Dep 37.81.10.32 Structural Steel Fabrication of Small Deepwater Offshore Skids Facilities Packages and Subsea Manifolds
Dep 37.81.10.32 Structural Steel Fabrication of Small Deepwater Offshore Skids Facilities Packages and Subsea Manifolds
DEP 37.81.10.32-Gen.
September 2011
(Amendment A01 has been incorporated – September 2012)
(Amendment A02 has been incorporated – February 2013)
ECCN EAR99
This document contains information that is classified as EAR99 and, as a consequence, can neither be exported nor re-exported to any country which is under an
embargo of the U.S. government pursuant to Part 746 of the Export Administration Regulations (15 C.F R. Part 746) nor can be made available to any national of such
country. In addition, the information in this document cannot be exported nor re-exported to an end-user or for an end-use that is prohibited by Part 744 of the Export
Administration Regulations (15 C.F.R. Part 744).
PREFACE
DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global Solutions
International B.V. (Shell GSI) and, in some cases, of other Shell Companies.
These views are based on the experience acquired during involvement with the design, construction, operation and
maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference international,
regional, national and industry standards.
The objective is to set the recommended standard for good design and engineering practice to be applied by Shell
companies in oil and gas production, oil refining, gas handling, gasification, chemical processing, or any other such facility,
and thereby to help achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to Shell companies for their consideration and decision to
implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at each
locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the
quality of their work and the attainment of the required design and engineering standards. In particular, for those
requirements not specifically covered, the Principal will typically expect them to follow those design and engineering
practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or
Manufacturer/Supplier shall, without detracting from his own respons bility, consult the Principal.
The right to obtain and to use DEPs is restricted, and is typically granted by Shell GSI (and in some cases by other Shell
Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and
other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three
categories of users of DEPs can be distinguished:
1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by these
Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement.
2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part of
a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI disclaims
any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person
whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination of DEPs
or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell Company. The
benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies affiliated to these
companies, that may issue DEPs or advise or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and the
DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be returned after
use, including any copies which shall only be made by users with the express prior written consent of Shell GSI. The
copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe custody and Shell
GSI may at any time require information satisfactory to them in order to ascertain how users implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................ 5
1.1 SCOPE........................................................................................................................ 5
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS ......... 5
1.3 DEFINITIONS ............................................................................................................. 5
1.4 CROSS-REFERENCES ............................................................................................. 7
1.5 SUMMARY OF MAIN CHANGES ............................................................................... 7
1.6 COMMENTS ON THIS DEP ....................................................................................... 7
1.7 DUAL UNITS ............................................................................................................... 8
2. GENERAL REQUIREMENTS .................................................................................... 9
2.1 GENERAL ................................................................................................................... 9
2.2 STRUCTURE CATEGORY......................................................................................... 9
2.3 WORK, MATERIALS, AND SUPERVISION ............................................................... 9
2.4 REFERENCE COPIES ............................................................................................... 9
2.5 TYPICAL WELDING DETAILS DRAWING................................................................. 9
2.6 APPLICABLE DOCUMENTS .................................................................................... 10
2.7 INCONSISTENCIES ................................................................................................. 10
2.8 SIMILAR DETAILS .................................................................................................... 10
2.9 SUBCONTRACTORS ............................................................................................... 10
3. FABRICATION ......................................................................................................... 10
3.1 GENERAL FABRICATION REQUIREMENTS ......................................................... 10
3.2 FABRICATION AIDS ................................................................................................ 10
3.3 DIMENSIONS AND TOLERANCES ......................................................................... 11
3.4 CLEAN-UP REQUIREMENTS .................................................................................. 11
3.5 LIFTING PADEYES .................................................................................................. 11
3.6 BOLTING .................................................................................................................. 11
3.7 WELD TRACEABILITY ............................................................................................. 12
3.8 AS-BUILT DATA ....................................................................................................... 12
4. MATERIALS ............................................................................................................. 13
