Beams & Slab 2 1.1.3.2 0
1.1.3.4 Curing Period 21 1.1.3.3 0
1.1.3.5 Deshuttering 7 1.1.3.3 0
1.1.4 Second Floor Tie Beams
1.1.4.1 Columns up to Tie Beam Bottom 6 1.1.3.3 0
1.1.4.2 Shuttering & Reinforcement of Tie Beams 10 1.1.4.1 2
1.1.4.3 Casting of Tie Beams with RCC 1 1.1.4.2 0
1.1.4.4 Curing Period for Deshuttering 21 1.1.4.3 0
1.1.4.5 Deshuttering 5 1.1.4.4 0
1.1.5 Truss & Sheeting
1.1.5.1 Waiting Period for Tie Beams to Gain Strength 7 1.1.4.4 0
1.1.5.2 Truss Erection above Tie Beams 3 1.1.4.4 0
1.1.5.3 Sheeting Work 5 1.1.5.2 0
1.2 Finishing Work
1.2.1 Blockwork, Plastering, False Ceiling Work & Tiling
1.2.1.1 Blockwork and Plaster for Ground Floor 15 1.1.3.5 0
1.2.1.2 Blockwork and Plaster for First Floor 15 1.1.4.5 0
1.2.1.3 False Ceiling Work for First Floor 8 1.2.1.2 0
1.2.1.4 Tiles Work for Ground Floor 10 1.2.1.1 0
1.2.1.5 Tiles Work for First Floor 10 1.2.1.2 0
1.2.2 Plumbing & Sanitary Works
1.2.2.1 Plumbing & Sanitary for Ground Floor 10 1.2.1.1 0
1.2.2.2 Plumbing & Sanitary for First Floor 10 1.2.2.1 0
1.2.3 Electrification Works
1.2.3.1 Electrification for Ground Floor 10 1.2.1.1 0
1.2.3.2 Electrification for First Floor 10 1.2.2.1 0
1.2.4 Doors & Windows Fixing
1.2.4.1 Doors & Windows Fixing for Ground Floor 10 1.2.1.1 0
1.2.4.2 Doors & Windows Fixing for First Floor 10 1.2.2.1 0
1.2.5 Painting and Finishing
1.2.5.1 Painting & Finishing for Ground Floor 15 1.2.3.1 0
1.2.5.2 Painting & Finishing for First Floor 15 1.2.3.2 0
1.2.5.3 Cleaning of Entire Structure 2 1.2.5.2 0
B Handover to Client 0 1.2.5.2 0
g

Link with Start Date End Date


Predecessor

1/1/2021 1/1/2021

FS 1/2/2021 1/5/2021
FS 1/6/2021 1/8/2021
SS 1/7/2021 1/13/2021
SS 1/8/2021 1/14/2021

FS 1/15/2021 1/21/2021
FS 1/22/2021 1/25/2021
FS 1/26/2021 2/1/2021
FS 2/2/2021 2/3/2021
FS 3/26/2021 3/30/2021

FS 2/4/2021 2/10/2021
SS 2/6/2021 2/20/2021
FS 2/21/2021 2/23/2021
FS 2/24/2021 3/17/2021
FS 3/18/2021 3/25/2021

FS 2/24/2021 3/2/2021
SS 2/26/2021 3/8/2021
FS 3/9/2021 3/10/2021
FS 3/11/2021 4/1/2021
FS 4/2/2021 4/7/2021

FS 3/11/2021 3/18/2021
FS 3/19/2021 3/22/2021
FS 3/23/2021 3/28/2021

FS 3/26/2021 4/10/2021
FS 4/11/2021 4/26/2021
FS 4/27/2021 5/5/2021
FS 5/6/2021 5/16/2021
FS 5/17/2021 5/27/2021

FS 4/11/2021 4/21/2021
FS 4/22/2021 5/2/2021

FS 4/11/2021 4/21/2021
FS 4/22/2021 5/2/2021

FS 4/11/2021 4/21/2021
FS 4/22/2021 5/2/2021

FS 4/22/2021 5/7/2021
FS 5/8/2021 5/23/2021
FS 5/24/2021 5/26/2021
FS 5/27/2021 5/27/2021
Remarks/Assumptions

New acitivity added as start milestone.

Start of work. Excavation to be done by excavator after demarcation by site engineer.

Reinf. & Shuttering work will start from one end of the building. Assuming 5 Footings per day. Total 27 footings.

Assuming 5 sets of column shuttering. Duration= (27 Columns/5 lift everyday)= 5.4 days say 6 days
Assumed Backfilling duration=1 day, watering=1 day and compaction=1 day.

Grade Slab & Soling Works after deshuttering of First Floor Slab

Shutt. & Reinf. Work to start after column casting of first two grids.

New activity added to minimise the deshuttering lead by 21 days

Shutt. & Reinf. Work to start after column casting of first two grids.

New activity added to minimise the deshuttering lead

New activity added to minimise the truss erection lead

The truss erection team will continue the sheeting work, thus FS relationship.

One blockwork and plaster team will be used for the project. Thus, the first floor to start after ground floor.

One tiling team will be used for the project. Thus, the first floor to start after ground floor.

One plumbing team will be used for the project. Thus, the first floor to start after ground floor.

One electrical team will be used for the project. Thus, the first floor to start after ground floor.

One carpenter team will be used for the project. Thus, the first floor to start after ground floor.

One painting team will be used for the project. Thus, the first floor to start after ground floor.

New activity added as completion milestone.