Project Name: Construction of G+1 Residential Building
Project Owner: ABC
Project Contractor: XYZ
Project Start Date: 1/1/2021
WBS ID Activity Duration Predecessor ID Lead
1 Building Project
A Site Handover to Contractor 0
1.1 Structure Work
1.1.1 Foundation
1.1.1.1 Excavation 3 A 1
1.1.1.2 PCC 2 1.1.1.1 0
1.1.1.3 Reinforcement & Shuttering 6 1.1.1.2 1
1.1.1.4 Casting with RCC 6 1.1.1.3 1
1.1.2 Plinth Level
1.1.2.1 Columns up to Plinth Beam Bottom 6 1.1.1.4 0
1.1.2.2 Backfilling & Compaction 3 1.1.2.1 0
1.1.2.3 Plinth Beam Reinf. & Shuttering 6 1.1.2.2 0
1.1.2.4 Casting of Plinth Beam with RCC 1 1.1.2.3 0
1.1.2.5 Ground Soling & Compaction 4 1.1.3.5 0
1.1.3 First Slab
1.1.3.1 Columns up to First Slab 6 1.1.2.4 0
1.1.3.2 Shuttering & Reinforcement of Beams & Slab 14 1.1.3.1 2
1.1.3.3 Casting of First Floor Beams & Slab 2 1.1.3.2 0
1.1.3.4 Curing Period 21 1.1.3.3 0
1.1.3.5 Deshuttering 7 1.1.3.3 0
1.1.4 Second Floor Tie Beams
1.1.4.1 Columns up to Tie Beam Bottom 6 1.1.3.3 0
1.1.4.2 Shuttering & Reinforcement of Tie Beams 10 1.1.4.1 2
1.1.4.3 Casting of Tie Beams with RCC 1 1.1.4.2 0
1.1.4.4 Curing Period for Deshuttering 21 1.1.4.3 0
1.1.4.5 Deshuttering 5 1.1.4.4 0
1.1.5 Truss & Sheeting
1.1.5.1 Waiting Period for Tie Beams to Gain Strength 7 1.1.4.4 0
1.1.5.2 Truss Erection above Tie Beams 3 1.1.4.4 0
1.1.5.3 Sheeting Work 5 1.1.5.2 0
1.2 Finishing Work
1.2.1 Blockwork, Plastering, False Ceiling Work & Tiling
1.2.1.1 Blockwork and Plaster for Ground Floor 15 1.1.3.5 0
1.2.1.2 Blockwork and Plaster for First Floor 15 1.1.4.5 0
1.2.1.3 False Ceiling Work for First Floor 8 1.2.1.2 0
1.2.1.4 Tiles Work for Ground Floor 10 1.2.1.1 0
1.2.1.5 Tiles Work for First Floor 10 1.2.1.2 0
1.2.2 Plumbing & Sanitary Works
1.2.2.1 Plumbing & Sanitary for Ground Floor 10 1.2.1.1 0
1.2.2.2 Plumbing & Sanitary for First Floor 10 1.2.2.1 0
1.2.3 Electrification Works
1.2.3.1 Electrification for Ground Floor 10 1.2.1.1 0
1.2.3.2 Electrification for First Floor 10 1.2.2.1 0
1.2.4 Doors & Windows Fixing
1.2.4.1 Doors & Windows Fixing for Ground Floor 10 1.2.1.1 0
1.2.4.2 Doors & Windows Fixing for First Floor 10 1.2.2.1 0
1.2.5 Painting and Finishing
1.2.5.1 Painting & Finishing for Ground Floor 15 1.2.3.1 0
1.2.5.2 Painting & Finishing for First Floor 15 1.2.3.2 0
1.2.5.3 Cleaning of Entire Structure 2 1.2.5.2 0
B Handover to Client 0 1.2.5.2 0
g
Link with Start Date End Date
Predecessor
1/1/2021 1/1/2021
FS 1/2/2021 1/5/2021
FS 1/6/2021 1/8/2021
SS 1/7/2021 1/13/2021
SS 1/8/2021 1/14/2021
FS 1/15/2021 1/21/2021
FS 1/22/2021 1/25/2021
FS 1/26/2021 2/1/2021
FS 2/2/2021 2/3/2021
FS 3/26/2021 3/30/2021
FS 2/4/2021 2/10/2021
SS 2/6/2021 2/20/2021
FS 2/21/2021 2/23/2021
FS 2/24/2021 3/17/2021
FS 3/18/2021 3/25/2021
FS 2/24/2021 3/2/2021
SS 2/26/2021 3/8/2021
FS 3/9/2021 3/10/2021
FS 3/11/2021 4/1/2021
FS 4/2/2021 4/7/2021
FS 3/11/2021 3/18/2021
FS 3/19/2021 3/22/2021
FS 3/23/2021 3/28/2021
FS 3/26/2021 4/10/2021
FS 4/11/2021 4/26/2021
FS 4/27/2021 5/5/2021
FS 5/6/2021 5/16/2021
FS 5/17/2021 5/27/2021
FS 4/11/2021 4/21/2021
FS 4/22/2021 5/2/2021
FS 4/11/2021 4/21/2021
FS 4/22/2021 5/2/2021
FS 4/11/2021 4/21/2021
FS 4/22/2021 5/2/2021
FS 4/22/2021 5/7/2021
FS 5/8/2021 5/23/2021
FS 5/24/2021 5/26/2021
FS 5/27/2021 5/27/2021
Remarks/Assumptions
New acitivity added as start milestone.
Start of work. Excavation to be done by excavator after demarcation by site engineer.
Reinf. & Shuttering work will start from one end of the building. Assuming 5 Footings per day. Total 27 footings.
Assuming 5 sets of column shuttering. Duration= (27 Columns/5 lift everyday)= 5.4 days say 6 days
Assumed Backfilling duration=1 day, watering=1 day and compaction=1 day.
Grade Slab & Soling Works after deshuttering of First Floor Slab
Shutt. & Reinf. Work to start after column casting of first two grids.
New activity added to minimise the deshuttering lead by 21 days
Shutt. & Reinf. Work to start after column casting of first two grids.
New activity added to minimise the deshuttering lead
New activity added to minimise the truss erection lead
The truss erection team will continue the sheeting work, thus FS relationship.
One blockwork and plaster team will be used for the project. Thus, the first floor to start after ground floor.
One tiling team will be used for the project. Thus, the first floor to start after ground floor.
One plumbing team will be used for the project. Thus, the first floor to start after ground floor.
One electrical team will be used for the project. Thus, the first floor to start after ground floor.
One carpenter team will be used for the project. Thus, the first floor to start after ground floor.
One painting team will be used for the project. Thus, the first floor to start after ground floor.
New activity added as completion milestone.