4.1 CONTRACTOR FURNISHED MATERIALS ............................................................. 13
4.2 STRUCTURAL STEEL ............................................................................................. 13
4.3 MISCELLANEOUS ITEMS ....................................................................................... 13
4.4 MILL CERTIFICATES ............................................................................................... 14
4.5 PRINCIPAL-FURNISHED MATERIALS ................................................................... 14
4.6 MATERIAL TRACEABILITY ..................................................................................... 14
5. WELDING ................................................................................................................. 15
5.1 SCOPE...................................................................................................................... 15
5.2 GENERAL ................................................................................................................. 15
5.3 MATERIAL REQUIREMENTS .................................................................................. 15
5.4 WELDING QUALIFICATIONS – PROCEDURES AND PERFORMANCE ............... 16
5.5 EXTENT OF WELDING ............................................................................................ 18
5.6 WORKMANSHIP AND TECHNIQUE ....................................................................... 18
6. INSPECTION ............................................................................................................ 20
6.1 GENERAL ................................................................................................................. 20
6.2 INSPECTION OF STRUCTURAL WELDING ........................................................... 20
6.3 FUNCTIONAL TESTING .......................................................................................... 21
7. PAINTING AND PROTECTIVE COATINGS ............................................................ 22
8. LOADOUT AND TIEDOWN ..................................................................................... 22
8.1 GENERAL ................................................................................................................. 22
8.2 TRANSPORTATION AND ARRANGEMENTS......................................................... 22
8.3 LOADING MATERIALS ............................................................................................ 22
8.4 DAMAGES ................................................................................................................ 22
9. REFERENCES ......................................................................................................... 23
APPENDICES
APPENDIX 1 SPECIAL REQUIREMENTS FOR GMAW-S WELDING ................................ 24
APPENDIX 2 CHARPY IMPACT TESTING .......................................................................... 28
APPENDIX 3 TABLE OF DELIVERABLES .......................................................................... 30
APPENDIX 4 TYPICAL WELDING DETAILS DRAWING (US Customary Version) ......... 31
APPENDIX 5 TYPICAL WELDING DETAILS DRAWING (Metric Version) ........................ 36
1. INTRODUCTION
1.1 SCOPE
This new DEP specifies requirements and gives recommendations for the fabrication of
structural steel skids, facility packages, subsea sleds, subsea manifolds, and other
miscellaneous structural steel structures. It is applicable for designs performed using
DEP 37.81.10.31-Gen.
EPP Projects Civil/Marine Engineering should be consulted on the use of this DEP for
applications outside those noted above.
This DEPapplies to small statically designed steel structures, less than 907 metric tons
(1000 short tons), that are not subject to significant global cyclic stress that may lead to
fatigue failure over the structural life.
Steel structures covered in this DEP are categorized as either a Type-A or Type-B
structure. The category is dependent on weight and/or function and is defined by the
Principal. See (2) for default category.
This DEP is based on:
• AISC-ASD
• AWS D1.1
• API RP 2A-WSD
The additional and/or modified requirements contained in this DEP form the complete
specification.
This DEP replaces the former SIEP standard DEP 37.81.10.32-EPP dated January 2010.
1.3 DEFINITIONS
1.3.1 General definitions
The Contractor is the party that carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation of a
facility. The Principal may undertake all or part of the duties of the Contractor.
The Manufacturer/Supplier is the party that manufactures or supplies equipment and
services to perform the duties specified by the Contractor.
The Principal is the party that initiates the project and ultimately pays for it. The Principal
may also include an agent or consultant authorised to act for, and on behalf of, the
Principal.
The word shall indicates a requirement.
The word should indicates a recommendation.
1.3.2 Specific definitions
Term Definition
Accept,
The Principal’s written agreement that the submitted item has been
Accepted, or
performed in accordance with the requirements.
Acceptance
Approve,
Approved, or The Principal’s written approval process
Approval
Auditable Requirement that is observable, measurable, is neither vague nor
(requirement) ambiguous, and has finite acceptance/rejection criteria.
The detailed engineering drawings prepared for this project and all
Contract
official revisions to those drawings. The Tie Specification or General
Drawings
Data Sheet contains a list of those drawings.
The Principal’s right, but not obligation, to comment on the submitted
Review
item. Contractor may begin construction of the item following submittal.
Document, established by consensus and approved by a recognized
body, that provides, for common and repeated use, rules, guidelines or
Standard
characteristics for activities or their results, aimed at the achievement of
the optimum degree of order in a given context.
Standard, primarily pictorial, representing an item or configuration and
Standard
considered to have wide applicability in Shell International Exploration
Drawing
and Production – EP Projects.
Shall mean any person or company having a subcontract with any
Subcontractor
Contractor to perform work covered under this DEP.
Structures shall include skids and packages weighing less than 455
Type A
metric ton (500 short tons), except for subsea structures.
Structures shall include skids and packages weighing more than 455
Type B metric ton (500 short tons) but less than 907 metric tons (1000 short
tons), and subsea structures (sleds and manifolds) regardless of weight.
