Quotation - Jeff
Quotation - Jeff
: 7 February 2023
TO :
MR. JEFFREY RODRIGUEZ
Block 17 Lot 13, Camellla Homes, Imus Cavite
PROJECT
PROJECT: HOUSE EXTENSION AND IMPROVEMENT
ITEMS DESCRIPTION QTY UOM UNIT PRICE TOTAL PRICE
I. GENERAL REQUIREMENTS
1 Mobilization / Demobilization 1.00 lot -
2 Delivery and hauling of materials/debris 1.00 lot 5,000.00 5,000.00
3 Scaffolding Rent 1.00 lot 5,000.00 5,000.00
4 Complete Set of Plans for Building Permits (varies) 1.00 lot 10,000.00 10,000.00
1 Demolition of existing back wall and 2nd floor partition 1.00 lot 2,000.00 2,000.00
13 Roofing using long span, tubular pipe and angular bars 5.90 m² 6,601.69 38,950.00
Prepared by:
JOSHUA GO
Quantity Surveyor