1.3.3 Abbreviations
Term Definition
API American Petroleum Institute.
ASME American Society of Mechanical Engineers.
AWS American Welding Society.
BOP Bead on Plate.
BS British Standard.
DEP Design and Engineering Practice.
EPP SIEP - Exploration and Production – Projects.
ID Internal Diameter.
FY Specified Minimum Yield Stress
Term Definition
ISO International Standards Organization.
NDT Non Destructive Testing
OU An Operating Unit of the Royal Dutch/Shell Group.
PQR Procedure Qualification Record
PQT Procedure Qualification Testing
QA/QC Quality Assurance / Quality Control.
SIEP Shell International Exploration and Production.
SWL Safe Working Load.
WPS Welding Procedure Specification.
1.4 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section
number is shown in brackets ( ). Other documents referenced by this DEP are listed in (9).
In this Amendment, the Figures shown in (Appendix 4) and (Appendix 5) have been
replaced with higher quality images.
Comments on this DEP may be submitted to the Administrator using one of the following
options:
Feedback that has been registered in the DEP Feedback System by using one of the above
options will be reviewed by the DEP Custodian for potential improvements to the DEP.
2. GENERAL REQUIREMENTS
2.1 GENERAL
A Scope of Work document may be issued by Principal, detailing the project-specific
general requirements. The Scope of Work shall supplement / supersede the specific
requirements contained within (2).
Alternative codes for the fabrication, welding, and inspection of the structure may be
proposed by Contractor for approval by the Principal, prior to the start of fabrication. The
proposed codes shall provide a basis with an equivalent set of requirements for the
fabrication, welding and inspection. The specific requirements in this DEP, Contract
Drawings, and Standard Drawings shall apply.
2.7 INCONSISTENCIES
Contractor shall carefully study and compare Contract Drawings and/or Standard Drawings,
this DEP, and other instructions and shall report at once to the Principal any error,
inconsistency, or omission.
2.9 SUBCONTRACTORS
Approval of all Subcontractors shall be obtained from the Principal prior to the start of the
subcontractor work.
It shall be Contractor’s responsibility to ensure that all work done by the Subcontractors is
in accordance with this DEP.
The Principal’s inspection rights also apply to all work done by the Subcontractor.
3. FABRICATION
The Principal reserves the right to restrict the location and welding of such items.
Stamp: 4x
SWL 25 tons
0 - 90°
3.6 BOLTING
Bolts shall be as noted on the welding detail drawings.
Bolts, nuts and washers shall be galvanized or coated with Sermagard, or equivalent
material approved by the Principal.
4. MATERIALS
Phenolic Grating:
Phenolic grating shall be slip resistant and have ultraviolet stabilizer. Phenolic grating
manufacturer shall be approved by the Principal.
All phenolic grating shall have 38 mm (1-1/2 inch) bearing bars spaced on 38 mm
(1-1/2 inch) centers, and be approved by the Principal. All phenolic grating shall be
attached to the beams using a fastening system. Fasteners are required at the end of each
grating section and every other support beam, spaced no more than 406 mm (16 inch)
apart (i.e., 3 fasteners for a 914 mm [3’] wide panel at each tie-down location).
Every piece/panel of grating shall have a minimum of six grating fasteners. Additionally,
each panel shall have three fasteners per beam crossing. If manufacturer’s requirements
are more restrictive, manufacturer’s requirements shall govern.
Fastening system shall be approved by the Principal.
Mechanical fasteners are not designed to resist lateral forces (skidding equipment on
grating).
Grating – General:
Grating bearing bars shall be supported at both ends. Cantilevered grating shall be
acceptable only with the Principal approval.
Edge grating panels free to move due to location of a hole in the decking, or at the edge of
the platform and not restrained by a minimum of two fixed handrail posts or sockets, shall
be restrained by one of the following methods:
a) Two – 6 mm x 26 mm x 67 mm (¼ inch x 1 inch x 3 inch) long bars, seal welded to
the supporting steel beam on the free side of the grating. One bar shall be located
near one end of the grating panel edge, and the other bar near the other end of the
grating panel edge. The bars shall be located to allow maximum 13 mm (½ inch) or
less grating panel movement in the direction of the free edge.
b) The entire grating panel shall be secured to the supporting steel beams using
mechanical fasteners.
c) Secure the free edge of the grating from moving by using a minimum of two –
19 mm (¾ inch) wide stainless steel banding straps, looped around the grating and
the supporting steel beam, and tightened to prevent grating movement.
5. WELDING
5.1 SCOPE
This section covers the materials, welding, and inspection required for fabrication of steel
structures for steel skids and miscellaneous items.
5.2 GENERAL
5.2.1 General Authority for Welding
The general authority for welding shall be AWS D1.1 and (Appendix 4) or (Appendix 5)
“Typical Welding Details” drawing with exceptions, clarifications, or additions as noted
herein.
Welding symbols shall be interpreted in accordance with AWS A2.4.
5.2.2 Welding Processes
The shielded metal arc welding (SMAW), submerged arc welding (SAW) and flux cored arc
welding (FCAW) processes are approved by the Principal. Other processes may be
submitted to the Principal for consideration.
The use of gas metal arc welding (GMAW) may be approved by the Principal for specific
applications; however, additional restrictions and limitations shall be applicable as given in
(Appendix 1).
Capacitance discharge stud welding shall only be used on steels with FY less than or equal
to 317 MPa (46 ksi).
Direct fastening studs (powder actuated, pneumatic, or gas powered systems) may be used
on all steels, subject to approval by the Principal. The studs shall be located no closer than
50 mm (two inches) from any weld or free edge. Paint damage must be repaired with
special attention given to the backside of beams and plates.
5.2.3 Qualification Records
Records of final weld procedure testing, welder and welding operator qualification test
results shall be submitted to the Principal for approval.
Essential Variables
a) When Charpy toughness testing is not required for weld metal or HAZ per(Appendix
4, Table A-1) or (Appendix 5, Table A-1), the essential variables specified per AWS
D1.1 for the welding process shall apply.
b) When Charpy toughness testing is required, any change in essential variables that
may affect the resulting toughness properties shall be prohibited without
re-qualification. The following additional items shall be considered essential
variables:
• A change in flux core wire manufacturer.
Charpy Testing
All impact testing for toughness shall be in accordance with (Appendix 2).
The Charpy requirement for welding procedures to join two different types of steel (e.g.,
250 MPa to 414 MPa – [GR36 to GR60]) shall be selected from (Appendix 4, Table A-1) or
(Appendix 5, Table A-1) applicable to the lower type joined (e.g., 250MPa – [GR36]).
However, all limitations on heat input preheat, etc.; applicable to either grade shall be
observed.
Joint details for testing shall conform to the details shown on the (Appendix 4) or
(Appendix 5) “Typical Welding Details” drawing of the Contract Drawings and/or Standard
Drawings and the provisions of (Appendix 2).
5.4.3 Additional Welding Procedure Requirements for Type-B Structures
The following hardness requirements apply to Type-B structures. These requirements are
in addition to (5.4.2).
All WPS’s used for Type-B structures, regardless of whether they fall into the pre-qualified
or qualified by testing category, shall be qualified by macrosection microhardness survey
and bead-on-plate (BOP) hardness testing as follows.
5.4.3.1 PQT Weld
A PQT weld shall be made using the WPS for each base-metal with each welding
consumable to be permitted by the WPS using PQT plate or pipe, as applicable, complying
with AWS D1.1 Table 4.2, 4.3 or 4.4, as applicable. One macrosection shall be extracted
from near the middle of the PQT weld. Macrosections shall be polished to a metallographic
finish and etched in a 5-10% Nital solution.
5.4.3.2 Macrosection Microhardness Survey
A Vickers microhardness survey utilizing an applied load of 10 kgf (i.e., HV 10) shall be
performed on a macrosection from the test weld in accordance with EN 1043-1. Hardness
test indention locations shall be as recommended by EN 1043-1.
5.4.3.3 BOP Test
A BOP weld pass and Vickers microhardness survey shall be made on each base metal
with each consumable to be permitted by the WPS in accordance with BSI BS 7363
Type 2. The length of the deposited bead shall not exceed the minimum permissible bead
length for the WPS. This pass shall be made with the lowest permissible heat input and
preheat temperature applicable to the WPS being qualified.
Location of hardness readings shall be as shown in Figure 9 of BSI BS 7363. Additionally,
an all-weld-metal hardness reading shall be obtained. Hardness measurements shall be
HV 10.
5.4.3.4 Acceptable Microhardness
The maximum acceptable microhardness for the hardness traverses required by (5.4.3.2)
and (5.4.3.3) shall be 350 HV10, unless specifically approved otherwise by the Principal
and Contractor, if applicable.
c) No arc strikes outside of the weld groove shall be permitted. Repair of inadvertent
arc strikes shall be done by grinding followed by visual and Magnetic Particle
inspection.
d) The root side of complete joint penetration groove welds shall be back-gouged,
using grinding, air-arc gouging or chipping, to sound metal before any weld is
applied to the backside. The groove shall be prepared by grinding to provide the
proper shape and bevel for the welding procedure. Oxy-fuel gouging shall not be
permitted.
5.6.2 Preparation
Requirements for the acceptance of surfaces to be welded shall be as follows:
a) Surfaces produced by carbon-arc gouging or cutting, or surfaces showing carbon
deposits due to oxy-fuel cutting or heating, shall be dressed by blasting, grinding,
brushing, or chipping, as required to remove carbon residue.
b) The workmanship criteria for the maximum surface roughness of weld bevel faces
shall be as shown in AWS C4.1, Surface Roughness Guide, Sample 3.
c) Surfaces of complete joint penetration groove welds shall be free of primers or
coatings. Anti-spatter compounds shall not be applied to surfaces to be welded
including weld bevels and weld beads. Such compounds may be applied to
completed welds after acceptance by visual examination.
Requirements for fit-up shall be as follows:
a) In-place fitting and trimming should be avoided. However, when fitting and trimming
in-place is necessary, Contractor should shift the member away from the connection
before trimming is begun.
b) The Principal, at its option, may require that weld fit-up and preheat temperature be
checked and accepted prior to placing the first pass. Any deviation from the WPS,
such as wide gaps or inadequate preheat, shall be rectified before welding
commences.
5.6.3 Weld Repairs
Contractor shall develop a weld repair process and include it in each weld procedure.
6. INSPECTION
6.1 GENERAL
Contractor shall furnish sufficient supervisory/quality control personnel to ensure that
materials and workmanship meet the requirements of this specification, and other codes
and specifications cited herein. Welding Inspectors, with qualifications in accordance with
AWS D1.1, shall be required. Additional testing and inspection may be performed at the
Principal’s prerogative, to verify that these requirements have been met. The Principal
shall approve all Quality Control Staff prior to starting fabrication.
The Principal shall have the right to inspect any and all equipment, material, coatings, or
workmanship involved in the construction and assembly of any component covered under
this DEP. Contractor shall provide free entry at all times for any personnel or equipment to
any work or component location so that verification inspection and testing may be
performed.
Principal may elect to use any applicable nondestructive testing method to perform
verification inspection and testing, including radiography, ultrasonics, magnetic particle,
liquid penetrants, hardness, etc.
Inspection for Type-A and Type-B structures shall be in accordance with AWS D1.1 and
(Appendix 4) or (Appendix 5), “Typical Welding Details”. Additionally, for Type-B structures,
Contractor shall develop an Inspection and Test Plan for the Principal’s approval.
Structural Tubes
Diameter Diameter
< 325 mm (12 - 3/4 in) > 325 mm (12 - 3/4 in)
Rolled Shapes
AISC-ASD* AISC-ASD*
Group I to III Group IV & V
Statically Loaded Cyclically Loaded
Non-Tubular Connections Non-Tubular Connections
*Note: AISC-ASD Properties Table 1 and Table 2 refer to ASTM A6 (1989) Groups.
Fabricated Shapes
(Including Stiffeners)
8.1 GENERAL
Contractor shall furnish all engineering, supervision, personnel, materials, equipment and
appurtenances necessary at Contractor’s yard to loadout and tie down all items on the
Principal-furnished transportation. Truck-loaded items shall be safely secured for highway
transportation as required by applicable Operating Unit and Governmental regulations
(49 CFR Parts 392 and 393 or applicable local requirements).
Contractor shall assume sole responsibility for proper and safe execution of all loadout
operations, but the location and arrangement of components on barge(s) and the method
and points of tie-down shall be determined by the Installation Contractor and Certified by
(Principal) Marine Surveyor.
Contractor shall be responsible for all barge-ballasting operations during loadout and shall
also be responsible for ballasting to the towing condition, as specified by the Installation
Contractor and Certified by (Principal) Marine Surveyor.
Contractor shall submit to the Principal the loadout / lift plan with all supporting calculations
prior to loadout.
If Contractor is required to make delivery of the finished item to any of the Principal’s
terminals or other designed location, the same responsibility applies on the part of
Contractor for proper and safe execution of loadout operations and delivery.
8.4 DAMAGES
Contractor shall report and repair damages caused during loadout, regardless of the cause
of damage. Repair of damages, including touch-up painting, shall be made in accordance
with the Principal-approved coating system, applicable Contract specifications, applicable
Contract Drawings and/or Standard Drawings.
9. REFERENCES
In this DEP, reference is made to the following publications:
NOTES: 1. Unless specifically designated by date, the latest edition of each publication shall be used,
together with any amendments/supplements/revisions thereto.
2. The DEPs and most referenced external standards are available to Shell staff on the SWW (Shell
Wide Web) at http://sww.shell.com/standards/.
Amendment A02
SHELL STANDARDS
INDUSTRY STANDARDS
US Department of Transportation (DOT) Code of Federal
Regulations 49: Transportation
Part 393: Parts and accessories necessary for safe operation 49 CFR Part 393
American Institute for Steel Construction (AISC) - Steel Construction
AISC 325 (2011)
Manual, Working Stress Design
API RP 2A-WSD Twenty-
Recommended Practice for Planning, Designing, and Constructing
First Edition; Errata and
Fixed Offshore Platforms – Working Stress Design.
Supplement 3: October 2007
Specification for the Fabrication of Structural Steel Pipe API Spec 2B
Specification for Line Pipe. API Specification 5L
Standard Specification for General Requirements for Rolled
ASTM A6
Structural Steel Bars, Plates, Shapes, and Sheet Piling
Standard Test Methods and Definitions for Mechanical Testing of
ASTM A370
Steel Products
Standard Test Methods for Notched Bar Impact Testing of Metallic
ASTM E23
Materials
Standard Symbols for Welding, Brazing, and Nondestructive
AWS A2.4
Examination.
Criteria for Describing Oxygen-Cut Surfaces and Oxygen Cutting
AWS C4.1
Surface Roughness Gauge.
Structural Welding Code (Steel). AWS D1.1:2008
Greater than
All other shop and yard locations Not Allowed
317MPa (GR46)
1.2 REQUIREMENTS
GMAW-S may only be used providing the following requirements are met:
a) For joints with dissimilar steel groups, the restrictions applicable to the
lower group apply.
b) The root-opening shall be detailed per AWS D1.1 for T-, Y-, and
K-connections. All other details shall be as qualified. The root-face shall
vary from 0 mm (0/32 inch) to 1 mm (1/32 inch) featheredge.
c) Weld groove preparation shall include either grinding or filing of beveled
surfaces to bright metal prior to fit-up, or blasting of the groove preparation
prior to welding. “Prior to” is defined as within the same working shift,
which precludes the reformation of surface oxide. Any contact with
moisture shall require re-preparation. Welding of flame-cut surfaces
without cleaning, as described above, is not acceptable.
d) Only 0.9 mm (0.035 inch) diameter ER70S-2, ER70S-3, or ER70S-6
electrodes shall be used. Regardless of how the process “feels” to the
welder, the following amperage values (Table A1.2-1) shall be used:
3mm (1/8”)<
_ t < 6mm (¼”) 17-19 130 200 ipm
6mm (¼”)<
_ t < 10mm (3/8”) 18-20 140 220 ipm
Notes: 1) Measurement of wire feed speed is more accurate than relying on ammeters.
2) Voltage shall be measured at the wire feeder to the work. Use a constant potential power source.
3) Adjust travel speeds so that each pass is 5mm (3/16-inch) maximum thickness.
4) Maintain 10mm (3/8-inch) to 13mm (½-inch) electrode stickout.
incomplete fusion, and porosity shall not exceed 5mm (3/16 inch) in the
75mm (3 inch) long fillet weld.
c) Retests:
In the case where a welder fails to meet the requirements, an immediate
retest shall be permitted. The retest shall consist of two test welds of the
same type and position on which the welder failed. Both retest specimens
shall meet the original test requirements stated in (2) above for the welder
to pass on retest.
If a retest fails and the welder has not made any production welds, the
Principal will notify the welder’s supervisor that the welder needs further
training or help in adjusting his machine. No further attempts at production
welding by this welder with short-arc shall be made until the problem is
rectified and two successful retests are made.
If a retest fails in the case where a welder has completed some production
welding, all welds made by this welder since his last successful fillet weld
break test, shall be carefully and thoroughly re-inspected at no cost to the
Principal. If practicable, the re-inspection shall be done with a different NDE
method than that used on the original inspection (i.e., welds that have been
x-rayed shall be re-inspected by ultrasonics while welds that have been
ultrasonically inspected shall be x-rayed). In addition, all of the provisions of
the preceding paragraph shall apply.